After 2017 bond plan stalled, city paid for Miami Hills siding
The council backed up to $14 million in bonds for the 151-unit complex in 2017. A later owner got nearly $1 million in TIF for windows and siding, finished in 2024.
Older records: Published November 22, 2026. The main records behind this story run through August 2024.
In June 2017, the South Bend Common Council endorsed up to $14 million in bonds to rehabilitate Miami Hills, the 151-unit apartment complex at 3534 High Street on the city's south side. City records show that plan never went forward. Five years later, a new owner got a different deal: the city used tax increment financing to pay for new windows and siding, and the work was finished in 2024.
The newest city record on the project the paper found is the August 2024 approval of the finished work. It found no later city report on the owner's obligations under the agreement.
The 2017 plan
The 2017 request came from BLVD Capital LLC, the complex's owner at the time. Under Resolution 4646-17, adopted June 26, 2017, the council approved the city issuing economic development revenue bonds of up to $14 million and lending the money to the owner for the rehabilitation. The city's cover letter said the bonds were contingent on the owner winning state low-income housing tax credits. The resolution said the bonds would be paid only from the project and would not be a debt of the city, and that a bond ordinance would still be needed.
At a council committee hearing that day, owner Robert Budman said the complex was built in 1975, was about fully occupied with Section 8 tenants, had not had a substantial renovation since it was built, and that his company had spent $300,000 on improvements since buying it in 2014, according to the minutes. The committee sent the resolution to the full council with a favorable recommendation.
The paper found no later bond ordinance for Miami Hills in the city's posted records. On Nov. 12, 2018, after Sharon Banicki, who lives on Ford Street, told the council she believed the city had helped Miami Hills and that the promised cleanup had not happened, Council President Tim Scott said the council "approved a bond for them," and that "they never followed through on that bond," the minutes show. The record shows no response from BLVD Capital.
A new owner and a TIF deal
By late 2020, Infinity RE II had taken ownership, city staff told the Redevelopment Commission. On Feb. 10, 2022, the commission approved a development agreement with Miami Hills MF II LLC, using money from the South Side TIF district. Tax increment financing, or TIF, captures growth in property taxes inside a district for projects there. Staff said the city would replace exterior siding, fascia, soffits and windows at an estimated cost of $1 million.
At that meeting, Greg Jones, speaking for the owners, said they had spent $2.6 million on the property, done a full interior rehab and cleared more than 400 code violations, according to the minutes. Commissioners approved the agreement unanimously.
No bids, then a higher price
The Board of Public Works hired Forum Architects for $70,000 to design the work. When the board sought bids in June 2022, none came in. The board then turned to an open-market process. At that June meeting, board member Murray Miller asked why the project carried no minority- and women-owned business goals, the minutes show.
The lowest price came from H&H Renovations Inc. of the Atlanta area, which staff told the commission had an existing relationship with the ownership team. Its price, $1,584,305, was more than the $1 million the city had committed. In January and February 2023, the commission amended the agreement: the owner would pay the difference, $654,305, and the completion deadline moved to Dec. 31, 2023. In February 2023, staff said the owner had wired its share and had reported investing a little over $3.6 million in the property through Dec. 31, 2022.
The work finished later than the amended deadline. The city's checkbook shows three payments to H&H in 2024 totaling exactly $1,584,305, and the board approved the contractor's completion affidavit on Aug. 13, 2024. The checkbook also shows $55,125 paid to Forum Architects for the job.
That puts the city's own TIF share at about $985,000, or roughly $6,500 per apartment, counting the 151 units in the 2017 filings.
Source: South Bend Redevelopment Commission records and city checkbook
What's next
Miami Hills still draws debate at City Hall. In her 2027 budget priorities, filed June 22, 2026, District 5 Councilmember Sherry Bolden-Simpson wrote that the city should "phase out housing like Miami Hills and Beacon Heights" in favor of mixed-income housing. The record shows no response from the owner.
More stories about South Bend Board of Public WorksSouth Bend Redevelopment CommissionSouth Side TIF District
- Bill 17-36, Miami Hills bond approval, with Department of Community Investment letter (filed June 21, 2017)(opens in a new tab)
- Resolution 4646-17, approving proposed economic development revenue bonds (Miami Hills), June 26, 2017(opens in a new tab)
- Common Council Personnel and Finance Committee minutes, June 26, 2017(opens in a new tab)
- Common Council minutes, Nov. 12, 2018(opens in a new tab)
- Redevelopment Commission minutes, Dec. 10, 2020(opens in a new tab)
- Redevelopment Commission minutes, Feb. 10, 2022 (Miami Hills development agreement)(opens in a new tab)
- Development Agreement (Miami Hills), Redevelopment Commission packet, Feb. 10, 2022(opens in a new tab)
- Board of Public Works, professional services agreement, Forum Architects, Miami Hills Project 122-027 (March 22, 2022)(opens in a new tab)
- Board of Public Works minutes, June 14, 2022(opens in a new tab)
- First Amendment to Development Agreement (Miami Hills), Jan. 12, 2023(opens in a new tab)
- Redevelopment Commission minutes, Jan. 12, 2023(opens in a new tab)
- Redevelopment Commission minutes, Feb. 23, 2023 (Second Amendment)(opens in a new tab)
- Board of Public Works open market contract award, H&H Renovations, Miami Hills TIF Project 122-027 (Feb. 28, 2023)(opens in a new tab)
- Board of Public Works project completion affidavit, Miami Hills TIF Project 122-027 (Aug. 13, 2024)(opens in a new tab)
- City of South Bend checkbook: payments to H&H Renovation Inc. and Forum Architects LLC, 2022-2024, via the South Bend Transparency Portal(opens in a new tab)
- 2027 South Bend Common Council Budget Priorities (filed June 22, 2026)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines