City hires Burke for $10,000 South Bend Dam safety review
The city owns the dam and pays for its federal safety reports, but Notre Dame holds the hydropower exemption and files them with federal regulators.
The South Bend Paper
Development, money and daily life in Michiana
The city owns the dam and pays for its federal safety reports, but Notre Dame holds the hydropower exemption and files them with federal regulators.
City records say a state inspection rule for factory-built buildings, plus buried concrete and a damaged water line, raised the contract by $156,252.20.
After an ambulance-only sale drew no bids, the city moved to raze the building and expand Normain Park, and a resident has asked whether it can be saved.
The Nov. 24 change order covers steel, a water line, benches and anti-vandalism fencing, and brings the concrete trail contract to $5.32 million, still due May 1, 2027.
Materials filed for the board's Nov. 19 meeting also lay out a six-hour orientation for new members and a 2027 calendar with a training session every other month.
Also this Thanksgiving week: South Bend's public works board weighs buying 13 properties for $300,000, and county commissioners meet Tuesday.
Bill 94-26, up for first reading Monday, would hold such bills until the sponsor certifies the citations and legal fit, and require official city accounts for AI tools.
Leftover money from an expired West Washington tax district will pay for a master plan reaching from City Cemetery toward the Kroc Center.
A December 2024 sample from a well inside the park found vinyl chloride above a state cleanup goal, and regulators say no wells exist to show how far it extends.
The building renovation follows a rebuild of the park's outdoor courts, named for A. David Filer V, under a contract that grew to $1,792,951.07.
The Nov. 19 agenda covers the Common Council's October changes to attendance, quorum and member training, with two of the board's nine seats still listed as pending.
Park Board advisers say amenities floated for the riverside park could cut its tree canopy. The neighborhood plan adopted in September calls those ideas conceptual.
The owner who hauled more than 1,000 buckets of earth and mud from its basement by hand now asks to tear the brick building down.
Also this week: the county hearing on banning new hyperscale data centers, a Mishawaka annexation on Fir Road and Elkhart's vote on bigger Love Plaza loans.
Officials say the playground does not meet present-day park standards, and a new parking lot north of the zoo may still take some trees.
Cemetery Superintendent Cyneatha Milsaps told the Common Council the city buries about 250 people a year and needs a fifth heavy equipment operator.
The Board of Public Works again set its 'prime borrowing rate' at 2% for 2027, which under city code leaves single-family owners paying no interest over five years.
The first rewrite since 2019, on the Board of Public Works' Nov. 10 agenda, also stretches payment plans from three months to as long as 12.
City staff said two benches had been moved from their approved spots and two others had sat in the right-of-way without permits since 2022.
Engineers would replace the park's aging well-fed system with a line to New Carlisle's water. Shelter fees stay flat for 2027 except a new Anderson Trail shelter.
The Board of Public Works on Nov. 10 added a $34,250 land survey to first-phase design work, raising the engineering contract to $179,935.
James C. Trotter Jr., owner of the West Washington Street building since 2000, won a 6-0 vote as two council members recalled their own ties to it.
City records show rounds of quotes that drew no takers, a grant nearly lost and a rejected $395,000 price before the WPA-era building's repairs were finished Oct. 13.
The bidder promises to start a single-family home within a year. The vacant lot at 310 E. Calvert St. went up for sale at a nearby owner's request.
Also on the week's agendas: Mishawaka tax breaks, $1.3 million in county jail spending, Elkhart's Love Plaza loan and Microsoft's Toll Road sound wall.
The Venues, Parks & Arts department's self-reported 2025 numbers, filed Oct. 30, include a budget page whose listed sources don't add up to its printed total.
Cold air crossing a warmer Lake Michigan builds narrow snow bands, which is why South Bend averages 64.5 inches a winter and totals can swing within a few miles.
Abonmarche's $113,000 contract covers failing glass, masonry and mechanical systems at the 1963 glasshouse, with bids to go out by March 1 and no construction estimate yet.
The Board of Public Works approved a change order bringing Garmong's contract to $15,991,908.83, swapping asphalt courts for post-tension concrete.
The $6 million riverside venue has a $3 million state grant, poor soil under its site and about $2.5 million in construction costs still unfunded.
The Leighton Garage's fire standpipe failed over a major underground leak, and the Main/Wayne garage has no working elevators after a repair project was put on hold.
Owner-occupied rentals are allowed by right, existing absentee operators can be grandfathered and new ones need a zoning special exception.
Six of the 38 recommendations within city power remain under review, including housing-discrimination testing and blood-lead testing near Beck's Lake.
CommunityCounty records trace the building from company lodge to housing for Army officers, a corporate president's home and the offices of St. Joseph County's first park.
Bill 85-26, set for a final vote Monday, would add a tier for complexes of 20 to 50 units and make tenants responsible for calls they generate.
The splash pad and restroom contract has grown about $93,000 since the award, and the consultant says the only route to a more accessible corner runs through private property.