Anderson Trail County Park runs about $1 million over budget

Parks records give no opening date for the Granger park, and bond money set aside for snowmaking and fiber may be needed to finish it.

By South Bend Paper AI Desk · November 4, 2026 at 3:56 PM

Before St. Joseph County's newest park had a trail, a pond or a name, it had a list.

Parks staff submitted 22 possible names for the park going in on Anderson Road, according to the Parks Board's August 2025 meeting packet. They ran the alphabet from Anderson Oaks County Park to Whitetail Oaks County Park, with Glacier Flats, Twin Hollows, Meadowline, Legacy and Granger Vista in between.

The land sits at the northeast corner of Beech and Anderson roads in Granger. The county parks master plan for 2019-2023 describes it as "a 118-acre plot of land owned by the Parks Board" and says "future park plans have not yet been developed." The 2014-2018 master plan called the same 118 acres "currently undeveloped."

Anderson Trail County Park sits north of Anderson Road at Beech Road in Granger, in northeast St. Joseph County. Circles mark the park's approximate location.
Anderson Trail County Park sits north of Anderson Road at Beech Road in Granger, in northeast St. Joseph County. Circles mark the park's approximate location. South Bend Paper graphic; base map © OpenStreetMap contributors
The 118-acre Anderson Road property, outlined, at the northeast corner of Beech and Anderson roads, as shown in the county parks master plan for 2019-2023, before the park was designed.
The 118-acre Anderson Road property, outlined, at the northeast corner of Beech and Anderson roads, as shown in the county parks master plan for 2019-2023, before the park was designed. St. Joseph County Parks Five Year Master Plan 2019-2023

One entry was Catanzarite County Park. Larry Catanzarite is the Parks Board's president.

Staff voted on the suggestions, and Leslie Witkowski, then deputy director, presented the most popular at the Aug. 19, 2025, meeting. The board put the decision off "until additional board members are present to provide input," the minutes say.

Two months later, at the Oct. 21, 2025, meeting, members handed their votes to administrative manager Savannah Kish. According to the minutes, she reported that "with a vote of 5 to 1, Anderson Trail County Park was selected." The board made it official the same day. A groundbreaking ceremony was scheduled on the site for the next day, Oct. 22, the minutes say.

The park is being built with money from a bond of just over $6.6 million that the county parks department received for capital improvements, according to the department's 2025 annual report. The department manages, in that report's words, "more than 1,300 acres of publicly accessible green space."

Bids, ponds and a snowstorm

Getting the work under contract took two tries. Only one bid came in for the first bid package in August 2025; the board rejected it and re-advertised. At a special meeting Sept. 30, 2025, on the recommendation of engineering firm DLZ, the board awarded earthwork and paving to R&R Excavating for $2,630,876.43 and landscaping to Davey Resource Group for a base bid of $185,000.

Contracts were signed Oct. 14, 2025. The scope: site grading, trail development, road base, two large ponds and landscaping.

Then winter arrived. The December 2025 administrative report says R&R Excavating "is making great progress, although things came to a grinding halt after the big snowstorm over the Thanksgiving holiday." By then the south pond was dug and the north pond was about half done.

By spring the landscaping was moving. At the April 21, 2026, meeting, Clay Kusbuch of Davey Resource Group gave the board a landscaping update; the minutes record that "more than 200 bare-root trees have been planted." He also suggested an idea, according to the minutes: animal track imprints along the paved trail, like the ones his children enjoy at the River Ramble at St. Patrick's County Park.

The turn

The same spring brought the project's second bid package, the remaining work that includes a pavilion, a restroom building and a gatehouse. After bids were opened, on April 21 the board followed DLZ's recommendation and awarded the work to Brown & Brown General Contractors for $2,115,000.

Together, the three contract awards total $4,930,876.43. That figure covers contract awards only, not the full cost of the project.

Anderson Trail County Park contract awardsNominal dollars, one-time contract amounts as awarded by the Parks Board
$0$1M$2M$3MEarthwork and paving (R&R Excavating)$2.6MBuildings and site work (Brown & Brown)$2.1MLandscaping (Davey Resource Group)$185K

Source: St. Joseph County Parks Board minutes, Sept. 30, 2025, and April 21, 2026

Three weeks later, the May 12, 2026, administrative update laid out the problem. "Additional costs associated with the county-required passing lane, elevation changes, and the drainage swale necessitated by portions of the park being located within a former floodplain, along with generally elevated material costs, have increased the overall project cost," it said. "At this point, the Anderson Trail project is approximately $1 million over the original $4.9 million budgeted amount."

Months earlier, minutes from December 2025 had noted that bond money originally set aside for "park equipment, new signage, fiber connectivity to St. Patrick's County Park, and snowmaking equipment may be needed to complete planned improvements at Anderson Trail County Park," and that about $500,000 of those funds had already been committed to the project.

The park is also showing up in the operating budget. The 2026 budget proposal added a park leader position at $42,151 and a part-time maintenance position for Anderson Road, and marked up lines for fuel, tires and supplies as "Increased for Anderson Rd." In January 2026 the board reviewed a $114,215.86 equipment purchase for the park, including a three-quarter-ton truck with a snowplow.

Neighbors with a code

In August 2026 the board approved a memorandum of understanding, a written agreement between the parties, with Legacy Homes, developer of The Ranch Subdivision just north of the park. Residents of the gated community will get direct pedestrian access "through a locked gate and fencing to be installed by the developer at no cost to the County Parks Department," the minutes say.

There are conditions. Residents must buy an annual park pass and get the gate code only after confirming they paid. "The gate code will be changed annually," and a camera watches the gate.

That same meeting was the last for director Steve Slauson, who said it had been an honor to serve county residents "for more than 37 years," according to the minutes. The board named Witkowski director; Slauson retired Sept. 3.

What's left

The overall concept plan for the park, dated May 20, 2025, prepared for St. Joseph County Parks. Anderson Road runs along the bottom, and the two ponds are near the middle. The plan is a concept, and the finished park may differ.
The overall concept plan for the park, dated May 20, 2025, prepared for St. Joseph County Parks. Anderson Road runs along the bottom, and the two ponds are near the middle. The plan is a concept, and the finished park may differ. St. Joseph County Parks / DLZ

Witkowski's Oct. 14, 2026, update reads like a punch list. The pavilion's concrete pad is poured and its trusses are up. Restroom framing is underway. "Gatehouse framing was completed, and roof trusses were set." Light pole foundations, drainage and storm sewer work are done. The first contract's share of the one-mile loop trail was finished in June, and the landscaping contract is about 85 percent complete.

"Both ponds have been stocked with fish which included Bluegill, Redear Sunfish and Largemouth Bass," the update says. "Channel Catfish are slated to be stocked in 2028."

The records reviewed do not give an opening date for the park.

The board next meets Nov. 17 at 9 a.m. at St. Patrick's County Park, in the White Barn's Harvest Room.

What did you think of this story?

More stories about Anderson Trail County ParkSt. Joseph County Parks

Sources
  1. St. Joseph County Parks Board packet, Sept. 16, 2025 (Aug. 19, 2025 minutes, 2026 budget, submitted park names)(opens in a new tab)
  2. St. Joseph County Parks Board packet, Oct. 21, 2025 (Sept. 30, 2025 special meeting minutes, bid awards)(opens in a new tab)
  3. St. Joseph County Parks Board packet, Nov. 18, 2025 (Oct. 21, 2025 minutes, naming vote)(opens in a new tab)
  4. St. Joseph County Parks Board packet, Dec. 16, 2025 (administrative report)(opens in a new tab)
  5. St. Joseph County Parks Board packet, Jan. 20, 2026 (Dec. 16, 2025 minutes, equipment purchase)(opens in a new tab)
  6. St. Joseph County Parks Board packet, May 19, 2026 (April 21, 2026 minutes, May 12 administrative update)(opens in a new tab)
  7. St. Joseph County Parks Board packet, June 16, 2026 (June 10 administrative update)(opens in a new tab)
  8. St. Joseph County Parks Board packet, July 21, 2026 (July 15 administrative update)(opens in a new tab)
  9. St. Joseph County Parks Board packet, Sept. 15, 2026 (Aug. 18, 2026 minutes)(opens in a new tab)
  10. St. Joseph County Parks Board packet, Oct. 20, 2026 (Sept. 15, 2026 minutes, Oct. 14 administrative update)(opens in a new tab)
  11. St. Joseph County Parks, 2025 State of the County Parks report(opens in a new tab)
  12. St. Joseph County Parks Five Year Master Plan 2019-2023, Anderson Road Property map(opens in a new tab)
  13. St. Joseph County Parks Master Plan 2014-2018, Anderson Road Property(opens in a new tab)
  14. New Anderson Road County Park Final Concept Plans, May 20, 2025(opens in a new tab)
  15. OpenStreetMap base map for locator graphic (© OpenStreetMap contributors)(opens in a new tab)

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.