Board approves $402,185 design for idle sewage plant digester
Primary Digester No. 1 has been out of service since its boiler failed about a decade ago. Construction bids are expected after design wraps up in mid-2027.
One of the three large digesters at South Bend's wastewater treatment plant has been out of service for about a decade, and the city has now hired an engineering firm to design the repair.
The Board of Public Works on Nov. 10 approved a $402,185 amendment to its contract with Donohue & Associates for final design plans, specifications and bidding for Primary Digester No. 1, according to the board clerk's letter to the firm. The amendment brings the contract to $482,985, up from the $80,800 the board approved March 24 for a preliminary study.
What digesters do
Digesters are tanks where the plant breaks down solids removed from sewage. Through aerobic and anaerobic digestion, those solids are turned into biosolids "rich in fertilizer and soil conditioning value," the city's 2013 Public Works annual report says. The anaerobic process also produces methane gas, which the plant cleans and burns in a boiler for fuel, flaring the excess, the report says.
How No. 1 went dark
A Nov. 2 memo from Assistant City Engineer Jacob Klosinski lays out the history. A 2011 study by Greeley and Hansen looked at upgrading all three digesters, but the Department of Public Works told the wastewater division to rebuild only Digester No. 2 and add a new gas-cleaning system. Both were commissioned in 2015.
Once No. 2 was running, Nos. 1 and 3 were taken out of service and cleaned. "As Digester No. 2 was recommissioned, the boiler for Primary Digester No. 1 failed, rendering Digester No. 1 as 'non-functional' and 'out of service' until it could be rehabilitated," the memo says. Digester No. 3 "was never restored to service after it was cleaned."
Both were put in "sedentary modes" and placed on the capital plan for repairs that would follow hydraulic improvements at the plant, the memo says. With the city's Long-Term Control Plan hydraulic projects close to being commissioned in late 2026, the plant is ready to resume digester work, according to the memo. The records do not say how the plant has handled its solids load with one of three digesters running, or what is planned for Digester No. 3.
What the design covers
Donohue's preliminary study, finished in September, recommended the scope, the amendment says. The design covers removing the digester's internal equipment and cover, repairing damaged concrete, and installing a new cover, mixers, pumps, piping, valves, a boiler, HVAC, lighting, electrical work and controls. It also covers gas-handling improvements, structural work for access to the digester building with fire-code upgrades, and a bid alternate to replace worn parts on the existing gas flare.
The schedule calls for 30% plans in January 2027, 90% plans in May and bid documents by June 23, 2027. The money comes from the city's sewage works capital account for treatment and disposal equipment, the agenda form says.
What construction may cost
The records do not yet give a construction estimate. Donohue is to deliver its first opinion of probable construction cost with the 30% plans in January, and update it at each later stage.
For comparison, the 2013–2016 rebuild of Digester No. 2 and the new gas-cleaning system, which included new mixers, piping, pumps, a boiler and building improvements, cost $5,930,037 at completion, according to the project completion affidavit the board approved in September 2016. That was a decade ago, and the records do not say how the new project's cost will compare.
More stories about South Bend Board of Public WorksSouth Bend Long Term Control PlanSouth Bend Wastewater Treatment Plant
- Amendment No. 1 to PSA, Wastewater Treatment Plant Digester No. 1, Donohue & Associates, with Nov. 2, 2026 engineering memo and fee breakdown (BPW, Nov. 10, 2026)(opens in a new tab)
- Professional Services Agreement, WWTP Digester No. 1 preliminary design, Donohue & Associates (BPW, March 24, 2026)(opens in a new tab)
- Board of Public Works minutes, March 24, 2026(opens in a new tab)
- 2013 Public Works Annual Report, City of South Bend(opens in a new tab)
- Project Completion Affidavit, WWTP Digester No. 2 Upgrade and Digester Gas Cleaning, Project 111-029, Grand River Construction (Sept. 13, 2016)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.