Chocolate factory, dinosaur museum draw full $2.7M city loan

The city's abatement report counts 33 of 54 promised retained jobs at the U.S. 20 complex, and posted records don't show whether the loan was forgiven.

By South Bend Paper AI Desk · November 7, 2026 at 9:03 PM

Older records: Published November 7, 2026. The main records behind this story run through October 23, 2025.

City checkbook records show South Bend paid the full $2.7 million it authorized in 2022 as a forgivable loan for the South Bend Chocolate Company's new factory and the Indiana Dinosaur Museum. The money went out from January 2023 to March 2024 and covered fossil skeletons, signs, candy-making equipment, brickwork and flooring.

The complex at U.S. 20 and the U.S. 31 Bypass on the city's far west side opened in 2024. It was three years behind the schedule in its original tax abatement and missed the completion deadline in its first city development agreement. In the city's latest annual abatement report, the company is listed as "substantially in compliance," with fewer retained jobs than it promised.

Three kinds of help

The city backed the project, led by South Bend Chocolate Company president Mark Tarner, in three ways:

Land and infrastructure. The Redevelopment Commission sold the site to Tarner's SBCC Development Corp. at what a 2019 development agreement calls a "discounted purchase price," under a 2017 purchase agreement. The documents don't give the price. In December 2019, the commission agreed to spend up to $1.4 million in tax increment financing (TIF) money on sewer and water lines to the site, including up to $500,000 for sewer connection fees. TIF is property tax growth in a district that the city sets aside for development. That same month, the Board of Public Works approved a $446,148 sewer and water main extension agreement for the factory and museum.

In return, the developer agreed to spend at least $7.4 million, start construction by July 1, 2020, and finish by Dec. 31, 2023. If it missed those terms, it would owe back 150% of the infrastructure money the commission had spent.

A tax abatement. In late 2019, the Common Council approved a six-year property tax break. Under the memorandum of agreement, the company committed to spending at least $6.3 million on the factory and museum buildings, keeping 54 full-time jobs and adding 70 within five years.

The forgivable loan. In October 2022, the Redevelopment Commission voted unanimously to back a loan of up to $2.7 million from River West TIF revenue, followed by approvals from the Economic Development Commission and the council. In a letter to the council, the Department of Community Investment said the loan "would be forgivable provided the Indiana Dinosaur Museum and South Bend Chocolate Factory open by June, 30, 2024 and private investment exceeds $15.4 million." Under the loan agreement the commission approved, each part of the loan is forgiven once the developer files an affidavit of completion and the city accepts it. At the same meeting, the commission extended the development agreement's completion deadline from Dec. 31, 2023, to June 30, 2024. City staff told the commission that if that date wasn't met, "payments would begin on the loan after that date."

What the records show since

The money. Checkbook records show $620,830 paid to South Bend Chocolate Co. in January 2023, for items including $307,900 for Triebold Paleontology. Another $2,079,170 went to Indiana Dinosaur Museum Inc. in 81 payments through March 26, 2024. Together they equal the $2.7 million ceiling. All of the payments were recorded under the Department of Community Investment.

Delays. The abatement's construction window expired Nov. 25, 2022. In January 2024, the council voted 9-0 to extend it through Dec. 31, 2024, and to move the break to two related companies, SBCC RE LLC and SBCC Development Corp. A city letter said the project "could not be completed by the end of the original designation period because of the global pandemic, among other issues." At that meeting, according to the minutes, a city official said the private investment had grown from a 2019 estimate of $6 million to $17 million, and Tarner put it at "roughly $17 million."

Opening. At a May 13, 2024, county Hotel-Motel Tax Board meeting held at the museum, the tourism bureau reported that the museum would open in mid-June. The city's 2024 abatement report, filed in June 2025, gives July 12, 2024, as the actual completion date.

Jobs and spending. Here is how that report compares the company's promises with what it reported:

Measure Promised Reported
Real property spending $6,361,010 $5,892,279
Retained full-time jobs 54 33
New full-time jobs 70 65
Completion June 30, 2021 July 12, 2024

The report rates the abatement a 2, "substantially in compliance." That score covers companies that missed one or more goals when the city finds other factors slowed progress. The report notes that because abatements apply only to what is actually built, lower spending "automatically" reduces the tax break.

What the records don't show

The South Bend Paper did not find an affidavit of completion for the loan in the city's posted records. It also did not find a city action accepting one, a finding on whether the $15.4 million investment threshold was met, or any record of loan payments starting. The investment figures in the record come from statements at the January 2024 council meeting, not from an audited accounting. The development agreement required the developer to file yearly reports on investment and jobs, and those reports are not in the posted records either.

Still on the city's agenda

The city is still spending on the site's traffic. In October 2025, the Redevelopment Commission approved $30,000 for more study of a possible traffic signal at U.S. 20 and Olive Road, across from the museum entrance. An assistant city engineer said it would use a traffic count taken "following the museum's opening." She told commissioners that the Indiana Department of Transportation was concerned about traffic flow, while the city was concerned with safety. Earlier traffic study requests for the same intersection came before the commission in 2023 and 2024.

What did you think of this story?

More stories about South Bend Redevelopment Commission

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.