City hires Burke for $10,000 South Bend Dam safety review

The city owns the dam and pays for its federal safety reports, but Notre Dame holds the hydropower exemption and files them with federal regulators.

By South Bend Paper AI Desk · November 28, 2026 at 6:49 PM

The South Bend Board of Public Works on Nov. 24 approved an agreement of up to $10,000 with Christopher B. Burke Engineering for this year's federal safety checks on the South Bend Dam, the low dam across the St. Joseph River downtown.

The work is billed by the hour. The first pieces are due Dec. 31: an annual inspection, a certification that the dam's gates work and a review of the dam's exemption from writing an emergency action plan. A yearly safety report and updates to the dam's monitoring plan are due April 1, 2027, according to the agreement.

The contract also shows how responsibility for the dam is split. The city owns it. The University of Notre Dame holds the federal hydropower exemption for it. And Burke, paid by the city, sends its paperwork to Notre Dame to file with federal regulators.

Who owns, who files

The dam is regulated by the Federal Energy Regulatory Commission (FERC), which oversees hydropower projects. The agreement describes it as "a low-head, run-of-the-river dam on the St. Joseph River near downtown South Bend," under License No. 7569. FERC requires a Dam Safety Surveillance and Monitoring Report every year "to review instrumentation and monitoring data to determine if potential failure modes are developing," the agreement says.

A 2016 Board of Public Works resolution states that "the City is the owner of the South Bend Dam." The city had held a FERC exemption for a small hydropower plant there since 1984, the resolution says, but a 2013 study found it was "not financially feasible" for the city to build and run one. In Resolution 62-2016, adopted Dec. 13, 2016, the board agreed to "relinquish the FERC exemption to the University of Notre Dame," tied to a ground lease between the university and the city's Board of Parks Commissioners dated Dec. 12, 2016.

A 2015 board resolution said a hydroelectric plant "would help Notre Dame mitigate its campus carbon footprint, increase electric reliability, address utility cost uncertainties, and provide academic research opportunities."

The new agreement calls Notre Dame the "license exemption holder." Burke's report "will not include the hydroelectric facility." The agreement says Notre Dame or its consultants are expected to file Burke's report with FERC and to prepare the report covering the hydroelectric plant themselves. Burke will also send the gate certificate and the emergency-plan letter to Notre Dame or its consultants for submission to FERC.

What the inspection covers

A Burke professional engineer will look over "safely-accessible portions of the dam." The agreement notes that because the dam sits in the river channel, "much of the dam and its appurtenances are not readily accessible for visual observation." Burke will watch city staff operate the three East Race gates for the gate certificate. The report will also rely on quarterly inspections and readings from two water-level gauges along the East Race that the city provides.

The emergency action plan review rests on an earlier finding that "no reasonably foreseeable emergency at the dam would endanger life, health, or property." Burke's job is to check whether conditions upstream or downstream have changed in ways that could affect that finding. The review will use only "publicly-available aerial photography and observations at the site," the agreement says, and "specifically excludes dam failure flood inundation mapping." Burke will also update the emergency contact list.

The agreement's schedule lists a "2024 DSSMR Report" due April 1, 2027. Its scope of work describes that report as the 2026 report, covering the 2026 calendar year.

What it has cost

Burke has done this work for several years. The board approved a $5,000 agreement for the 2020 report in December 2019, $8,500 for each of the 2021 and 2022 reports, $9,500 for 2024 and now $10,000, according to the agreements and board minutes. The 2024 agreement also included updates to a public safety plan, which the new agreement does not list.

City checkbook records show 37 payments to Burke described as dam work from June 2020 through September 2026, totaling about $70,600. The largest came in 2020 and 2021, when the board also approved amendments for extra work FERC asked for, including a survey of the river bottom downstream. Payments since 2022 have run from about $1,200 to $5,100 a year. The figures are not adjusted for inflation.

The new contract is paid from the city's stormwater professional services account. City Engineer Abigail Magas is the city's designated representative on the agreement.

What did you think of this story?

More stories about South Bend Board of Public WorksUniversity of Notre Dame

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.