City hires designer for Potawatomi Conservatory overhaul
Abonmarche's $113,000 contract covers failing glass, masonry and mechanical systems at the 1963 glasshouse, with bids to go out by March 1 and no construction estimate yet.
South Bend has hired an engineering firm to design repairs to the Potawatomi Conservatory, the 1963 glasshouse in Potawatomi Park whose overhead glass, masonry and mechanical systems city records describe as deteriorating.
The Board of Public Works approved a $113,000 contract with Abonmarche Consultants on Oct. 13 for architectural and engineering design, bidding and construction oversight. The money comes from River East tax increment financing, or TIF, which is property tax growth in a redevelopment district that the city sets aside for projects there.
The contract's schedule calls for bid documents to be advertised by March 1, 2027. How much the repairs themselves will cost is not yet known: the records show no construction estimate, and producing one is part of Abonmarche's job.
What staff say is wrong
In a request to the Redevelopment Commission for its Oct. 8 meeting, Patrick Sherman, the city's director of project management, asked for $200,000 from the River East district for design work "for studying and renovating the inadequate mechanical and other systems in the building."
The conservatory "was originally constructed in 1963, with additions completed in 1967 and 1973," Sherman wrote. It was "designed by the renowned conservatory firm Lord & Burnham and supported by local philanthropist Ella Morris." The plans will cover the building's mechanical, plumbing, electrical and glazing systems and "long-term structural needs," he wrote, with "a local engineering firm and a Lord & Burnham specialist."
A signed copy of the request is filed with that meeting's records. The commission's minutes for the meeting were not among the records available. The request does not say what the $87,000 beyond Abonmarche's contract would pay for.
The contract's scope says the roughly 12,850-square-foot facility "shows signs of deterioration of both the exterior shell and the interior structure, along with an antiquated mechanical system." It draws on a needs assessment completed in April 2026 by Montgomery Smith Inc., whose James Smith will consult on the design for up to $5,000, plus earlier studies by American Structurepoint in 2024 and Kil Architecture & M/E Designs in 2017.
The primary items listed are:
- repairs to the overhead glass structure and code-compliant safety glass
- tuckpointing and waterproofing of the exterior masonry
- upgrades to venting equipment
- mechanical system upgrades
- mechanical and electrical controls
A second tier includes shading, circulation fans, a greenhouse climate-control system, new floor tile and substructure in the Muessel-Ellison building, electrical distribution, repairs to steel column bases, sidewall glass and brick knee walls, and replacing missing insect screens. All of these are to be ranked with the city so the first phase includes "as many items as feasible within budget," the scope says.
Left for a future phase are new walkways and planting beds, heated soil beds, light-reducing glass for the first three bays of the Ella Morris Conservatory, a return to the original street-facing entrance, a fog system for cooling and new lighting.
Earlier repairs
This is not the first round of fixes. In 2006, the city announced a $52,000 grant from local trusts for repairs to the Ella Morris and Muessel-Ellison conservatories and the Potawatomi greenhouses. A Lord & Burnham specialist had put those restorations at $50,000 to $70,000, covering broken glass, roof vent motors and controls, masonry and a boiler room fan, according to the mayor's office's announcement.
This year the board closed out a $151,812 roof replacement by Slatile Roofing and Sheet Metal Co., completed in March. A city parks report lists it as roof repair on the growing wing.
The River Park Neighborhood Plan, which the Common Council adopted Sept. 28, says "stabilization of the existing buildings should be a priority to ensure the long-term functionality of the facility." It also suggests a master plan to tie the conservatories into the rest of Potawatomi Park and add garden and event space.
What's next
Under Abonmarche's schedule, base drawings were due Oct. 27, schematic design Nov. 24, design development Jan. 5 and construction documents Feb. 16, each followed by a two-week city review.
More stories about Abonmarche ConsultantsPotawatomi Conservatory
- RDC agenda item 5A1, Budget Request (Potawatomi Conservatory), Oct. 8, 2026(opens in a new tab)
- Redevelopment Commission agenda and packet, Oct. 8, 2026(opens in a new tab)
- PSA, Potawatomi Conservatory Improvements, Abonmarche (Oct. 13, 2026)(opens in a new tab)
- BPW minutes, Oct. 13, 2026(opens in a new tab)
- Resolution adopting the River Park Neighborhood Plan (Sept. 28, 2026)(opens in a new tab)
- Change Order No. 1 and PCA, Potawatomi Conservatory roof, Slatile Roofing (July 14, 2026)(opens in a new tab)
- 2025 VPA Annual Report(opens in a new tab)
- City of South Bend news release, Grant for Conservatories and Greenhouses Announced (Nov. 27, 2006)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.