Sunday, November 29, 2026Sun, Nov 29

The South Bend Paper

Development, money and daily life in Michiana

Development

City moves toward demolishing fire-damaged Lafayette Building

Staff estimate a full rehab of the city-owned downtown building would top $20 million after the June fire, and the insurer paid $3.6 million.

By South Bend Paper AI Desk · November 7, 2026 at 10:51 PM

Updated November 7, 2026 at 10:51 PM: Correction: An earlier version called the Lafayette Building a landmark. City records describe it as historically significant but do not show a landmark designation.

South Bend is preparing to seek bids to tear down the Lafayette Building, the fire-damaged downtown building the city's Redevelopment Commission owns at 115 S. Lafayette Blvd. The commission has called it "an important and historically significant structure."

A request to advertise for demolition bids, Project No. 123-071, was on the Board of Public Works agenda for Oct. 27. The request form lists the funding as River West Development Area TIF, money from tax increment financing, in which property taxes from growth in a district are set aside for projects there. It gives no estimated cost. Minutes of that meeting were not yet posted in city records.

The request came after staff asked the Redevelopment Commission on Oct. 8 for authority to demolish the building "if ongoing redevelopment efforts do not result in a viable redevelopment opportunity." The signed copy of that agenda item in city records is marked approved; minutes of the meeting were not yet posted.

Before and after the fire

The building was in trouble before the June 8 fire. According to the Oct. 8 staff report from Joseph Molnar, deputy director of community investment, the commission had a purchase agreement and development agreement with a private developer. In late 2024 and early 2025, engineers opened walls and floors and found that key structural parts "were either inadequate under current building codes, had been removed during past renovations, or were damaged in the 1940 fire and never properly replaced."

The fix would have meant rebuilding much of the building floor by floor, from the foundation through the fifth floor, the report says, and the cost estimate rose from about $8 million to $10 million to $12 million to $15 million. The developer chose not to go ahead, the sale did not close and the agreement was terminated. The report does not name the developer.

The June fire "consumed the majority of the roof structure, causing the skylight to collapse to the ground floor," the report says. Without the roof bracing them, parts of the fifth-floor masonry walls are at risk of collapse, and about 1 million gallons of water used on the fire soaked lower-floor wood framing. "Winter freeze-thaw cycles are expected to accelerate the deterioration of the masonry and further weaken the building," staff wrote.

A third-party engineering consultant put a "bare bones" rehab at about $11 million. Adding mechanical, electrical and plumbing systems, fire protection, an elevator and interior finishes "would then likely drive the total rehabilitation cost over $20M," the report says.

Insurance and the fire investigation

The cause of the fire remains under investigation by the State Fire Marshal, the report says. The city's insurer investigated the claim, including "the condition, maintenance, and security of the building prior to the fire," found coverage applied and paid $3,596,650. The money went into the Redevelopment Commission's general fund.

Staff told the commission they would first use money already set aside for the property and, if that runs short, the general fund, including the insurance money. In June, Molnar told commissioners about $750,000 had been set aside under the former development agreement and most of it remained, according to the minutes.

What happens next

Staff wrote that they will keep looking for a redevelopment partner and "remain engaged in discussions with potential local development partners." If they decide demolition is warranted, the report says, they will notify the commission and explain why; any sale or development deal would go to the commission for a vote.

The building has been under emergency orders since the fire. The Board of Public Works declared an emergency June 9, which lets the city contract for work without advertising if it invites at least two bids. On June 11 the Redevelopment Commission unanimously passed Resolution No. 3673, telling staff to "seek to preserve or stabilize the structure" where practical but allowing them to clear it to address "an imminent threat to public health or safety."

At that June meeting, Molnar described the building as "a rare late-1800s structure with a significant atrium and deep community and civil rights significance," the minutes say. Firefighters, 75 to 90 of them by the minutes' count, brought the fire under control within hours, and no injuries were reported.

What did you think of this story?

More stories about Lafayette BuildingSouth Bend Redevelopment Commission

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.