City paid sewer contractor $799,524 to settle 2018 contract fight
The city dropped a liquidated-damages claim in the 2022 deal with Inland Waters. Its next sewer-lining contract closed this year at 1.8% over the winning bid.
Older records: Published November 17, 2026. The main records behind this story run through March 2026.
Two entries in South Bend's checkbook on Feb. 28, 2023, stand out from the routine payments to sewer contractors. Both went to Inland Waters Pollution Control Inc., a Detroit firm, and both carry the same description: claim settlement. Together they total $799,524.27.
The money closed out a dispute over a sewer and manhole rehabilitation contract the city awarded in 2018, Board of Public Works records show.
The contract and the dispute
The board awarded Inland the job, Project No. 118-093, on Dec. 20, 2018, for $2,015,380.50, then added more segments on Feb. 7, 2019, for $1,108,896, according to the board's settlement resolution. The work relines aging sewer pipes and manholes from the inside. After four change orders, the contract stood at $3,105,965.60 in July 2021.
The resolution says the city and Inland disagreed over the final amount owed for the work, and settled to avoid the cost of prolonged litigation. The board adopted it, Resolution 59-2022, on Dec. 20, 2022, approving the $799,524.27 settlement and letting the city's Law Department negotiate the remaining terms.
Michael Schmidt, the board's attorney, told members the project dated to 2018 and had finished that year, according to the minutes. He said about $2 million had been in play and that the city had negotiated a settlement for an additional $100,000. In exchange, he said, the city gave up a claim for liquidated damages, a set daily penalty for late work, that would have exceeded $1 million. He called the deal "very favorable to the City over litigation," and said the Engineering Division and city lawyers agreed.
The minutes do not explain how those figures relate to the $799,524.27 payment, and the settlement agreement itself was not attached to the resolution in the city's archive. The record shows no statement of Inland's position beyond Schmidt's note that the company wanted the agreement finished before year's end for accounting purposes.
What the city paid
City checkbook entries for Inland total $3.18 million from 2019 through the 2023 settlement. The checkbook begins in 2019, so it may not capture every payment on a contract awarded in late 2018.
Source: City of South Bend checkbook via the South Bend Transparency Portal
The next contract
The city's next sewer and manhole rehabilitation job went to Visu-Sewer LLC of Pewaukee, Wis., awarded by the board on July 23, 2024, for $1,529,590.50.
That contract also changed along the way. Two change orders added $40,832.75 and $304,750, the second an increase of 19.41%. A final change order on Feb. 10, 2026, cut $317,697.82, citing work dropped near Benedict Avenue and on Illinois Street, which was already lined, and added custom liners on Scott and Marine streets. The final cost was $1,557,475.43, or 1.82% above the original award.
City checkbook payments to Visu-Sewer, made from 2025 through March 2026, match that final amount to the cent.
More stories about South Bend Board of Public Works
- City of South Bend Checkbook Explorer (South Bend Transparency Portal): payments to Inland Waters Pollution Control and Visu-Sewer, 2019-2026(opens in a new tab)
- City of South Bend finances dashboard (source of the checkbook)(opens in a new tab)
- Board of Public Works Resolution No. 59-2022, approving settlement agreement with Inland Waters Pollution Control on Project 118-093 (Dec. 20, 2022)(opens in a new tab)
- Board of Public Works minutes, Dec. 20, 2022(opens in a new tab)
- Change Order No. 4, Sewer & Manhole Rehabilitation, Project 118-093, Inland Water Pollution Control (July 27, 2021)(opens in a new tab)
- Award Bid, 2024 Sewer and Manhole Rehabilitation, Project 122-019, Visu-Sewer LLC (July 23, 2024)(opens in a new tab)
- Change Order No. 1, Sewer and Manhole Rehabilitation, Project 122-019 (May 27, 2025)(opens in a new tab)
- Change Order No. 2, Sewer and Manhole Rehabilitation, Project 122-019, Visu-Sewer (June 10, 2025)(opens in a new tab)
- Change Order No. 3 (Final) and Project Completion Affidavit, Sewer and Manhole Rehab, Project 122-019, Visu-Sewer (Feb. 10, 2026)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.