City picks CMTA for City Hall heating and cooling deal via Sourcewell
The city used a national cooperative contract instead of its own request for proposals. No price is set yet; a final agreement must return to the Board of Public Works.
South Bend has chosen CMTA Inc. to develop an energy-savings project for City Hall's heating and cooling system, and it did so without issuing its own request for proposals.
The Board of Public Works approved the selection Oct. 27 on a motion by Vice President Joseph Molnar, seconded by Abigail Magas, according to the board's minutes, approved Nov. 10. The city will hire CMTA through Sourcewell contract #071624-CMA, a cooperative purchasing agreement, according to a memo from project engineer Rolf Seh. The work will be paid for with local income tax economic development money, the city's agenda form says.
No dollar amount is attached yet. Seh's memo asks the board to let the Department of Public Works negotiate a final agreement with CMTA "to develop the guaranteed energy savings project scope," and says that agreement will come back to the board for approval.
How the deal works
A guaranteed energy savings contract, or GESC, is a state-authorized arrangement in which a company designs and installs energy upgrades and guarantees a level of yearly utility savings. If savings fall short, the company pays the city the difference. Seh's memo cites Indiana Code 36-1-12.5, the state law that governs these contracts.
The selection letter in the board file says this first step covers development services only: facility assessments and energy audits, a full GESC proposal, design and engineering of the energy-saving measures, bid-ready documents and coordination of competitive bidding for the work. "A separate agreement would be required to proceed with construction or implementation," the letter says.
Why there was no city request for proposals
At the board's Oct. 22 agenda review, board attorney Michael Schmidt said such contracts would typically go out for proposals "as is consistent with state law," the minutes say. This time the city is using Sourcewell, which the minutes describe as "an organization that solicits and awards competitive contracts on behalf of participating agencies." CMTA answered Sourcewell's public solicitation for GESC providers.
Schmidt said that because the Sourcewell contract was publicly let for GESC providers, it meets the usual statutory requirements under Indiana law, according to the minutes. He also said CMTA had committed that if its price comes in above budget, the city would owe nothing and could reject it.
Seh's memo says Sourcewell "competitively solicits and awards contracts" and picked CMTA as a qualified provider of energy services. It also says CMTA has agreed to take part in the city's minority- and women-owned business program.
The city took a different route with CMTA last time. For solar at the Central Fire Station and the MLK Dream Center, the city issued its own request for qualifications in January 2025. CMTA, Veregy and Ameresco responded, according to the Jan. 28, 2025, board minutes. A city review committee interviewed two of them and chose CMTA, according to a March 11, 2025, memo from project engineer Lidya Abreha.
What CMTA's first city deal guarantees
The board approved those two solar contracts March 24, 2026: $391,710 for the fire station and $369,318 for the MLK Dream Center, according to the contract files. Each adds solar panels and battery storage.
CMTA guarantees $3,053 in utility savings at the fire station and $5,865 at the MLK Dream Center in the first year, rising 3% a year over a 20-year term, according to the contracts' savings schedules. Added up, the guaranteed savings come to $73,242 at the fire station and $140,697 at the MLK center, about $214,000 in all against $761,028 in contract prices. The paper totaled those figures from the contracts' yearly tables. They are nominal dollars, not adjusted for inflation.
Source: CMTA guaranteed energy savings contracts, Board of Public Works, March 24, 2026
The contracts also have the city pay CMTA a separate yearly fee to measure and verify the savings. At the fire station it starts at $1,000 in 2027 and rises to $1,702 by 2045, about $25,000 over the term. If the city cancels that service, the contracts say, the savings are no longer guaranteed. The contracts also have the city apply for federal solar tax credits, with CMTA supplying the paperwork. They do not say how much those credits would be worth.
The City Hall project is different work, heating and cooling rather than solar, and the records do not yet show its scope, price or guaranteed savings. The paper's earlier story on Veregy's sewage-plant solar contract is here.
More stories about CMTA Inc.SourcewellSouth Bend Board of Public WorksSouth Bend City Hall
- GESC – City Hall HVAC Improvements, Project No. 126-055 – CMTA Inc. (Board of Public Works, Oct. 27, 2026): clerk letter, engineering memo, Sourcewell selection letter, agenda form(opens in a new tab)
- Board of Public Works minutes, Oct. 22 agenda review and Oct. 27, 2026 regular meeting (approved Nov. 10)(opens in a new tab)
- Board of Public Works agenda review session agenda, Oct. 22, 2026(opens in a new tab)
- GESC – Central Fire Station Solar, Project No. 125-008A – CMTA (March 24, 2026)(opens in a new tab)
- GESC – MLK Dream Center Solar, Project No. 125-008B – CMTA (March 24, 2026)(opens in a new tab)
- Accept Qualifications – SBFD & MLK Solar GESC – CMTA (March 11, 2025)(opens in a new tab)
- Board of Public Works minutes, Jan. 28, 2025 (opening of qualifications)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.