City rebids Nexus Center elevator ahead of year-end deadline
The south side community center met the terms of its 2021 city deal. A $300,000 elevator promised in 2025 drew no bids and was redesigned, with a Dec. 31 deadline.
The city has put the Nexus Center's new elevator out to bid a second time, about 11 weeks before the date its development agreement sets for finishing the project.
The Board of Public Works approved a new request to advertise for bids on Oct. 13, 2026. The first round, opened Dec. 9, 2025, drew no bids, according to board minutes. In between, the city paid its engineer to move the elevator shaft from inside the building to the outside, which the April 2026 amendment says was done "to reduce costs."
The elevator is the second phase of city help for the center at 3607 S. Main St., the former Praxair building that Pastor David Buggs and Dr. LaRissa Chism Buggs turned into a community and health center. Records show the first phase did what it promised.
The 2021 deal
In August 2021, the Redevelopment Commission agreed to spend up to $300,000 in tax increment financing on public improvements at the building. TIF is money from the growth in property taxes inside a district, which the commission can spend on projects there. The Nexus Center LLC, in turn, promised to invest at least $1 million and finish within 36 months.
At that meeting, David Buggs told commissioners he and his wife had bought the vacant building and invested more than $200,000 in it during the pandemic, and described a 37,000-square-foot center, according to the minutes. LaRissa Buggs, a forensic physician, said it would have a wellness theme, with a charity clinic in the first of four phases.
In September 2022, the commission raised its share to $525,000 as the owners raised their investment to $1.6 million. City contractors replaced the roof for a final cost of $196,981 and completed site and building work for $340,524, according to project completion affidavits filed in October 2023 and February 2024. A second amendment in October 2023 let the city's contractor cover a $36,705 overage, which the minutes say the Nexus Center would reimburse.
At that meeting, Erik Glavich of the Department of Community Investment told the commission the owners had exceeded their financial requirements. The 2025 agreement states that the Nexus Center met all of its 2021 obligations on time.
A tax break for the last phase
In January 2024, the Common Council confirmed a nine-year property tax abatement for the final phase, which a city report said would add a commercial kitchen, great hall, auditorium and outdoor amphitheater to the roughly 20,000-square-foot building. The report put that phase at $800,000 and the full project at more than $2.4 million.
The city estimated the abatement at $102,180 in property taxes over nine years. The owners expected to create at least 10 full-time jobs averaging $20 an hour; the report said about 20 people, mostly with Goodwill, already worked in the building. Records reviewed for this story do not include a report yet on those jobs.
The elevator
In January 2025, the commission signed a second agreement with the Nexus Center and Cultivating Life Clinic, a nonprofit the couple runs from the building. The commission agreed to spend up to $300,000 in TIF to buy and install an elevator, which the agreement says the building lacks. The developers agreed to invest at least $745,000 and finish by Dec. 31, 2026.
If the developers miss that date or fall short on their investment, the agreement lets the commission recover 150% of the TIF it has spent as damages. The elevator itself is the city's to build: the commission agreed to complete it on a schedule set with the developers, which the agreement says may change because of unforeseen delays.
The agreement also makes the developers responsible for preparing the elevator's bid specifications and says any city spending on that work comes out of the $300,000. The city hired JQOL Global in May 2025 under a $48,000 contract covering the Nexus elevator and elevators at the Main and Wayne parking garage, then added $38,700 in April 2026 for the redesign and $20,000 in July 2026 for mechanical, electrical and plumbing design. Records reviewed do not show how those costs were charged.
The city records found run through the Oct. 13 approval. They do not show when the new bids are due, whether any came in, or whether the commission and developers have changed the schedule.
Other city money
The checkbook also shows an $800,000 payment to Nexus Center LLC in December 2024 from the Revolving Business Enterprise Fund, the city's low-interest business loan program, which borrowers repay. Records found do not show its terms. The center also received city grants of $3,350 in 2024 and $30,000 in 2025.
More stories about Nexus CenterSouth Bend Board of Public WorksSouth Bend Department of Community InvestmentSouth Bend Redevelopment Commission
- Development Agreement, Redevelopment Commission and The Nexus Center LLC (Aug. 12, 2021)(opens in a new tab)
- Redevelopment Commission minutes, Aug. 12, 2021(opens in a new tab)
- First Amendment to Development Agreement, Nexus Center, with agenda memo (Sept. 2022)(opens in a new tab)
- Redevelopment Commission minutes, Oct. 12, 2023 (Second Amendment)(opens in a new tab)
- Project Completion Affidavit, Nexus Center Roof Replacement, Project 121-064A, Slatile Roofing (Oct. 24, 2023)(opens in a new tab)
- Project Completion Affidavit, Nexus Center Site and Building Improvements, Project 121-064, R. Yoder Construction (Feb. 13, 2024)(opens in a new tab)
- Bill 23-65, declaratory resolution, DCI report and petition, Nexus Center LLC nine-year abatement (Dec. 2023)(opens in a new tab)
- Resolution 5064-24, confirming nine-year tax abatement for The Nexus Center LLC (Jan. 8, 2024)(opens in a new tab)
- Development Agreement, Redevelopment Commission, The Nexus Center LLC and Cultivating Life Clinic Inc. (signed, Jan. 23, 2025)(opens in a new tab)
- Professional Services Agreement, South Bend Elevator Projects 125-016 and 125-027, JQOL (Board of Public Works, May 13, 2025)(opens in a new tab)
- Board of Public Works minutes, Dec. 9, 2025 (Nexus Center elevator bid opening, no bids)(opens in a new tab)
- Amendment No. 1 to PSA, Nexus Center elevator redesign, JQOL (April 14, 2026)(opens in a new tab)
- Amendment No. 2 to PSA, Nexus Center elevator MEP design, JQOL (July 28, 2026)(opens in a new tab)
- Board of Public Works minutes, July 28, 2026(opens in a new tab)
- Request to Advertise and title sheet, Nexus Center Elevator, Project 125-016 (Oct. 13, 2026)(opens in a new tab)
- Board of Public Works minutes, Oct. 13, 2026(opens in a new tab)
- City of South Bend checkbook via the Transparency Portal: payments to Nexus Center LLC, 2024-2025(opens in a new tab)
- Department of Community Investment 2026 budget presentation (Revolving Business Enterprise Fund loans)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.