Sunday, November 29, 2026Sun, Nov 29

The South Bend Paper

Development, money and daily life in Michiana

Development

City report lists no jobs for Royal Adhesives tax break

The H.B. Fuller affiliate pledged to keep 201 jobs and add six for a 2021 equipment break. The city's latest report shows zeros and still rates it substantially compliant.

By South Bend Paper AI Desk · November 28, 2026 at 12:53 AM

Older records: Published November 28, 2026. The main records behind this story run through June 2025.

Updated November 28, 2026 at 12:53 AM: Updated Nov. 28 to describe Dan Buckenmeyer's title as the 2021 record gives it.

When Royal Adhesives & Sealants asked South Bend for a tax break in early 2021, it promised to keep 201 jobs and add six more. The city's most recent tax abatement report, filed in June 2025, lists zero for both.

The same report rates the company "substantially in compliance," the second-best of the city's six scores.

What was promised

Royal Adhesives, which a city staff report described as an affiliate of the global adhesive maker H.B. Fuller, petitioned in January 2021 for a five-year break on $1,380,875 in new equipment at a leased warehouse at 1915 N. Bendix Drive. The equipment would fill cylinders with adhesives and propellants for roofing and industrial customers, work the company said was being done by an outside filler in another state.

The company's petition said it had considered Houston before choosing South Bend, where it already makes the adhesive at its main plant at 2001 W. Washington St. Its Statement of Benefits listed 201 retained jobs at that plant, with a total annual payroll of $12,928,877, and six new full-time jobs averaging $23 an hour.

At the council's Feb. 8, 2021, meeting, Randy Greenlee, the company's operations director, said six jobs would come in the first phase and five more in a second phase, according to the minutes. Dan Buckenmeyer, listed in the 2021 records as the city's director of business development, told the council the company would pay about $16,000 in taxes on the equipment over five years while about $82,000 would be abated. The council confirmed the break Feb. 22, 2021, in Resolution 4886-21.

What the reports show

The city tracks each break through a yearly form, the CF-1, on which companies report what they spent and how many people they employ.

  • The 2022 report lists the project as not started, though it also gives a completion date of July 7, 2021. It leaves the actual-jobs columns blank and rates the break in full compliance.
  • The 2023 report, filed with the council in September 2024, again leaves the actual-jobs columns blank and lowers the rating to substantially in compliance.
  • The 2024 report lists 0 retained jobs and 0 new jobs against the 201 and 6 promised, and keeps the substantially-in-compliance rating.

All three reports list the equipment's actual cost as $1,380,875, the same figure as the estimate.

The city's key says a "substantially in compliance" score can mean a company missed one or more goals but the project is relatively new, met goals earlier, or gave an explanation that still applies. The reports do not say which applies to Royal Adhesives, and the paper found no council action or company statement in the record explaining the zeros.

The 2024 report is the newest the paper found; it covers abatements active through Dec. 31, 2024, and a 2025 report has not been posted. The break's schedule runs through 2027.

What did you think of this story?

More stories about South Bend Common CouncilSouth Bend Department of Community Investment

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.