City's Black & Veatch payments hit $871,000 as PFAS work grows
About half of what South Bend has paid the engineering firm in 2026 is for designing treatment to pull 'forever chemicals' out of North Station water.
South Bend has paid engineering firm Black & Veatch $871,460 so far this year, more than in any full year since at least 2019, and about half of it is for work on removing PFAS, the so-called "forever chemicals," from the city's drinking water.
City checkbook records show the payments, all through the Department of Public Works, ran between $133,000 and $359,000 a year from 2019 through 2023. They rose to $544,351 in 2024, $694,852 in 2025 and $871,460 through Sept. 29 of this year.
Payments labeled for PFAS work did not appear in the checkbook until September 2024. Since then they total $823,074 over 19 payments, including $442,334 this year. The rest of the firm's 2026 payments went to other water and wastewater engineering jobs, labeled in the checkbook as lift station measurement, "DAF building improvements" and water system modeling and calibration.
Source: City of South Bend checkbook via the South Bend Transparency Portal
Why the city is paying
The Environmental Protection Agency set enforceable limits for six PFAS chemicals in April 2024, including 4 parts per trillion for PFOA and PFOS, with compliance required by 2031, according to a September 2025 presentation by Public Works Director Eric Horvath to a Common Council committee.
Horvath told the committee that 12 of the city's 29 wells had PFAS above the EPA limit, the committee's minutes say. His presentation said one of the city's nine treatment plants, North Station, had treated water above the limits, and that the city had cut back or stopped using its worst wells and blends their water with other sources to stay below federal limits. Horvath told the committee the city's levels are similar to those in Elkhart and Mishawaka.
The contracts
The Board of Public Works hired Black & Veatch in May 2024 for a $99,863 study of treatment options, then added $126,574 in January 2025 for lab testing of treatment resins on water from the North and Pinhook plants.
At an April 2025 public hearing for a state loan, a Black & Veatch engineer told the board the firm and the city chose anion exchange, a resin process, for its cost, feasibility and removal of the PFAS found in South Bend's water. The plan then was to install four treatment tanks on a new upper level inside the existing North plant, avoiding new outside construction, at a budget of a $12 million state loan plus $3.43 million in city capital money, the minutes say.
In July 2025 the board approved a $1,368,887 contract for Black & Veatch to design the work. Board member Gary Gilot said the choice of method surprised him and that he preferred granular activated carbon, which also removes other contaminants such as TCE, according to the minutes. Board attorney Michael Schmidt said it was a strategic decision of the department. In April, the firm's engineer had said resin outperformed carbon on cost and removal in the study.
In June 2026 the board added $161,987 to redesign the project around a new building to house the tanks, pumps, a chemical room and a generator, bringing the design contract to $1,530,874. The amendment and the meeting minutes do not say why the plan changed.
The city's 2026 budget presentation listed $20 million for PFAS treatment at North Station. Horvath's 2025 presentation said the design work drew a $1.3 million federal infrastructure-law reimbursement, and he told the council that money from the city's class-action lawsuit against PFAS makers will go toward design and treatment. The proposed 2027 Public Works budget includes $2 million to design PFAS treatment at the Pinhook plant.
More stories about Black & Veatch CorporationEric HorvathNorth Water Treatment PlantSouth Bend Board of Public WorksSouth Bend Department of Public Works
- City of South Bend Checkbook Explorer (South Bend Transparency Portal): Black & Veatch Corporation payments, 2019-2026(opens in a new tab)
- City of South Bend finances dashboard (source of the checkbook)(opens in a new tab)
- PSA, PFAS Minimization Evaluation, Black & Veatch (Board of Public Works, May 28, 2024)(opens in a new tab)
- Amendment No. 1 to OEA, PFAS Follow-up Bench Testing, Project 124-056, Black & Veatch (Jan. 28, 2025)(opens in a new tab)
- Board of Public Works minutes, April 22, 2025 (PFAS public hearing)(opens in a new tab)
- PSA, Design of North Water Treatment Plant for PFAS Minimization, Black & Veatch (July 22, 2025)(opens in a new tab)
- Board of Public Works minutes, July 22, 2025(opens in a new tab)
- Amendment No. 1 to PSA, North WTP PFAS, Project 124-056, Black & Veatch (June 9, 2026)(opens in a new tab)
- Board of Public Works minutes, June 9, 2026(opens in a new tab)
- 'PFAS in South Bend Water,' Department of Public Works presentation to Common Council (Sept. 8, 2025)(opens in a new tab)
- Public Works & Property Vacation Committee minutes, Sept. 8, 2025(opens in a new tab)
- Public Works 2026 Budget Presentation (Sept. 3, 2025)(opens in a new tab)
- Public Works 2027 Budget Summary (Sept. 16, 2026)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.