City's Cascade TIF pledge more than doubles to $10.7 million
The developer's required private investment rose 69% to $65 million, and about $8 million of the city money is left for the project's second riverfront tower.
Older records: Published November 22, 2026. The main records behind this story run through April 27, 2026.
The most South Bend has agreed to spend on the Cascade development on the East Bank has more than doubled since 2018, from $5 million to $10.7 million, Redevelopment Commission records show.
The money is tax increment financing, or TIF: property tax growth inside a district, here the River East district, that the commission can spend on projects there. Under its agreement with developer Wharf Partners LLC, the commission pays for "Local Public Improvements" such as site preparation and infrastructure, while the developer builds the towers along the St. Joseph River just north of Seitz Park.
Source: South Bend Redevelopment Commission development agreement, amendments and minutes
The cap was $5 million in the February 2018 agreement and $5.237 million after an amendment that December. A second amendment in August 2025 raised it to $9.737 million, and a third, effective March 26, 2026, raised it to $10.737 million.
The developer's side grew more slowly. The minimum private investment rose from $38.5 million in 2018 to $65 million, an increase of 69%, while the city's cap rose 115%. That moved the city's pledge from about 13% of the required private investment to about 16.5%.
Where the money goes
City staff told the commission in August 2025 that it had spent just over $2.7 million on the first phase, a seven-story tower with an underground garage finished in December 2019, according to the minutes. That leaves roughly $8 million for the second phase, none of it spent as of March, the third amendment says.
That second building, at 312-318 E. Colfax Ave., must have at least seven stories, 20 housing units and 10,000 square feet of commercial space, plus an underground garage, under the 2026 project plan. Developer Frank Perri told the commission in 2025 he expected 20 to 25 condominiums. The 2026 staff memo puts the developer's planned spending on it at $40.5 million at least.
That memo said cost estimates in 2025 had come in higher than expected, and that the work had to be scheduled around the city's Colfax Avenue streetscape project.
The case for and against
Staff told the commission in 2025 that delays to the Seitz Park rebuild and Notre Dame's hydroelectric project, which used the second-phase site for staging, were outside the developer's control. They estimated the city's second-phase money would be paid back in property taxes in 12 to 15 years. Caleb Bauer, executive director of the Department of Community Investment, said the concrete building could pay taxes for close to 100 years, the minutes say.
Matt Barrett, identified in the minutes as a resident, raised concerns about the total investment per market-rate unit compared with the city's spending on affordable housing, and asked for more conditions in such agreements. The commission approved the 2025 amendment unanimously.
In April 2026 the Common Council also granted the second phase a six-year property tax abatement. Condos qualify only while the developer owns them and they are not occupied, the resolution says.
The newest records found for this story are from April 2026. They do not show whether construction began in June 2026, as the 2025 schedule planned.
More stories about CascadeRiver East TIF districtSeitz ParkSouth Bend Redevelopment CommissionWharf Partners LLC
- Third Amendment to Development Agreement, Wharf Partners LLC, with staff memo (effective March 26, 2026)(opens in a new tab)
- South Bend Redevelopment Commission minutes, Aug. 28, 2025 (Second Amendment, Cascade-Wharf Partners)(opens in a new tab)
- Development Agreement, Redevelopment Commission and Wharf Partners LLC (Feb. 22, 2018)(opens in a new tab)
- First Amendment to Development Agreement, Wharf Partners LLC (Dec. 13, 2018)(opens in a new tab)
- Resolution 5169-26 confirming six-year real property tax abatement for Wharf Partners LLC (April 27, 2026)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.