City's payments to Slatile Roofing jump nearly fivefold in 2025
Three big jobs, the Public Works service center, Central Fire Station and the downtown Center City Place building, drove $2.19 million in payments to the South Bend roofer.
South Bend paid Slatile Roofing and Sheet Metal Co. $2.19 million in 2025, nearly five times the $444,300 it paid the South Bend roofer in 2024, the city checkbook shows.
From 2019 through 2024 the city's payments to Slatile averaged about $539,000 a year, with a high of $1.02 million in 2023. The 2025 jump came almost entirely from three construction contracts the Board of Public Works awarded that year, plus an emergency repair on a historic downtown theater.
Source: City of South Bend checkbook via the South Bend Transparency Portal
The chart combines two spellings of the company's name in the checkbook, "Slatile Roofing & Sheet" and "Slatile Roofing & Sheet Metal." The checkbook runs through mid-October 2026; this year the city has paid Slatile $901,364 so far.
Where the 2025 money went
Public Works service center roof, $723,133. The board awarded the reroofing job to Slatile for $898,812 on Jan. 14, 2025. It drew two bids. A Kalamazoo company, Hoekstra Roofing, bid less, $627,700, but a city project engineer recommended rejecting it because Hoekstra "failed to submit a complete bid form, did not meet WBE goal requirement, and the responsible bidder ordinance requirement," according to her memo. The money came from the Motor Vehicle Highway fund and the sewer capital fund.
The job ran 103 days past its May 23, 2025, completion date. A final change order in January raised the contract to $906,032.70, covering unforeseen metal work and liquidated damages, the penalty a contract sets for late finishes. Assistant City Attorney Michael Schmidt told the board there were delays "that the company owned, so instead of the City seeking damages, there was a deduct on the overall pricing in that same amount (roughly $40,000)," the Jan. 13, 2026, minutes say. The minutes record no statement from the company.
Central Fire Station roof, $658,171. Slatile won this job the same day with a $696,812 bid, the lowest of the bids for the base work, from the Fire Department's capital fund. The city engineer's estimate for that work was $449,144, the bid tabulation shows.
Center City Place, $434,377. In July 2025 the board gave Slatile a $688,832 contract to replace the roof and windows and restore the facade at the long-vacant building at 225-229 S. Michigan St. Slatile was the only bidder. The building is privately owned: in February 2025 the Redevelopment Commission signed a development agreement promising Benjamin and Christina Miller up to $900,000 for the roof, historic facade, windows and utilities, in exchange for at least $5.1 million in private investment and a finished project by the end of 2028. The money comes from River West tax increment financing (TIF), property taxes on growth in a redevelopment district set aside for projects there.
Two change orders have since raised the contract to $799,486. The second, approved Oct. 13, added 127 days after a subcontractor delivered custom facade panels and medallions months late. The project engineer wrote that delay "was beyond Slatile's control."
State Theater, $196,812. The Redevelopment Commission closed on its purchase of the theater on May 1, 2025, and staff found damage during the review before the sale. The board ratified an emergency contract with Slatile a week later. Under the state's emergency rules, two roofers were asked for prices within 72 hours; the other one did not bid.
Smaller 2025 payments covered the Monroe Street arts building roof ($99,484 in 2025; final contract $341,632), a Potawatomi Zoo roof repair ($49,181) and brick work at Twyckenham Drive and Ewing Avenue ($25,420).
More stories about Central Fire StationSlatile Roofing and Sheet Metal Co.South Bend Board of Public WorksSouth Bend Redevelopment CommissionState Theater
- City of South Bend Checkbook Explorer (South Bend Transparency Portal): Slatile Roofing payments(opens in a new tab)
- City of South Bend finances dashboard (checkbook source)(opens in a new tab)
- Award Bid: PW Service Center Roofing Replacement, Project R124-032B, Slatile Roofing (Jan. 14, 2025)(opens in a new tab)
- Change Order No. 2 (Final), PW Service Center Roofing, Project R124-032B (Jan. 13, 2026)(opens in a new tab)
- Board of Public Works minutes, Jan. 13, 2026(opens in a new tab)
- Award Bid: SBFD Central Fire Station Roofing Replacement, Project R124-032A, Slatile Roofing (Jan. 14, 2025)(opens in a new tab)
- Opening of Bid and Award: Center City Place Rehabilitation, Project 125-022 (July 22, 2025)(opens in a new tab)
- Change Order No. 2: Center City Place Rehabilitation, Project 125-022 (Oct. 13, 2026)(opens in a new tab)
- Redevelopment Commission development agreement, former Center City Building, Benjamin and Christina Miller (Feb. 13, 2025)(opens in a new tab)
- Ratify Emergency Contract: State Theater Roof Repairs, Project 125-030 (May 8, 2025)(opens in a new tab)
- August 2026 DPW Report (Monroe Street Arts Building final contract)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.