City board renews licenses for 2 garages with known problems

The Leighton Garage's fire standpipe failed over a major underground leak, and the Main/Wayne garage has no working elevators after a repair project was put on hold.

By South Bend Paper AI Desk · November 6, 2026 at 3:03 PM

Updated November 12, 2026 at 9:48 AM: Updated Nov. 12: The Board of Public Works approved the licenses on Nov. 10, and the approval file gives the cause of the standpipe failure.

South Bend's Board of Public Works on Nov. 10 approved parking licenses for two city-owned downtown garages with known problems: at the Leighton Garage, 109 W. Jefferson Blvd., the fire protection standpipe and riser are out of service, and at the Main/Wayne garage, 119 W. Wayne St., there are no working elevators.

The board's approval letter to LAZ Parking Midwest LLC covers 109 W. Jefferson Blvd., 119 Wayne St., 126 N. Main St. and 1228 N. Eddy St., and asks the company to "coordinate with the Fire Department to address and complete the fire protection requirements outlined in the attached memo."

That memo gives the Fire Department's recommendation for the Leighton Garage as favorable "with the understanding that the fire protection standpipe & riser are out of service." It says the standpipe failed inspection and testing by a fire protection company "because of a major underground leak." The sprinkler system is working, the memo says, and the problem "only affects the fire department use of the standpipe which would aid us in any fire on the upper levels of the garage." (A standpipe is a pipe system that lets firefighters connect hoses inside a building.)

City staff had given both renewals "favorable recommendations," according to the agenda for the board's Nov. 5 agenda review session. For Main/Wayne, the recommendation was subject to the understanding "that the facility has no working elevators," and property management and the city "have been made aware of the status."

Who owns the garages

The city does. A May 2024 agency agreement says the Redevelopment Commission "owns or will soon own" the Leighton Garage and the Main Wayne Street Garage, and appoints the Board of Park Commissioners as its agent to manage parking there and to hire others to do it. LAZ's 2025 license application for the Leighton Garage lists the premises as leased, with the City of South Bend as owner, and puts the garage at 500 spaces, open 24 hours.

What the license covers

Public parking licenses fall under Section 4-39 of the city code, which the city attaches to each application. It requires signs at each entrance with the operator's name, hours, rates and license number; a bond or liability insurance; an $80 license fee; "proper fire extinguishing apparatus subject to the approval of the Fire Department"; and storage that lets cars "be reached readily in case of fire or other emergencies." The section does not mention elevators or standpipes. It exempts lots that are both government-owned and government-operated; these garages are owned by the city and run by a private operator.

Past renewals have carried conditions. In July 2025 the board approved LAZ's renewal for Main Street, Leighton and the city's 121 E. Wayne St. garage "contingent on egress lighting in SE Stairway" at 121 E. Wayne. In September 2024 a renewal for 119 W. Wayne St. was approved contingent on posting rates and contact information at both entrances.

The elevator project

The city has tried to replace the Main/Wayne elevators. When bids for the Main & Wayne Garage Elevator project were due on Dec. 9, 2025, the minutes record "no bids submitted." The board approved advertising again in January. On Feb. 10, 2026, Gibson-Lewis LLC of Mishawaka submitted the only bid: $708,400 base, or $654,400 for an alternate.

On March 10 the board rejected all bids "due to exceeding available budget," at the request of Zak Tebell of the city's engineering staff. Asked whether the project would be advertised again, Tebell said it "will be on hold," according to the minutes.

The city's design contract with JQOL Global LLC covers both the Nexus Center and Main/Wayne garage elevators. Two amendments approved this year, both described as work on the Nexus Center elevator, raised it from $48,000 to $106,700.

What the records don't show

The records reviewed do not say when the Leighton Garage standpipe went out of service, what fixing the leak would cost or when it is due, or whether the Main/Wayne elevator project has a new schedule or budget. The 2024 agency agreement, as archived, does not say who pays for major repairs.

What did you think of this story?

More stories about Leighton GarageSouth Bend Board of Public Works

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.