City to buy concrete for Cascade Phase 2 with TIF money

The Board of Public Works awarded the $735,666 contract to the only bidder for Wharf Partners' $50 million East Bank condo tower, with the developer installing the concrete.

By South Bend Paper AI Desk · November 8, 2026 at 8:52 AM

Updated November 26, 2026 at 4:52 AM: Updated Nov. 26: the Board of Public Works awarded the concrete contract Nov. 19 to Kuert Concrete, the only bidder, for $735,666.25.

South Bend is buying concrete for the second phase of the Cascade, a privately developed condominium and commercial tower on the East Bank, and paying for it with River East tax increment financing. On Nov. 19 the Board of Public Works awarded the cast-in-place concrete contract to Kuert Concrete LLC of South Bend for $735,666.25. Kuert's was the only bid.

TIF money comes from growth in property taxes inside a redevelopment district, which the city sets aside for projects in that district.

The concrete contract

Kuert's bid was opened Nov. 10, the board's minutes show. It came in $14,123.75, or about 2%, below the engineer's estimate of $749,790, according to the bid tabulation. Caitlin Wyant of city Engineering recommended awarding the contract to Kuert as the lowest responsive, responsible bidder, and the award form says the board took the base bid only.

The contract covers about 3,900 cubic yards of 6,000-psi concrete for the building's columns, shear walls and post-tensioned floor slabs, from Level 1 through the Level 9 roof, at $184.75 to $222.75 a cubic yard. Kuert also listed an alternate that would add $6 a cubic yard in 2027 and $6 more in 2028.

When the bid was opened, board member Murray Miller asked whether the city was buying concrete for the project. Wyant said she had told local concrete suppliers about the bids, and that while it is a large purchase, the development agreement has $8 million in the budget, the minutes summarize. The award is about 9% of that amount.

Kuert has until Dec. 8 to return the signed contract and an insurance certificate, according to the board clerk's award letter.

The developer's agreement

At the Nov. 10 meeting, the board approved a waiver and indemnification agreement with the developer, Wharf Partners LLC, covering "all future material purchases" for Phase 2, according to the board clerk's letter to the company. The agreement was not among the records posted before the meeting; the signed copy is now in the city's records.

It says the city buys building materials "as specified in writing by Owner," and that Wharf Partners "is solely responsible for the proper care and installation" of them. The developer waives any claims against the city arising from the delivery or installation of those materials, and agrees to defend and indemnify the city, its employees and contractors against claims arising from installing them. The agreement lists no dollar amount. City Engineering's request form names the funding source as "River East TIF – Development Agreement."

Why the city is buying materials

The purchases are how the city is paying its share under a development agreement first signed in 2018. On March 26 the Redevelopment Commission unanimously approved a third amendment to that agreement. It raised the city's total commitment for both phases to $10,737,000, up from $9,737,000, and raised Wharf Partners' required private investment to $65 million.

The amendment lists what the city's money may pay for in Phase 2: "site preparation, infrastructure elements, construction materials, and/or other exterior improvements" needed for the developer to finish the building. It also allows the city to meet its obligation through contracts "entered into on its behalf by the Board of Works serving as its agent." Once the city has spent or committed at least $10,687,000, it doesn't have to spend any more, and the developer pays any costs above the funding amount.

The city spent just over $2.7 million on Phase 1, Joseph Molnar of the city's community investment staff told the commission in August 2025, and no city money had gone to Phase 2 as of March. That would leave roughly $8 million for Phase 2.

On Oct. 13, the board approved Wyant's request to advertise for bids on cast-in-place structural concrete for the project. That request listed no dollar amount.

The building

Wharf Partners plans an eight-story building at 312-318 E. Colfax Ave., next to the 2019 Phase 1 tower at 320 E. Colfax. City filings describe about 112,000 square feet, including 30,200 square feet of commercial space and 22 to 32 for-sale condominiums of two to four bedrooms, from about 1,550 to 3,429 square feet. The cost is estimated at about $50 million. The developer estimates 15 new full-time jobs.

The Common Council approved a six-year tax abatement 9-0 on April 27. The commercial space is abated fully for six years. Residential units are abated only while Wharf Partners still owns them. Erik Glavich, the city's director of growth and opportunity, told the council the building would pay about $2.4 million in property taxes over those six years, with about $2.7 million abated, compared with $27,000 if the lot stayed empty. Nobody spoke at the public hearing, the minutes show.

At the March commission meeting, Thomas Panzica of Wharf Partners said rising construction costs and market conditions had created affordability challenges for Phase 2. City help remains essential to keep condo prices competitive with lower-cost, low-rise buildings, the minutes summarize him as saying. Molnar told commissioners construction should start at the end of April and finish in 2029.

What did you think of this story?

More stories about CascadeSouth Bend Board of Public WorksSouth Bend Redevelopment CommissionWharf Partners LLC