City agrees to sell old Claeys Candy plant for $1,000, records show

Claeys Candy reported $11.8 million invested in its new factory against an $8.1 million plan, keeping 30 jobs but adding none of three promised new ones.

By South Bend Paper AI Desk · November 6, 2026 at 3:03 PM

Older records: Published November 6, 2026. The main records behind this story run through August 2024.

When Claeys Candy asked South Bend for tax breaks in 2021 to build a bigger factory, the deal came with a second piece: the city would buy the family company's old plant at 525 S. Taylor St.

Five years later, city records show the new factory on Nimtz Parkway cost more than promised and the company kept the 30 jobs it pledged, but had not added the three new ones. The old plant took a different path. The city's Redevelopment Commission agreed to buy it for $550,000, set a minimum price of $382,000 when it put it up for sale, rejected the only bid, and in July 2024 approved selling it for $1,000 as part of a deal tied to a data center at Union Station.

What was promised

Claeys Candy was founded in 1919 by Jerome C. Claeys, grandfather of current president Gregg Claeys, according to a March 2021 city staff report. The report says the company had "overgrown" its Taylor Street plant and wanted to build a 45,000-square-foot factory in the Blackthorn Corporate Park, at Nimtz Parkway and Mayflower Road, with a new hard candy production line.

The petition, filed by Claeys Candy Inc. and GFC Holdings LLC, listed $5.5 million for construction, $220,000 for land and $2.4 million for new equipment, a total of $8.12 million. The company said it would keep 30 full-time jobs with an annual payroll of $1,280,586 and add at least three new full-time jobs paying $100,000 a year in total.

In return, the council granted two property tax abatements, which phase in taxes on new investment over several years. The building break runs nine years, starting at 100% in the first year and stepping down to 60% in the ninth. The equipment break runs five years. City staff estimated the company would pay about $659,940 in property taxes on the new investment over 10 years, compared with nothing on the empty land.

At a March 8, 2021, committee meeting, Gregg Claeys said the new plant would double the company's capacity and that it was behind on orders, according to the minutes. Asked what would happen to the old building, Dan Buckenmeyer, the city's business development director, said the city was "looking at purchasing the old facility" and parking on the east side of Taylor Street, the minutes say.

Two residents spoke. Murray Miller, who lives on Western Avenue, asked who the contractor would be. Drew Duncan, who lives on High Street, said he believed a nine-year break was "a considerable amount of time to offer a business with only five (5) jobs coming back into the community," according to the minutes, which paraphrase his remarks. The council confirmed both abatements by 9-0 voice votes on March 22, 2021. Gregg Claeys told the council the company had been in its Taylor Street building since 1941, the minutes say.

A gas line and an option to buy

In April 2022 the Redevelopment Commission signed a development agreement with Claeys Candy and GFC Holdings. The city agreed to pay up to $93,824.61 in tax increment financing (TIF) money, property tax revenue from growth in a special district that the city can spend on development, for the company's share of a larger gas main. The company agreed to invest at least $8,152,484 within 12 months, or repay 150% of what the city spent.

City checkbook records show a payment of exactly $93,824.61 to NIPSCO on May 27, 2022, labeled "CLAEYS CANDY EXTENSION."

The agreement also required the company to sign an option giving the commission the right to buy the Taylor Street plant. In February 2023, after the company said it was ready to move out completely, the commission voted to exercise that option at "the agreed upon purchase price of Five Hundred and Fifty Thousand Dollars ($550,000.00)," according to Resolution 3571.

The city checkbook shows a payment of $456,589.64 to Meridian Title Corp. on Jan. 30, 2024, labeled "525 TAYLOR ST-CLAEYS," and a $7,970.30 payment in August 2024 to Land Services USA labeled "CLAEYS CANDY ACQUISITION." The records reviewed do not explain the difference between the closing payment and the $550,000 price.

The three payments, the city checkbook entries tied to Claeys Candy in the records reviewed, total $558,384.55. Buying the old plant accounts for about 82% of that and the gas main for about 17%.

City checkbook payments tied to the Claeys Candy movesThree payments, May 2022 to Aug. 2024, totaling $558,384.55; nominal dollars, one-time amounts; excludes the tax abatements
82%17%Old plant closing (MeridianTitle)$457K · 82%Gas main (NIPSCO)$94K · 17%Acquisition services (LandServices USA)$8K · 1.4%

Source: City of South Bend checkbook via the Transparency Portal

The chart does not include the tax abatements, whose value depends on assessments the records reviewed do not show, or the $1,000 the city approved receiving when it sells the old plant.

What the records show since

The city's annual abatement report dated June 15, 2024, covering 2023, lists:

  • Building cost: $7,416,925 actual, against a $5.5 million estimate.
  • Equipment cost: $4,343,478 actual, against a $2.4 million estimate.
  • Completion: Oct. 31, 2022, for the building, about seven months after the expected April 1, 2022 date. Gregg Claeys had told the council in 2021 that the goal was spring 2022.
  • Jobs: 30 retained, as promised. The building row reports 0 new jobs against 3 promised.
  • Compliance score: 2, "substantially in compliance," on the building break.

Together, the $11.76 million the city reports is about 45% more than the $8.12 million in the petition.

The year before, the report dated June 15, 2023, gave the building break a score of 1, "Company is in compliance," with the same $7,416,925 cost and 30 retained jobs. The city's legend says a 2 can mean a company "did not meet one or more goals" but that the project is relatively new or other factors have slowed progress. The reports do not say which applies here.

The building break's pay years run from 2023 to 2032, and the equipment break's from 2024 to 2028, according to the 2024 report. It is the most recent abatement report in the city's public records archive.

The old plant

In April 2024 the commission set a minimum offering price of $382,000 for the roughly 26,134-square-foot former factory, the average of two independent appraisals, and invited bids for uses allowed in industrial zoning.

It got one. Stoic Distillery Company bid the $382,000 minimum, but city property manager Joseph Molnar told the commission May 23, 2024, that the bid was incomplete, with "an incomplete narrative description, no site plan," and an unfinished non-collusion affidavit, according to the minutes. He said staff wanted to keep working with Stoic, and that accepting the bid would leave "no ability to put any restrictions on the sale of the building." The commission rejected it unanimously.

Two months later, on July 25, 2024, the commission approved buying the Grand Hall and parking lot of Union Station for $2.43 million, the average of two appraisals. In the same package, staff asked to sell the former Claeys building to Union Station Properties Holding for $1,000. According to the minutes, "The sale is part of an effort to activate the property as part of a new data center development. This would facilitate removal of the data center office space over time from the Grand Hall building." The commission approved it unanimously.

The records reviewed do not show whether the $1,000 sale has closed, what the buyer has done with the building, or what the commission's agreement requires of it; the signed purchase agreement in the archive has no readable text beyond its cover memo.

What did you think of this story?

More stories about South Bend Redevelopment Commission

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.