Council approves $1.7 million TIF loan for 50 affordable units
The city's share of the Heartwood Commons project on South Main Street grew from $1 million after buried debris and higher costs pushed up the budget.
The South Bend Common Council on Oct. 26 approved a city loan of up to $1.7 million to help build Heartwood Commons, a 50-unit affordable apartment building planned for 2018-2020 S. Main St. on the city's south side, according to Ordinance No. 11321-26.
The money will come from tax increment financing, or TIF. TIF lets the city's Redevelopment Commission spend the growth in property taxes inside a district, here the South Side Development Area, on projects there instead of sending it to the city, schools and other taxing units.
Who gets the money and on what terms
The borrower is KCG Donald & Main, LP, an Indiana limited partnership tied to the Indianapolis-based developer KCG. The ordinance puts the project's total cost at about $16.7 million, including at least $15 million in private investment.
Under the ordinance, the loan carries no interest, is paid out in draws as construction proceeds, and may run until Dec. 31, 2066. No more than $1 million can be drawn in 2026. The ordinance says it is not a debt of the city.
A city cover letter to the council says the loan "would be forgivable upon substantial completion of the project." If the developer abandons the project, the ordinance requires it to repay what it has drawn, with interest.
The same letter says the project won an allocation of federal Low-Income Housing Tax Credits from the Indiana Housing and Community Development Authority. The council also approved a 10-year real property tax abatement for the project in July 2025.
Why the city's share went up
The loan replaces and enlarges an earlier commitment. According to the signed minutes of the Redevelopment Commission's Sept. 24 meeting, the commission agreed in June 2025 to sell the site at 2020 S. Main St. to KCG if the developer won the tax credits. KCG won them in November 2025, and the city then committed a $1 million local match.
Deputy Director of Community Investment Joseph Molnar told the commission that site studies found difficult soil conditions and higher construction costs, the minutes say. Megan Schuetz of KCG said the project budget had grown by about $2 million since last year. Ground-penetrating radar found buried foundations and demolition debris, requiring an estimated $700,000 to prepare the site, according to the minutes. KCG raised its minimum private investment from $13 million to $15 million, and the city's commitment rose from $1 million to $1.7 million. Molnar said none of the earlier money had been spent.
The commission approved the TIF funding, Resolution No. 3679, unanimously on Sept. 24, the minutes show.
How the city's share compares
With the larger loan, city support for Heartwood Commons other than its tax abatement comes to about $35,100 per apartment: the $1.7 million loan plus $56,350 that a review of city records counts as the city's discount on the land, divided by 50 units. The Redevelopment Commission's purchase agreement sets a $1,000 price; the $57,350 value it cites is a 2012 offering price that also covered other lots. Using the earlier $1 million commitment, the review had put it at about $21,100.
The review lists 24 other affordable housing projects that received city money beyond tax abatements. Their median was about $21,500 per unit. Heartwood's figure is about 64% above that median and higher than 16 of the 24. Eight received more, led by the 466 Works Southeast infill homes at about $116,700 per unit and Tri-Day Development at about $109,500. KCG's own 50-unit senior building at 1202 S. Lafayette Blvd., approved in 2023, received the least, about $600 per unit.
The chart below shows the 15 projects with the highest city support per unit; the median line covers all 24 other projects.
Source: A review of city records via the Transparency Portal; Ordinance No. 11321-26
The figures are each deal's total city commitment divided by its units, not yearly amounts. They are nominal dollars as approved, not adjusted for inflation to 2026 dollars; years in the chart are the year of each deal. The comparison counts TIF, loans, grants, land discounts and city-paid site work, and leaves out tax abatements and federal money. The projects range from new apartment buildings to renovations and single-family homes, which affects cost per unit.
Site concerns
Rebecca Ford, who lives on West Donald Street near the site, told the commission she was worried about the property's former industrial use, saying demolition debris and potentially hazardous materials may have been buried there, and questioned whether soil testing had been sufficient, according to the minutes.
Molnar said environmental assessments and soil testing had been done by both the city and the developer, and that 2026 testing "found no contamination above residential standards," the minutes say. He said buried rubble had been found and will be removed, and that the results will be made public. Schuetz said KCG was committed to sharing the environmental reports with the public.
Schuetz told the commission the project has commitments of Section 8 vouchers from the Housing Authority of South Bend and Section 811 vouchers for people with disabilities, the minutes say.
The records reviewed do not state the income limits for the 50 units or when construction will begin.
More stories about Heartwood CommonsSouth Bend Common CouncilSouth Bend Redevelopment Commission
- Ordinance No. 11321-26, Authorizing a Direct Loan to the Developer of an Economic Development Facility (Heartwood Commons Project), City of South Bend(opens in a new tab)
- Oct. 26, 2026 Common Council agenda packet (Bill 69-26 cover letter)(opens in a new tab)
- Redevelopment Commission minutes, Sept. 24, 2026 (signed)(opens in a new tab)
- South Bend Redevelopment Commission agenda and packet, Oct. 8, 2026(opens in a new tab)
- Resolution 5141-25, Confirming Resolution, Real Property Tax Abatement for KCG Donald & Main, LP(opens in a new tab)
- Resolution 5139-25, Designating Resolution, Real Property Tax Abatement for KCG (contact Megan Schuetz)(opens in a new tab)
- Real Estate Purchase Agreement, 2018-2020 S. Main St. (KCG), Redevelopment Commission, June 2025(opens in a new tab)
- A review of city records: South Bend development incentives (Transparency Portal; source documents mirror)(opens in a new tab)
- Development Agreement, Property Bros LLC (River West TIF), Sept. 2023(opens in a new tab)
- Redevelopment Commission minutes, April 13, 2023 (Western Avenue / Monroe Circle demolition)(opens in a new tab)
- Redevelopment Commission minutes, Jan. 8, 2026 (Rabbi Shulman building demolition)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.