County seeks federal aid for $9.9M second phase of Pierce Road
Commissioners vote Monday on an application that would leave the county paying about $1.98 million. A lift station at Douglas and Bittersweet roads also heads to bid.
St. Joseph County would pay about $1.98 million of a $9.9 million rebuild of Pierce Road between Juniper Road and Miami Highway if a federal aid application goes forward and is funded, according to the agenda packet for the Board of Commissioners' meeting Monday, Nov. 30.
County Engineer Sky Medors asks commissioners to let Public Works apply through the Indiana Department of Transportation's 2026 federal aid call for rural local projects. The application would cover the second phase of the Pierce Road reconstruction. The first phase, from U.S. 31 to Juniper Road, is under construction and scheduled to be finished in 2027, the request says.
What the money would buy
The packet puts construction at $8.8 million, figured in 2032 dollars, plus $1.1 million for construction engineering. Federal money would cover 80% and the county 20%, the request says, with the county's share paid from its Local Roads and Streets fund.
The work would rebuild the rural road with new subbase and asphalt, two 12-foot travel lanes, paved and gravel shoulders, pavement markings, driveway approaches and signs. Vegetated ditches and drainage work would run from east of Ivy Road to Miami Highway.
A commitment letter to INDOT, which only the board president signs, says the county has local money available for the match for construction in fiscal year 2032 or earlier. Any later approvals would come back to the board, the request says.
For the first phase, the county engineer recommended in March that commissioners pick Lochmueller Group to handle construction engineering, after the county received proposals from several firms under INDOT's qualifications-based process.
Lift station and road bids
Commissioners are also asked to advertise for bids on a lift station for the Capital Avenue Corridor Utility Expansion. Economic Development Director Bill Schalliol's memo says it would be built at the northwest corner of Douglas and Bittersweet roads, with a new wet well, valve vault, pumps, a 10-inch force main and controls. The bid notice carries both a county project number and a City of Mishawaka project number. Bids would be opened Dec. 22. The packet gives no cost estimate.
Also on the agenda:
- A $4,000 change order with Rieth-Riley Construction on the Knollwood drainage project, raising the contract to $359,400. The county engineer's letter says two old drywells were no longer working and were at risk of undermining a new concrete intersection, so crews filled them.
- Bids for about 2.49 miles of asphalt overlay under the state Community Crossings matching grant program: Fillmore Road from Pine Road to Edison Road, and Mayflower Road from Cloyd Street north about 5,687 feet. Bids would also be opened Dec. 22.
- An Airport Authority board appointment and a Recorder's Office agreement with the City of South Bend for LAREDO, which the agenda does not describe further.
The meeting starts at 11 a.m. in the fourth-floor council chambers of the County-City Building and can be joined by Zoom. Speakers must sign up before it starts and get three minutes.
More stories about DLZ IndianaIndiana Department of TransportationRieth-Riley ConstructionSky MedorsSt. Joseph County Board of Commissioners
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines