County to add $42,500 to Sample Street bridge design contract
An inspection found missing stones, a damaged railing and water reaching the beam ends, raising American Structurepoint's cap to $269,025 on a contract signed in 2021.
Updated November 23, 2026 at 6:48 AM: Correction: An earlier version described where American Structurepoint is based; the county records this story relies on do not say, so that detail was removed.
St. Joseph County commissioners will vote Tuesday on adding $42,500 to an engineering contract for rehabilitating the Sample Street bridge over the St. Joseph River, after an inspection turned up work the original plans did not cover.
The change, Supplemental Agreement No. 1 with engineering firm American Structurepoint, would raise the most the county can pay the firm from $226,525 to $269,025, an increase of nearly 19%, according to the agenda packet for the Board of Commissioners' 11 a.m. meeting Nov. 24. The county signed the original contract, for engineering and construction inspection on Bridge No. 208, on Nov. 16, 2021, the amendment says.
What the inspection found
County Engineer Sky K. Medors wrote in a Nov. 10 letter to the commissioners that a detailed inspection of the bridge identified several items outside the original scope. The revised plans add three repairs:
- replacing missing masonry stones in the bridge's supports,
- repairing the pedestrian railing, and
- replacing the concrete approach slab at the south end and adding a rubber membrane behind it, to stop water from reaching the ends of the bridge beams.
The firm also must survey the southwest approach, from the end of the bridge to State Road 933, because inspectors saw drainage problems there and needed to map utilities, Medors wrote.
A state floodway permit required the county to make up for trees removed near the river. There wasn't enough public land to replant on site, so the county met that requirement through the Indiana Department of Natural Resources' in-lieu fee program, which the firm coordinated, the letter says.
Some costs went down. The revised scope no longer needs a state water quality certification or a U.S. Army Corps of Engineers permit, and the fee for wetland and permit work drops from $12,900 to $7,500.
Where the money goes
The largest change is bridge design and plans, which rises from $77,000 to $108,700. The new survey adds $16,200. Medors wrote that Public Works reviewed the fees, found them acceptable and recommends approval.
The packet does not include a construction cost estimate or a schedule for the bridge work.
More stories about American StructurepointSky MedorsSt. Joseph County Board of Commissioners
- St. Joseph County Board of Commissioners agenda and packet, Nov. 24, 2026 (Supplemental Agreement No. 1, Bridge 208 Sample Street over St. Joseph River, with County Engineer letter dated Nov. 10, 2026)(opens in a new tab)
- St. Joseph County Board of Commissioners agenda, Nov. 24, 2026 (county Agenda Center)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.