Our Lady of Hungary Parish's request to vacate a block of Chapin Street, which takes a council ordinance, comes up for a final vote Nov. 9.

By South Bend Paper AI Desk · November 6, 2026 at 8:24 AM
The stretch of Chapin Street between Bruce Street and West Calvert Street (outlined in red) that Our Lady of Hungary Parish has asked the city to vacate, from the diagram filed with Bill 82-26. The church and school sit on either side. City of South Bend records

When a South Bend street or alley is "vacated," the city gives up the public's right to use it as a way to travel. The pavement may stay for a while, but the strip stops being a public street, and the land becomes part of the neighboring property.

The South Bend Common Council will hold a public hearing and final vote Monday, Nov. 9, on one such request: Bill 82-26, which would vacate Chapin Street between West Calvert Street and Bruce Street on the city's southwest side, according to the council's agenda. Here's how the process works, using that request as the example.

Who decides

State law gives the call to the council. The ordinance cites Indiana Code 36-7-3-12, which it says charges the council "with the authority to hear all petitions to vacate public ways or public places within the City."

Before a petition reaches the council, though, it goes through the city's Board of Public Works, which gathers comments from other departments and makes a recommendation.

Step 1: A preliminary review

An applicant starts with a preliminary review form for the Board of Public Works. It asks where the street or alley is, whether the applicant's property is next to it, whether other owners use it, and why the applicant wants it closed.

City staff answer a short checklist on the same form, including whether the block is longer than 600 feet, whether closing it would create a dead-end alley or interfere with a bike route, and whether utilities run underneath.

For Chapin Street, the forms filed with the bill show the parish's engineering firm, ERI Consulting of Fort Wayne, submitted preliminary reviews dated June 26 and July 13, 2026. Staff noted that utilities do run under the street and wrote that connecting the church and school "is consistent with ideas shown within the Rum Village Neighborhood Plan adopted in 2022."

Step 2: Department sign-off and the four tests

Next, the Board of Public Works clerk sends the request to engineering, community investment, fire and police for recommendations. The memo for Chapin Street, dated Aug. 12, 2026, asks each department to weigh the four criteria in Indiana Code 36-7-3-13: whether the vacation would

  • hinder the growth or orderly development of the neighborhood,
  • make access to an objecting owner's land "difficult or inconvenient,"
  • hinder the public's access to a church, school or other public building, or
  • hinder the neighborhood's use of a public right-of-way.

Community Investment, Fire and Police each returned a favorable recommendation. Public Works and Engineering's was favorable "contingent on recording 20' easement for watermain."

At its Sept. 8 meeting, the Board of Public Works found the Chapin Street vacation would meet all four tests and sent a favorable recommendation, according to its letter to the parish's pastor, the Rev. Benjamin Landrigan.

The application to the board requires a $300 payment by check or money order, according to the form in the bill.

Step 3: An ordinance, a hearing and a council vote

The applicant then takes the board's recommendation to the City Clerk, and the vacation is written as an ordinance. "Alley/Street vacations require a presentation to the Common Council, approval of an ordinance, and certification of the ordinance from the Mayor," the board's letter says.

The Chapin Street ordinance was filed with the clerk Oct. 6. It lists 29 nearby addresses that "may be injuriously or beneficially affected" by the vacation. The council's Public Works and Property Vacation Committee is scheduled to take it up at 4:25 p.m. Nov. 9, ahead of the full council's public hearing and vote that evening.

What the city keeps

Vacating a street doesn't clear out what's under it. The Chapin Street ordinance reserves the rights and easements of all utilities and the city to build and maintain electric, phone, gas, water and sewer lines and drainage structures in the vacated strip, "unless such rights are released by the individual utilities."

The city can also attach conditions. This ordinance requires the parish to hire a contractor bonded with the city to remove the street's curb opening, replace it with curb and plant a tree lawn within 90 days of final council approval.

Step 4: Recording the change

After the mayor signs, the vacation has to be recorded with the county Recorder's Office. The board's letter tells the pastor that step ensures "your 50% ownership of the property is appropriately transferred to your name," and directs questions about how the change will affect property taxes to the county Auditor's Office.

Why the parish asked

In the parish's request letter, engineer Calvin Tims wrote that the block "is not a central travel path for the neighboring streets so there would be no anticipated traffic impacts." Closing it, he wrote, "will allow for more unified parcel between the church and the school buildings while also allowing for future play spaces for the children," and a more cohesive parking layout "which will allow for safer traffic patterns during church events."

The ordinance's statement of purpose says the land would become a green space and recess area for students and would also be used for "parish events such as festivals, food sales, youth group, etc."

The records filed with the bill do not show any objections from neighbors. Anyone who wants to speak can do so at the Nov. 9 public hearing, which begins at 7 p.m. in the Council Chambers on the third floor of City Hall, 215 S. Martin Luther King Jr. Blvd., or online through Microsoft Teams, according to the agenda.

What did you think of this story?

More stories about Chapin StreetOur Lady of Hungary ParishSouth Bend Board of Public WorksSouth Bend Common Council

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.