Development

Why the lowest bid doesn't always win South Bend public works jobs

The Board of Public Works awards jobs to the "lowest responsive and responsible bidder," which this year meant passing over two cheaper bids on Harrison Avenue.

By South Bend Paper AI Desk · November 3, 2026 at 9:32 PM

When South Bend tears down a building or rebuilds a street, the job usually goes out for bids. The contract does not automatically go to the cheapest bidder. It goes to the lowest bidder that followed the rules. This year's demolition of a former church on Harrison Avenue shows how that works.

Who decides

Contracts are awarded by the Board of Public Works, a five-member board whose members are appointed by the mayor for an indefinite term, according to the board's agenda. City engineers manage each project and bring recommendations to the board at its public meetings.

Step by step

1. Permission to advertise. An engineer asks the board for permission to advertise for bids. For example, on March 24, 2026, the board approved advertising for bids to demolish the River Glen office buildings.

2. Bids are opened in public. Sealed bids are opened and read aloud at a board meeting on the due date. Each bid includes forms such as a non-collusion affidavit and forms on minority- and women-owned business (MWBE) subcontractors.

3. An engineer reviews them. The engineer checks the lowest bid first. Is it complete? Does it meet the project's MWBE goals? Is the company a "Responsible Bidder" under the city's ordinance? A bid that fails those checks is called "non-responsive" and is rejected, and the engineer moves on to the next lowest.

4. The board awards the contract. The engineer's memo recommends a winner. The board votes. The clerk sends letters to every bidder.

5. Bonds and insurance. Before the contract is final, the winner has to turn in a signed contract, a labor and material payment bond, a performance bond of 125% of the bid and proof of insurance naming the city.

6. Change orders. If the work turns out to be bigger or smaller than planned, the board approves a change order that raises or lowers the price.

7. Completion. The contractor signs a project completion affidavit. After the city engineer accepts the work, the final payment goes to the board along with a waiver of lien.

A real example: 747-749 Harrison Ave.

The city had recently bought the former church complex at Harrison Avenue and Van Buren Street. An engineering memo described the building as "in a state of disrepair beyond salvaging." On Feb. 10, 2026, the board opened five bids:

Bids to demolish 747-749 Harrison Ave.Nominal dollars, lump-sum bids opened Feb. 10, 2026; Ritschard Brothers was awarded the contract
$0$100K$200K$300K$400K$500KKLF Enterprises$385KDore & Associates$405KRitschard Brothers$443KIndiana Earth$455KGreen Demolition$499K

Source: City of South Bend Board of Public Works records

Zach Hurst, a senior project engineer, recommended rejecting the two lowest bids. KLF Enterprises of Markham, Ill., bid $385,000. According to his memo, its women-owned subcontractor was from Grayslake, Ill., outside the area the bid rules allow (Indiana and Berrien County, Mich.). KLF also listed no other women-owned firms it had contacted, so it did not qualify for a "Good Faith Effort waiver." It also was not pre-qualified as a Responsible Bidder and had filled out the wrong checklist.

Dore & Associates of Bay City, Mich., bid $404,800. The memo said it could not show membership in an apprenticeship program approved by the U.S. Department of Labor, which the city's Responsible Bidder Ordinance requires.

The third-lowest bid, $443,486 from Ritschard Bros. of South Bend, was "complete and responsive" and within budget, the memo said. On March 10 the board awarded it the contract, $58,486 more than the lowest bid. The work is paid from the River West Development Area TIF. A TIF, or tax increment financing district, sets aside property tax growth in one area to pay for projects there.

When the low bidder does win

Two months later, KLF Enterprises won. On April 28 the board opened six bids to demolish three buildings in the former River Glen office park at 348 and 404 Columbia St. and 501 E. Monroe St. KLF's $442,000 was lowest. This time Hurst's memo said KLF was "pre-qualified as a Responsible Bidder" and could meet the MWBE goals. The board awarded it the job on May 12. The highest of the six bids was $793,876.

When the price changes

A contract amount isn't always final. On March 24, the board awarded the demolition of the Qualex building at 921 Louise St. to Green Demolition Contractors for $365,000. In June it approved a $95,800 change order after crews found a second buried concrete slab of about 20,000 square feet. On Oct. 13 the board accepted the job at a final cost of $460,800.

The South Bend Paper did not interview anyone for this explainer. It is based on the Board of Public Works records listed below.

What did you think of this story?

More stories about Ritschard Bros.South Bend Board of Public Works

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.