Hill Apartments' reported cost is less than half what council heard
City staff described a $27.6 million rehab of a vacant Notre Dame Avenue medical office. City reports list $12.55 million, which still met every investment pledge in the deal.
Older records: Published November 19, 2026. The main records behind this story run through June 2025.
When the South Bend Common Council took up a tax break in November 2022 for turning a vacant medical office building at Notre Dame Avenue and Cedar Street into apartments, city staff described it as a $27.6 million project.
City reports since then put the finished cost of The Hill Apartments, at 511 N. Notre Dame Ave., at $12.55 million.
The records do not explain the gap. But the lower figure still clears every investment pledge written into the project's agreements with the city, and the city's tax abatement reports rate the project in compliance.
What was promised
The developer, ND QOZB LLC, is an Idaho company that the city's report describes as a partnership between Public Development Partners LLC of Utah and GPWM Funds, a qualified opportunity zone fund. Its plan was to gut the building, vacant since July 2014, and convert it into 69 studio and one-bedroom apartments.
In a Nov. 9, 2022, letter to the council, Community Investment Executive Director Caleb Bauer put the total private investment at $27.6 million, and the department's report by Erik Glavich used the same figure. Glavich presented it to the council on Nov. 14 as a "$27 million renovation," with 20% of units at low-income rents based on federal housing guidelines, the minutes say. The council approved the first resolution 7-0 that night and confirmed the break Nov. 28.
The developer's own petition told a smaller story. Its investment table, which included $2.45 million for land and $8 million for building improvements, showed a total of $13,695,000. The memorandum of agreement the company signed committed it to about $10.38 million in spending, at least 20% of units for low- and moderate-income households for the life of the break, and 10 full-time jobs with a $760,000 payroll within three years.
The eight-year abatement, starting at 100% and stepping down to 65%, was estimated to save the owner $1,028,241 in property taxes, according to the department's report.
The city's report also said the developer planned 25 owner-occupied townhouses on the rest of the site, outside the abatement. The site was split into two building lots in 2023, Plan Commission records show. Records reviewed do not show the townhouses being built.
The city's $500,000
In February 2023, the Redevelopment Commission agreed to spend up to $500,000 in River East TIF money on site work: parking lot repairs, fencing, drainage, bike racks and landscaping. TIF, or tax increment financing, uses growth in property taxes within a district to pay for projects there. In return, the developer had to spend at least $12 million and finish by Dec. 31, 2024, or repay 150% of what the city spent.
The Board of Public Works hired Majority Builders for the site work at $476,786 and added $23,214 in a final change order, for exactly $500,000. City checkbook records show six payments to Majority Builders for the project from August 2023 to April 2024, totaling $500,000.
What the reports show
The city's abatement report covering 2023 lists the project's actual cost at $12.55 million, against an estimate of $11.385 million, and completion on Dec. 15, 2023, a year before the deadline. It lists eight new jobs, matching the eight in the company's first-year estimate, and rates the project "in compliance." The 2024 report, filed with the council in June 2025, repeats the cost and completion figures. It is the newest compliance report found; the 2025 report had not turned up in city records.
The reports measure cost and jobs. They do not say whether 20% of the units are rented to low- and moderate-income households, as the memorandum requires, and records reviewed do not show whether the city has checked.
No statement from the developer or the city explaining the difference between $27.6 million and $12.55 million appears in the records reviewed.
More stories about Erik GlavichRiver East TIF districtSouth Bend Common CouncilSouth Bend Department of Community InvestmentSouth Bend Redevelopment Commission
- Bill 22-57 packet: DCI letter (Nov. 9, 2022), tax abatement report, petition and Statement of Benefits, ND QOZB LLC, 511 N. Notre Dame Ave.(opens in a new tab)
- Bill 22-58 packet: confirming resolution and Memorandum of Agreement, ND QOZB LLC (Nov. 2022)(opens in a new tab)
- Resolution 4992-22, confirming eight-year tax abatement, 511 N. Notre Dame Ave. (Nov. 28, 2022)(opens in a new tab)
- South Bend Common Council minutes, Nov. 14, 2022 (signed)(opens in a new tab)
- Development Agreement, Redevelopment Commission and ND QOZB LLC, with agenda memo (Feb. 9, 2023)(opens in a new tab)
- Redevelopment Commission minutes, Feb. 9, 2023(opens in a new tab)
- Change Order No. 1 (Final), The Hill TIF Project Site Work, Project 123-030, Majority Builders (Jan. 23, 2024)(opens in a new tab)
- Plan Commission agenda packet, Feb. 20, 2023 (Cedar Street and Notre Dame Avenue Minor Subdivision, PC#0133-23)(opens in a new tab)
- Department of Community Investment, 2023 annual tax abatement report, in budget answers filed Sept. 12, 2024(opens in a new tab)
- City of South Bend 2024 Annual Tax Abatement Report (filed June 13, 2025)(opens in a new tab)
- City of South Bend checkbook via the Transparency Portal: payments to Majority Builders for 511 N. Notre Dame Ave., fund 429, 2023-2024(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.