Hotel deal's Hall of Fame half still vacant, city plan says
City reports rate the 2015 Courtyard by Marriott tax break compliant, but the landmark it was meant to reuse sold for $525,000 in 2018 and still sits empty.
Older records: Published November 17, 2026. The main records behind this story run through March 2026.
Updated November 17, 2026 at 2:50 AM: Correction: An earlier version referred to the author of a July 2019 JSK letter as "she." The letter does not identify the writer's gender.
When South Bend handed JSK Development the former College Football Hall of Fame and the parking lot beside it in 2015, the deal had two halves: a new 120-room hotel on the lot, and a second life for the Hall of Fame building as the hotel's lobby, restaurant and the company's headquarters.
City records show the hotel half happened. The Courtyard by Marriott opened in 2018, and the city's yearly tax abatement reports rate its tax break in compliance. The other half did not. The Downtown 2045 Plan the Common Council adopted in March says the Hall of Fame building has sat vacant for more than 10 years, and it lays out options that include tearing it down.
What was promised
A July 2015 Department of Community Investment memo to the Redevelopment Commission described the project as a hotel that would use the Hall of Fame structure as its grand entrance and lobby, with a possible restaurant, retail space and room for the developer's headquarters. The memo said the project would create 60 new jobs downtown and bring about $10 million in private investment.
The development agreement attached to that memo set the terms. The commission would convey the lot on St. Joseph Street, the Jefferson Lot, to the developer, Southhold LLC, for $1. The developer would buy the Hall of Fame building for $1.2 million in installments tied to the hotel's opening. The city would put up to $700,000 in tax increment financing (TIF), property tax money set aside within a district for development there, toward public improvements at the site. In March 2016, as the hotel's planned investment grew to $12 million to $14 million, the commission added up to $500,000 more, which the developer personally guaranteed, and approved a separate $415,000 utility budget to move lines around the new hotel, the commission's minutes show.
The Common Council approved a nine-year real property tax abatement for the hotel in June 2015 (Resolution 4457-15). The city's report on the petition estimated the break at $945,911 over nine years, with $1,464,805 in taxes still paid in that time. The petition promised 38 new full-time jobs, and the report noted JSK planned to relocate about 32 corporate jobs into the downtown building. The council also granted a two-year vacant building abatement on the Hall of Fame building, a 2019 department letter shows.
The hotel
When the commission issued the hotel's certificate of completion in June 2018, staff told the board the development agreement had committed to $10 million in private investment and the actual was over $12 million, the minutes say.
The numbers since have not always matched. A September 2018 letter from JSK's chief financial officer, Priti Patel, put the investment at $11 million with 38 new jobs. A department letter a year later said $12.4 million and 76 new jobs. The city's annual abatement reports list an actual cost of $9,927,576 against an $8.75 million estimate, and count fewer jobs than either letter.
The reports list 38 new jobs announced and count 27 in the 2022 report, 49 in the 2023 report and 36 in the 2024 report, the most recent. Each year the hotel gets a compliance score of 1. The 2022 report's legend defines that score as a company in compliance with all goals, including jobs created. The reports don't explain the score in the years the count fell short of 38.
Source: City of South Bend annual tax abatement reports, 2022-2024
The hotel's abatement also needed help along the way. In September 2018 the council extended the window for the project to qualify after JSK said the county had never sent the reassessment notice it needed to file. In September 2019 the council waived noncompliance for late-filed deduction forms on both the hotel and the Hall of Fame building (Resolutions 4805-19 and 4806-19). In a July 2019 letter in the council packet, a JSK official wrote that the employee who had handled the abatement paperwork had left the company and that the writer had not understood the filing steps. The department supported the waivers, writing that the companies had met or exceeded their commitments.
The Hall of Fame building
In June 2018 the commission cut the building's price from $1.2 million to $525,000. Business development director Daniel Buckenmeyer told the board that earlier versions of the deal had stalled over the building's heating and cooling system, maintenance, its interior and liability, and that the commission was also dropping its promise to maintain that system for three years after the sale, the minutes say.
Dan Boecher, speaking for the developer, told the commission the building was a major pivot from the original plan for a welcome center. He said it had been on the market for over a year and a half, that the developers who looked at it had all passed, and that JSK was dedicated to making it work, according to the minutes.
The amended agreement required the developer to get a certificate of occupancy for at least the street-level portion of the building within two years of closing. It also barred a sale to a third party for 36 months unless the commission received up to the original $1.2 million price. The sale closed Aug. 22, 2018. The next day the commission waived that restriction, and its right to payment, for a transfer to JSK Development Inc., which staff described as the majority owner of Southhold LLC.
The records reviewed for this story do not show whether the certificate of occupancy was issued or whether the commission took any action on that deadline. They show no later public statement from JSK on its plans for the building.
The Downtown 2045 Plan says the empty building looms over Gridiron Plaza, which the plan calls downtown's de facto town square, and that the part of the building under the Gridiron limits what the square can become. It offers three concepts: reuse the building with a family-friendly use such as a restaurant or interactive museum on the ground floor, or demolish it and build either a market hall or a boutique hotel with shops and restaurants at street level.
The hotel's abatement runs through taxes payable in 2028, according to the city's 2024 report.
More stories about South Bend Common CouncilSouth Bend Department of Community InvestmentSouth Bend Redevelopment Commission
- Resolution 4457-15, confirming nine-year real property tax abatement for JSK Development Inc./Southhold LLC, with DCI tax abatement report and petition (June 22, 2015)(opens in a new tab)
- DCI memo and Development Agreement, DTSB Hotel at Hall of Fame, Redevelopment Commission agenda item 6.B.(2) (July 13-16, 2015)(opens in a new tab)
- Redevelopment Commission minutes, March 24, 2016(opens in a new tab)
- Redevelopment Commission minutes, June 28, 2018(opens in a new tab)
- Fifth Amendment to Development Agreement, Southhold LLC (June 28, 2018)(opens in a new tab)
- Redevelopment Commission minutes, Aug. 23, 2018 (Resolution 3439)(opens in a new tab)
- Resolution 3439, waiver of prohibition of third-party transfer to JSK (Aug. 23, 2018)(opens in a new tab)
- Bill 18-45 packet: DCI letter and JSK Development letter, modifying and reconfirming resolutions (Sept. 5, 2018)(opens in a new tab)
- Bill 19-53 packet: DCI letter and JSK Development letter, waiver of noncompliance (Sept. 4, 2019)(opens in a new tab)
- Common Council minutes, Sept. 9, 2019(opens in a new tab)
- Resolution 4805-19, waiver of noncompliance, Courtyard by Marriott(opens in a new tab)
- Resolution 4806-19, waiver of noncompliance, former Hall of Fame building(opens in a new tab)
- City of South Bend 2022 Annual Tax Abatement Report (June 15, 2023)(opens in a new tab)
- Department of Community Investment budget answers with 2023 tax abatement report (Sept. 12, 2024)(opens in a new tab)
- City of South Bend 2024 Annual Tax Abatement Report (filed June 13, 2025)(opens in a new tab)
- Resolution 5165-26, approving and adopting the Downtown 2045 Plan (March 23, 2026)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.