How South Bend borrows against future federal grants

A $10 million HUD Section 108 loan is paying for streets and utilities at the Western Avenue housing site, repaid from about a fifth of the city's yearly block grant.

By South Bend Paper AI Desk · November 11, 2026 at 1:51 AM

South Bend is paying for a new street, utilities and other public work on the southwest edge of downtown with money it has not received yet: future federal housing grants.

The tool is a Section 108 loan, named for a section of the federal Housing and Community Development Act of 1974. The Common Council approved a $10 million one for the Western Avenue Transformation District on Aug. 24, 2026, by an 8-0 vote with one member absent, council minutes show.

What a Section 108 loan is

Every year the U.S. Department of Housing and Urban Development sends larger cities a Community Development Block Grant, or CDBG, a flexible grant for housing and neighborhood work. Section 108 lets a city borrow against that stream of future grants and spend the money now.

HUD describes the program as "a source of low-cost, long-term financing" for community and economic development. HUD guarantees the loans, and they are financed through public offerings. A city like South Bend can apply for up to five times its latest CDBG grant, and "the maximum repayment period for a Section 108 loan is 20 years," according to HUD.

The main security is the city's pledge of its future CDBG money. HUD requires additional collateral in case those grants fall short.

How South Bend's loan works

The city applied for the loan on Sept. 3, 2025, and HUD awarded it in May 2026, according to the ordinance and a Department of Community Investment presentation to the council.

Joe Molnar, deputy director of Community Investment, told the council's Community Investment Committee on Aug. 24 that the city receives about $2.3 million in CDBG money a year. He said repaying the loan would take about $500,000 of that each year, about 22%, "leaving approximately one-point-eight million dollars ($1,800,000) per year for other projects," according to the committee minutes. He estimated the interest rate at about 4.1% at closing.

The ordinance estimates the city's yearly payments at about $427,000 in 2026, rising to about $580,000 in 2045, over a term of up to 20 years.

The backup collateral is tax increment financing, or TIF: property tax growth inside a redevelopment district that the Redevelopment Commission can spend there. On Aug. 13, the commission pledged River West TIF revenue to repay the loan if CDBG money ever falls short. Its staff memo called that an "unlikely event" and said the city expects its block grants to "more than cover" the payments. The pledge ranks behind two earlier TIF bonds that already draw on River West revenue, the resolution says.

Asked how the city's CDBG amount is set, Molnar told the committee it comes from a formula that considers a city's population and poverty level, and that the amount has been relatively stable, with a slight reduction in recent years.

Because the loan money arrives during the year rather than in the adopted budget, the council also had to approve spending it. Its third-quarter additional appropriations ordinance, heard Sept. 28, included $10 million "from the Section 108 Loan, proceeds to be received from future Community Development Block Grant (CDBG) funds."

What the money buys

The Western Avenue Transformation District is the site of former public housing being rebuilt as mixed-income housing by the Housing Authority of South Bend and The Michaels Organization, with the Community Foundation of St. Joseph County as a partner, Molnar told the committee. The Redevelopment Commission memo describes the first phase as a planned 156-unit development, with 110 units reserved for households earning at or below 60% of the area median income.

The loan pays for the public side: "new utilities, a new road, and other public improvements," the commission memo says. On Aug. 25, the day after the council vote, the Board of Public Works awarded Indiana Earth Inc. of Osceola a $7,791,518 contract for that work, funded by the "HUD loan/River West TIF." Indiana Earth was the only bidder, the engineering firm that reviewed the bids wrote.

That firm, Jones Petrie Rafinski, put the combined budget for the construction contract, the earlier demolition of the Rabbi Shulman apartment building and its own design contract at $10.3 million: the $10 million HUD loan plus $300,000 in water funding.

Molnar told the committee the developer expected to start building the apartments in December and to begin leasing in spring 2028. The new internal street will be named Rabbi Schulman Place, he said.

No one spoke at the committee's public hearing on the loan, the minutes show.

What did you think of this story?

More stories about Housing Authority of South BendIndiana EarthJoe MolnarSouth Bend Common CouncilSouth Bend Redevelopment CommissionU.S. Department of Housing and Urban DevelopmentWestern Avenue Transformation District