How South Bend builds sidewalks with federal road money

The city runs the project, but the state lets the contract and signs off on each step. A Kennedy Academy job closed out about $231,000 under its award.

By South Bend Paper AI Desk · November 27, 2026 at 12:51 AM

Updated November 27, 2026 at 12:51 AM: Correction: An earlier version said the city pays for such projects up front. The records reviewed show the city pays a local match and expects part of the cost to be reimbursed through INDOT.

On Nov. 24, South Bend's Board of Public Works closed out a sidewalk project near Kennedy Academy by cutting $239,868.67 from the contract. The paperwork in front of the board was not the city's own form. It was an Indiana Department of Transportation change order, with an INDOT contract number, an INDOT area engineer and a "letting date."

That is how federally funded local projects work in Indiana. The city plans the work and pays a local match, but the state runs the bidding and approves the major steps. Here is how the Kennedy Academy job, part of the federal Safe Routes to School program, moved through that process.

The city becomes a 'local public agency'

In state and federal paperwork, the city is an "LPA," or local public agency. Before it can spend federal transportation money, it signs an agreement with INDOT to use it, the city's consultant contract for the project says. Each project gets a state designation number. Kennedy Academy's is Des. No. 2201237.

The city told the Common Council in April that it had secured federal money to rebuild 3.25 miles of sidewalk and 60 curb ramps built to Americans with Disabilities Act standards near Muessel Elementary School and Kennedy Academy, according to a Public Works update presentation.

The board signs a title sheet

On July 8, 2025, the Board of Public Works approved and signed a title sheet for the project, which the board's request form describes as an "INDOT-LPA project." The vendor listed on the form was INDOT itself.

The state takes the bids

The construction contract was let through INDOT, not by the city's board. INDOT's records list contract R-44776, a letting date of Nov. 13, 2025, and Rieth-Riley Construction Co. as prime contractor, at an awarded amount of $1,625,407.10. An earlier design estimate had put construction at $1,750,623.

A state-approved inspector

The city hired United Consulting, an Indianapolis firm, to inspect construction. Its contract, approved by the board Oct. 14, 2025, caps payment at $203,500. The firm's cover letter says part of that work is expected to be reimbursed by INDOT.

That contract had to clear INDOT first. United's cover letter lays out the steps: send a draft to INDOT's LaPorte District for approval, sign it, send the signed copy back, and wait until the state confirms that federal funding is authorized before the consultant may start. The package included INDOT letters prequalifying the firm and accepting its audited overhead rate, which the state uses to judge billing.

Changes still come to the board

When the work changed, the board still voted, on change orders a city engineer submitted "on behalf of INDOT," according to the board's Sept. 8, 2026 minutes. That day the board added $8,655.15 and 35 days to pay for removing pavement markings, which the original contract had not priced. The request form listed the city's match on that change as $1,731.03, or 20%.

The final count

The Nov. 24 change order was the last step: a final adjustment for any pay item that ran more than $20,000 over or under. All five went under. The contract had set aside $25,000 for stormwater protection that was never needed. Less full-depth asphalt patching, subgrade treatment, concrete for curb ramps and topsoil were used than planned. The contract ended at $1,394,193.58, about 14% below the award.

The Muessel Primary and Holy Cross project is following the same path. After its own second change order in September, that contract stood at $1,675,179.60, the minutes show.

What did you think of this story?

More stories about Indiana Department of TransportationRieth-Riley Construction Co.South Bend Board of Public WorksUnited Consulting