How South Bend helps owners pay to fix sidewalks and curbs

Owners are responsible under city code, but two programs share the cost. The council's neighborhood allocation falls to $1 million in 2027 from $1.6 million.

By South Bend Paper AI Desk · November 23, 2026 at 9:48 PM

If the sidewalk in front of your house is cracked or heaved by tree roots, fixing it is your job. Chapter 18, Article 3 of the South Bend Municipal Code makes the property owner responsible for maintaining and repairing the curb and sidewalk, according to a Public Works presentation to the Common Council in August.

The city does help pay, through two programs. One reimburses any owner who hires a contractor. The other, steered by council members, has the city replace sidewalks and curbs in low-income neighborhoods where they are in poor condition. Here is how each works, based on city records.

The reimbursement program

Any property owner inside city limits can apply, including landlords, businesses, churches and schools, city engineers told a council committee on Aug. 24. The city pays back part of the cost at a fixed rate per foot:

Repair Homeowner Target area Landlords, businesses, churches, schools
Curb $15 per ft $30 per ft $7.50 per ft
Sidewalk $20 per ft $40 per ft $10 per ft
ADA ramp $950 $950 $950

At those rates, a homeowner who replaces 50 feet of sidewalk would get $1,000 back, or $2,000 in a target area.

The target areas, chosen by income and sidewalk condition, earn double rates. The presentation says there were three for 2026; the committee minutes name two of them, one around Keller Park and the Morris Park Country Club area and one around Rum Village and Our Lady of Hungary. Owners there still pay part of the bill, project engineer Caitlin Wyant told Council President Canneth Lee.

The steps, from the city's presentation: get an estimate from a licensed, bonded contractor on the city's approved list; email it with an application to PWPrograms@southbendin.gov; wait for the city to inspect and pre-approve the job, which it says takes up to five business days; have the contractor pull any permits; then send proof of payment. The city inspects the finished work and mails a check. City Engineer Abigail Magas told the committee reimbursement arrives within six weeks of proof of payment.

The program had $150,000 for 2026, and Magas said the amount would stay the same in 2027. By late August it was 70% spent. The 2026 deadline for proof of payment was Nov. 6. Records reviewed for this story do not yet show when 2027 applications open; the city's Engineering office is at 574-235-9254 or 311.

The council allocation program

The second program costs owners nothing. Each council member picks properties in their district where curb and sidewalk are residential, existing, in poor condition and in low-income areas. City staff inspect and measure the picks, prepare a final list, and bid the work to a contractor, who gets a calendar year to finish.

That budget is shrinking. It was $1.6 million in 2026, enough for each member to choose up to 1,500 feet of sidewalk or 1,000 feet of curb, according to the minutes. For 2027 the city proposed $1 million, which Public Works said was part of budget reductions and would cover about 950 feet of sidewalk and 700 feet of curb per district at current prices.

Council members had until Oct. 16 to submit 2027 picks. Properties postponed from earlier years are selected automatically, Wyant said, and nominations that missed the 2026 list will be done in 2027. Councilmember Sharon McBride said some sidewalks buckled by tree roots on Roland Court, Haney Street and East Broadway had been bumped from the list repeatedly; Wyant said staff can re-rate long-postponed requests.

What the programs produced

The two programs replaced 16,615 feet of sidewalk and 12,593 feet of curb in 2025, Public Works reported in its annual report filed Oct. 30. That year 209 properties got new curb and sidewalk through the council program and 64 owners used the reimbursement program, up in footage from 2024, when 167 properties and 68 owners took part.

Curb and sidewalk replaced through South Bend's two programsLinear feet, council allocation and reimbursement programs combined
SidewalkCurb
05K10K15K20K14K7.8K202417K13K2025

Source: City of South Bend Department of Public Works annual reports, 2024 and 2025

The figures leave out streetscape projects and federal Safe Routes to School work, the report notes.

When a tree is the problem

Councilmember Karen L. White said she had heard from many residents who cannot afford to remove trees damaging curbs and sidewalks. Public Works Director Eric Horvath said the city's Venues, Parks and Arts department removes only hazardous trees in the right-of-way, and will set up a payment plan when a homeowner cannot afford the cost. Removal can run $2,000 to $4,000 a tree, he said, and he told the committee a dedicated program for lower-income residents would be beneficial. The records show no such program yet.

Streets are handled differently. Magas told the committee the city rates every street on a scale of 0 to 100 and paves the worst first, except for projects paid with location-specific tax increment financing (TIF) money, which is property tax growth set aside for a district. Council members do not pick which streets get paved, she said.

What did you think of this story?

More stories about Eric HorvathSouth Bend Common CouncilSouth Bend Department of Public Works