How South Bend holds back contractor pay until a job is done
State law has cities keep a slice of each payment, called retainage, until a public project is substantially finished. A $3.5 million subdivision job shows how it ends.
When South Bend hires a contractor to build a road, a pump station or a park building, it does not pay the whole bill as the work goes. It keeps back a small share of each payment, called retainage, until the job is substantially done and the city has signed off.
The point is leverage: the money the city holds gives the contractor a reason to finish the last items, fix defects and show that its subcontractors were paid.
What the law says
Indiana Code 36-1-12-14 governs retainage on local public works contracts over $200,000, except road, street and bridge work. For smaller contracts, the law lets a board such as South Bend's Board of Public Works choose to require it.
The law gives the board two ways to figure the amount:
- withhold no more than 6% of the value of work satisfactorily completed until the project is half finished, and nothing more after that, or
- withhold no more than 3% of the value of completed work until the project is substantially completed.
The contractor can choose to have the money held by the city or placed in an escrow account at a bank, savings and loan or the state. The city does not have to pay interest on retainage it holds itself.
Within 61 days after substantial completion, the city or escrow agent must pay the contractor. If minor items are still unfinished then, the law has the city keep twice the value of each item, as set by the project's architect or engineer, until it is done. The law was most recently amended in 2025.
What the city's contracts say
The city's standard public works quote documents, such as one used for a foundation job at Cross Community opened Oct. 27, 2026, cite that law and say the Board of Public Works will withhold a share of all satisfactorily completed work until the project is substantially complete and the board approves a project completion affidavit. The document's wording of the share is inconsistent: it reads "five percent (3%)."
Before the final payment and retainage are released, those documents require the contractor to:
- prove that all subcontractors were paid promptly, including recording the payments in the city's minority- and women-owned business tracking system,
- show that parts and labor meet the specifications,
- turn in test reports or product sheets for materials, and as-built drawings, and
- file a completion affidavit and a final lien waiver.
Bigger contracts can spell out their own terms. The city's $8 million guaranteed savings contract with Bowen Engineering for the Edison water plant, approved June 23, 2026, pays 95% of completed work, with the rest as retainage, and stops adding retainage once the job is half done if the work is going well. The city will not release retainage on that job without written consent from the contractor's surety, the company that bonds the work.
A local example
On Aug. 11, 2026, the Board of Public Works approved the completion affidavit for the streets and utilities that Rieth-Riley Construction built for the Youth Services Bureau and South Bend Thrive subdivision. The original $3,326,371.59 contract grew 6.61% through three change orders, to $3,546,311.69. In a memo to the board, Assistant City Engineer Jacob Klosinski said the work was complete and recommended releasing the retainage to Rieth-Riley. The memo said all closeout papers were in except a maintenance bond, which was expected by the meeting.
The city checkbook shows three payments to Rieth-Riley labeled for the project on Oct. 13, 2026, totaling $186,377.44. The checkbook does not say how much of that, if any, was retainage.
A few other checkbook entries name it directly. In 2025 the city recorded payments labeled retainage to Garmong Construction Services for the MLK Dream Center ($11,100), Rieth-Riley for curb and sidewalk work ($4,130.36) and Milestone Contractors for asphalt paving ($1,796.90).
More stories about Bowen Engineering CorporationRieth-Riley Construction Co.South Bend Board of Public Works
- Indiana Code 36-1-12-14, retainage on public work contracts (Counsel Stack)(opens in a new tab)
- Quote opening, Cross Community Foundation, Project No. 125-073A, Richard Custom Concrete (Board of Public Works, Oct. 27, 2026), with city quote specifications(opens in a new tab)
- Guaranteed Savings Contract, Edison WTP Improvements, Project 123-067, Bowen Engineering Corp. (Board of Public Works, June 23, 2026)(opens in a new tab)
- Project Completion Affidavit, Youth Services Bureau/South Bend Thrive Subdivision and Off-Site Improvements, Project No. 123-011, Rieth-Riley Construction (Aug. 11, 2026)(opens in a new tab)
- City of South Bend Checkbook Explorer (South Bend Transparency Portal): payments labeled retainage, and Rieth-Riley YSB/SB Thrive payments(opens in a new tab)
- City of South Bend finances dashboard (where the checkbook comes from)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.