Records show Imagineering fell short of 2016 equipment estimate
City reports list $464,659 in equipment spending against the metal finisher's 2016 estimate of $3 million, and the company did not file its 2024 compliance form.
Older records: Published November 3, 2026. The main records behind this story run through June 13, 2025.
When the South Bend Common Council granted Imagineering Enterprises two property tax abatements in September 2016, the metal finishing company said it would spend about $500,000 expanding its plant at 3722 Foundation Court and about $3 million on new equipment, and create 25 jobs.
A decade of city records shows the project changed shape. The company built a larger addition than first planned and reported more jobs than it promised, but put far less into equipment there. The council waived late paperwork on both abatements that would otherwise have cost the company a year of its breaks. In the city's most recent annual report, the equipment abatement is marked for failing to file a required compliance form. And in 2025, the company was sold.
The 2016 promise
The city's Department of Community Investment told the council in September 2016 that Imagineering, which then had two plants in South Bend and one in Indianapolis, would add an anodizing line and expected revenue to grow an estimated 15% to 20%. The staff reports said the project would create 25 full-time jobs with an annual payroll of $780,000 and retain 135 jobs.
Staff estimated the six-year real property abatement would save the company $7,635 in taxes and the five-year equipment abatement $118,589. An abatement phases in the taxes owed on new investment over several years.
The 2018 change
In a May 15, 2018, letter to the city, the company's chief financial officer, Joseph Rowan, wrote that Imagineering now expected to invest about $2.5 million across its two South Bend plants. At Foundation Court, it planned a building addition of about 15,500 square feet costing about $1.5 million, plus "Passivation" equipment costing $325,000 to $550,000. The anodizing line, about $450,000, would go to its plant at 1302 W. Sample St. instead. The company still projected about 25 jobs.
The company asked the council to extend the window to finish the project. The council approved both extensions on Sept. 10, 2018, each on a roll call vote of six ayes, according to the minutes.
"They didn't hit all of the marks," Councilmember Jo M. Broden said of Imagineering during the discussion, according to the minutes. James Mueller, then the city's executive director of community investment, answered that the change was "not changing the terms of the abatement at all, it's just changing the designating period."
What the records show since
The city's annual abatement reports for 2022, 2023 and 2024 show:
- Building: estimated cost $1.5 million; actual cost $1,767,004, completed April 16, 2019. The reports list 15 announced new jobs and 41 retained. Reported new jobs rose from 41 in the 2022 report to 71 in the 2024 report. The city rates this abatement fully compliant.
- Equipment: the reports still list the 2016 estimate of $3 million. The 2022 and 2023 reports show an actual cost of $464,659, completed Sept. 13, 2019. The 2024 report lists no actual cost or jobs and gives the abatement a compliance score of 5, which the report's legend defines as "Company failed to file Form CF-1." The legend says staff tried several times to get the form and recommends the council "consider this business non-compliant."
Source: City of South Bend annual tax abatement reports, 2022-2024
In May 2022, the council adopted two resolutions waiving the company's late filings. Each says Imagineering turned its compliance forms in to the city in May 2021 but "inadvertently failed" to file them on time with the St. Joseph County auditor, and that the company had met its objectives. The equipment resolution describes the 2018 plan as $550,000 in new equipment and 15 new or 41 retained jobs, a lower bar than the $3 million figure in the city's reports. The records reviewed for this story do not reconcile the two.
The equipment abatement's last tax year is payable in 2026, and the building's in 2028, according to the 2024 report.
The sale
In a March 28, 2025, letter to the Board of Public Works, the city's pretreatment manager wrote that "Toefco Engineering LLC (Toefco) purchased Imagineering Enterprises Inc." and that the new ownership would not change the plant's industrial processes. The board approved moving the Foundation Court wastewater permit to "Toefco Engineering LLC DBA Imagineering Enterprises LLC" on April 8, 2025.
The city's reports do not say whether the sale affected the missing 2024 filing. The company also holds a separate equipment abatement, granted in 2023, at its Sample Street plant, where the 2024 report shows it spent $2,990,940 against a $2,631,500 estimate.
Figures come from the 2016 staff reports, the company's 2018 letter, council minutes and resolutions, and the Department of Community Investment's annual abatement reports.
More stories about Imagineering Enterprises
- Bill 16-72: Designating Real Property Tax Abatement for Imagineering (staff report, petition)(opens in a new tab)
- Bill 16-74: Designating Personal Property Tax Abatement for Imagineering (staff report, petition)(opens in a new tab)
- Bill 18-47: Modifying and reconfirming resolution for Imagineering (includes company letter of May 15, 2018)(opens in a new tab)
- Bill 18-48: Modifying and reconfirming resolution for Imagineering (real property)(opens in a new tab)
- Common Council minutes, Sept. 10, 2018(opens in a new tab)
- Resolution 4958-22: waiving noncompliance, personal property, 3722 Foundation Ct.(opens in a new tab)
- Resolution 4959-22: waiving noncompliance, real property, 3722 Foundation Ct.(opens in a new tab)
- 2022 Annual Tax Abatement Report (June 15, 2023)(opens in a new tab)
- 2023 abatement report in 09-12-2024 Budget Meeting Questions (Answered)(opens in a new tab)
- 2024 Annual Tax Abatement Report (June 13, 2025)(opens in a new tab)
- Industrial Wastewater Discharge Permit Modification - Toefco Engineering (Board of Public Works, April 8, 2025)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.