McCormick plant reports 128 jobs after 2021 tax breaks
The spice maker pledged to keep 80 jobs and invest about $40 million in a Frank's RedHot line. City reports count $37.6 million, and the city later deeded it the land for $1.
Older records: Published November 15, 2026. The main records behind this story run through June 2025.
In 2021, McCormick & Company told South Bend it was weighing whether to close its West Lathrop Drive plant. Five years later, the city's own reports count more jobs there than the company promised to keep.
McCormick won two tax abatements in 2021 for an investment of about $40 million to add a new production line, pledging to retain 80 full-time jobs. The city's latest annual abatement report, filed in June 2025, lists 128 jobs at the plant and rates both breaks in full compliance.
That report covers 2024 and is the newest one the paper found; the city's report on 2025 was not among the records reviewed.
The pitch
The Department of Community Investment's May 18, 2021, report to the Common Council said the South Bend plant had recently lost a large piece of business tied to McDonald's North American account. The company was considering two options, the report said: close the plant, or add capacity with a retail glass Frank's RedHot line. It put the project's cost at $40 million to $42 million.
The company asked for a four-year property tax abatement on building improvements and a five-year abatement on new equipment, and estimated it would keep 80 permanent full-time jobs with a $3.3 million annual payroll. The department found the plant qualified for both under the city's ordinance. McCormick had received two earlier abatements at the site in 2011, the report noted.
At the council's May 24, 2021, meeting, plant manager Reginald Davis said the company had bought a fast-growing brand that was beating its growth expectations, so the plant needed to expand and add machinery, according to the minutes. Asked about new hiring, he said more jobs would come as volume grew. The council passed both declaratory resolutions 9-0 and confirmed the abatements 8-0 on June 14, 2021.
What the reports show
The abatements took effect for the 2025 tax payments, after the project was built, according to the city's reports. Each year the company files a compliance form with the city listing what it spent and how many people it employs.
| Abatement | Promised cost | Reported cost (2024 report) | Jobs promised / reported | City rating |
|---|---|---|---|---|
| Building (4 years) | $17,952,000 | $12,418,703 | 80 / 128 | Full compliance |
| Equipment (5 years) | $23,765,895 | $25,137,010 | 80 / 128 | Full compliance |
Together, McCormick reported $37.6 million against the $41.7 million on its two petitions. The equipment spending beat its estimate, while the building work came in about $5.5 million under.
The year before, in the report covering 2023, the company had reported $10.7 million in building costs and $14.8 million in equipment, with 112 jobs. The city rated the equipment abatement "substantially in compliance" that year, then in full compliance once spending passed the estimate.
The city's reports say an abatement applies only to improvements actually built, so when a company spends less than it planned, its tax break shrinks automatically.
A deed 48 years in the making
The tax breaks weren't the only paperwork. On May 14, 2024, the Board of Public Works approved a quitclaim deed giving McCormick the 3425 Lathrop site for $1.
The resolution says the city and McCormick signed a lease on June 1, 1976, that promised to transfer the property for $1 once the company met its financial obligations. McCormick finished those in 2001, the resolution says, but the transfer was never recorded, which the city and the company called an oversight. McCormick had paid property taxes on the site throughout, the resolution says.
As a condition of the transfer, McCormick signed an agreement to indemnify the city for environmental problems caused by its own use of the property since 1976.
More stories about South Bend Board of Public WorksSouth Bend Common CouncilSouth Bend Department of Community Investment
- Bill 21-29 packet: DCI letter and tax abatement report, petition and Statement of Benefits, McCormick & Company (May 18, 2021)(opens in a new tab)
- Common Council meeting minutes, May 24, 2021(opens in a new tab)
- Common Council meeting minutes, June 14, 2021(opens in a new tab)
- Resolution 4913-21, confirming four-year real property abatement, McCormick & Company (June 14, 2021)(opens in a new tab)
- Resolution 4915-21, confirming five-year personal property abatement, McCormick & Company (June 14, 2021)(opens in a new tab)
- City of South Bend 2022 Annual Tax Abatement Report (June 15, 2023)(opens in a new tab)
- Department of Community Investment budget answers with 2023 tax abatement report (Sept. 12, 2024)(opens in a new tab)
- City of South Bend 2024 Annual Tax Abatement Report (filed June 13, 2025)(opens in a new tab)
- Board of Public Works Resolution 16-2024, property conveyance to McCormick & Company, with environmental indemnification agreement (May 14, 2024)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.