Pure Green Farms expansion unstarted as tax-break deadline nears

The council extended two 2022 tax breaks for an $80 million greenhouse expansion to Dec. 31, 2026. The city's latest abatement report lists the project as not started.

By South Bend Paper AI Desk · November 18, 2026 at 12:49 AM

Older records: Published November 18, 2026. The main records behind this story run through June 13, 2025.

In early 2022, the South Bend Common Council approved two tax breaks for an expansion of Pure Green Farms, the hydroponic lettuce greenhouse at 3820 W. Calvert St. on the city's southwest side. The company promised to build a $12 million second greenhouse, buy $68 million in equipment and add 75 full-time jobs.

Nearly three years later, the expansion had not begun. In January 2025 the council voted 9-0 to extend both tax breaks to Dec. 31, 2026, after city staff said the project had been delayed. The city's most recent annual tax abatement report, filed June 13, 2025, still lists both the real property and equipment abatements as "Not Started."

That report is the newest public record the paper found on the expansion's status. It is about 17 months old, and newer city records on the project were not found. The extended deadline is now six weeks away.

What was promised

Greenleaf Holdco LLC, which does business as Pure Green Farms, asked for the breaks in January 2022. A tax abatement lets a business phase in property taxes on new buildings or equipment over several years.

The council's resolutions gave the company a nine-year abatement on a new greenhouse and a five-year abatement on new equipment. Under its memorandum of agreement with the city, the company committed to spend at least $12 million on the building and at least $68 million on equipment, to keep its 25 existing full-time jobs and to create at least 75 more "within the first three years of the tax abatement," paying at least $15 an hour.

A Department of Community Investment staff member, Angelina Billo, told a council committee on Jan. 24, 2022, that the property-tax break would forgo an estimated half a million dollars. A department presentation in August 2023 estimated the equipment break at $4,834,800 in taxes abated over five years. Neither break has taken effect, because nothing has yet been built or bought under them.

Earlier city help

The tax breaks were the second round of city support. In October 2020 the Redevelopment Commission signed a development agreement to pay up to $500,000 in tax increment financing, or TIF, for paving, a retention pond and landscaping at the site. TIF uses the growth in property taxes inside a district to pay for projects there. The company pledged at least $15.5 million in private investment and 20 new jobs within 24 months, and agreed to file job reports with the commission.

In October 2022 the commission raised the city's share to $657,000, mostly for electrical equipment, and the company raised its investment pledge to $25 million. At that meeting, Matt Barrett, listed in the minutes as a resident, "questioned the terms of the original agreement and accountability." According to the minutes, Joe McGuire, the company's CEO, said the reports had not been filed but that the company had "exceeded the original number of 30 with 45" jobs, and said he would work with staff to file them. The paper did not find those reports in the city's public records.

City checkbook records show $448,664 in Community Investment capital payments labeled for Pure Green Farms between May 2023 and August 2024, including $107,008 to AEP for electrical work and payments to C&E Excavating and Engineering Resources.

The 2025 extension

In a Jan. 8, 2025, letter to the council, Erik Glavich, the city's director of growth and opportunity, wrote that "the expansion project has been delayed" and that a company representative said it "is scheduled to begin by mid-2025, and the previously granted tax abatements are necessary for the project to move forward." The reconfirming resolutions say construction "was delayed by project development challenges and other issues outside of the control of Greenleaf Holdco LLC" and that the company had "not yet purchased and installed equipment" that would qualify. The company's new filing listed an April 1, 2025, start and a Dec. 31, 2026, finish.

At the council meeting Jan. 13, 2025, McGuire said the company had already invested $20 million to $25 million and would reach "closer to fifty million dollars" after the project, according to the minutes. He confirmed that the expansion would take production from 2 million to 8 million pounds of lettuce a year.

Dr. Robert Bennett, who lives on O'Brien Street, spoke against the bills and "raised concerns of low wages," the minutes say. McGuire responded that the typical starting wage is $15 an hour and that most employees are from the South Bend area. The minutes record no other public speakers. Council members praised the company, and both resolutions passed 9-0.

Under the agreement, the city can end the abatements if the company does not substantially comply with its commitments. Records do not show whether construction began in 2025.

What did you think of this story?

More stories about Erik GlavichSouth Bend Common CouncilSouth Bend Department of Community InvestmentSouth Bend Redevelopment Commission

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.