Radio company didn't file tax break report, city says

The broadcaster behind WSBT radio met its building goals at 316 E. Monroe St., city reports show, but did not file a required form for its equipment break.

By South Bend Paper AI Desk · November 12, 2026 at 9:53 PM

Older records: Published November 12, 2026. The main records behind this story run through June 2025.

The radio company that moved four stations into a vacant building at 316 E. Monroe St. in 2021 has met its promises on the building itself, according to South Bend's latest tax abatement report. But the city lists the company's separate break on broadcast equipment as one where it failed to file a required annual form, and city staff recommended the Common Council consider it noncompliant.

The report, filed with the council in June 2025, covers 2024. It is the newest such report found in city records; the 2025 report, which would cover last year, was not found.

What was promised

WSJM Inc., which also goes by Midwest Family Broadcasting, asked for three five-year tax breaks in April 2020: one for the vacant building, one for renovating it and one for new telecommunications and network equipment. A May 6, 2020, letter from Dan Buckenmeyer, then the city's director of business development, said the company planned to move its regional headquarters and four stations, WSBT, WNSN, WZOC and WQLQ, into the 18,185-square-foot building, with four studios and offices.

The company proposed buying the building for $235,000, spending about $2.5 million to renovate it and $800,000 on equipment, a total of about $3.5 million, the letter said. The city's report said the building had been vacant more than a year and that its outdoor heating and cooling equipment had been destroyed by vandalism and theft. The company estimated it would bring 23 full-time jobs to South Bend, with a payroll of about $1 million, and create three more within three years.

The Common Council confirmed all three abatements on May 26, 2020, each by a 9-0 vote. Bill Gamble spoke for the company, and no one spoke for or against at the public hearings, the minutes say.

What the reports show

The city's annual reports rate the renovation and vacant-building breaks in full compliance. The latest lists $2.78 million in actual project costs against a $3.1 million estimate, completion on Sept. 15, 2021, about six weeks after the planned date, and 26 retained jobs against 23 announced. The report for 2022 had counted 25 retained jobs and six new ones, against three promised.

The equipment break is different. Reports for 2022 and 2023 listed it in compliance, though with different spending figures: $1.58 million in the first and $720,322 in the second, against a $650,000 estimate. In the 2024 report, the line shows no actual figures and a compliance score of 5, which the report defines as a company that failed to submit its annual Form CF-1 after staff tried several times to reach it. For those, the report says, staff recommend the council consider the business noncompliant.

The posted records do not show any council action on that recommendation, and they show no response from the company. All three breaks run through taxes payable in 2027, the report says.

A tower and a land sale

Later that year the company sought permission for a 189-foot monopole beside the building. The Board of Zoning Appeals sent the request to the council with a favorable recommendation in September 2020; its staff wrote that the tower would help reuse the site for a local broadcaster.

In June 2022, the Board of Public Works agreed to buy seven nearby parcels from WSJM, on the 300 block of East Monroe Street and on South Carroll Street, for $29,000, after two appraisals. The board's letter said the land was for future development of the Monroe Park neighborhood. An August 2022 amendment clarified the legal description and kept the $29,000 price.

What did you think of this story?

More stories about South Bend Board of Public WorksSouth Bend Board of Zoning AppealsSouth Bend Common CouncilSouth Bend Department of Community Investment

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.