The Board of Public Works on Nov. 10 added a $34,250 land survey to first-phase design work, raising the engineering contract to $179,935.
The only mountain bike item in the first-phase contracts for Rum Village Park is a fence.
It is $4,575 worth of split-rail fencing at what city records call the "Rum Village Mountain Bike Trailhead." The new trail once sketched into the park's master plan, through its old-growth forest, is no longer there.
"The proposed mountain bike trail through the old growth forest area of the park has been removed from the plan because of public feedback," say the June 22 minutes of the Ecological Advocacy Committee, a city panel that had voted to oppose the trail's design.
What the first phase buys instead came into sharper focus Nov. 10. The Board of Public Works approved a $34,250 amendment for a full topographic survey, which maps the lay of the land. That raises the city's design contract with Jones Petrie Rafinski Corp. to $179,935, about 23.5% more than the $145,685 the board approved Aug. 25.
A trail meets resistance
Council Vice President Sheila Niezgodski, of the 6th District, announced at the Jan. 26 Common Council meeting that a public input meeting on the Rum Village Park Master Plan would be held Jan. 29.
By March 16, objections had reached the Park Board.
Clay Kusbach of North Liberty, newly appointed chair of the Ecological Advocacy Committee, addressed the board. The committee had voted Feb. 23 to authorize him to do so. According to the minutes, the proposed trail was planned for an area of sensitive champion trees and critical habitat that had been identified earlier.
"The early conceptual plans of the trail conflict with the guiding principles and practices outlined in the VPA 2021 Natural Resource Management Plan," the minutes say. VPA is Venues Parks & Arts, the city's parks department.
The minutes also say Rum Village Forest "is uniquely diverse in its native flora and fauna," and that local bird alliance groups have documented dozens of bird species, several of them rare.
The committee, the minutes say, "has voted to oppose the current trail design and called for engagement with ecological experts and community partners to develop alternative improvement plans."
Deb Marr, who lives on Eastwood Side Street, praised parts of the plan: increased access, accessibility under the ADA, or Americans with Disabilities Act, a playground updated with more natural materials and roads made safer for pedestrians.
Her concern, the minutes say, was that "doubling the number of trails" would harm a high-quality forest ecosystem, compact soil, fragment understory vegetation and hurt rare plants and wildlife. She urged alternatives for the mountain bike trail.
Jennifer Betts, who lives on Cottage Road and chairs the South Bend Bird Alliance, asked for more time for input from groups such as Wild Ones, the Ecological Advocacy Committee and other conservation groups before the plan was finalized.
"She shared there are a lot fears within the ecological community," the minutes say.
Bruce Cates, who lives on North Crescent Avenue, raised a separate objection. He objected to the term "zones of interest" on display images at the Jan. 29 meeting, noted its historical association with Auschwitz and recommended it be changed, according to the minutes.
Others followed. "Multiple additional residents, ecological advocates, and organizational representatives voice strong opposition to the proposed mountain bike trail in Rum Village," the minutes say. Those speakers are not named in the minutes.
The city's answer
Jordan Gathers, then executive director of Venues Parks & Arts, responded at the same meeting.
According to the minutes, Gathers "reiterated the city's commitment to ecological restoration and native plantings in Rum Village," clarified "that the Master plan remains conceptual," and "assured continued community engagement and protection of the park's natural character."
Bike trails already exist in the park. On May 26, the Common Council's Zoning and Annexation Committee heard a bill to rezone several Rum Village Park parcels, owned by Venues Parks & Arts, from suburban neighborhood to open space.
Asked whether that was consistent with the master plan, zoning specialist Mark Dellostritto said the parcels "are currently used as bike trails, and there may be some expansion of the trails," according to the minutes. He said zoning staff was working with Venues Parks & Arts to finalize the plan. Nobody spoke at the public hearing.
On June 9, Niezgodski announced an open house the next evening to view the final draft.
"After about a year of community engagement, careful listening, and consideration of many residents, organizations, and neighbors, I am very happy to welcome the community to view the final plan for Rum Village Park," she said in a June 9 news release.
By June 22, the Ecological Advocacy Committee's minutes recorded the trail's removal. Members had attended park board meetings and open houses to give individual feedback, the minutes say. The same minutes introduce Erin Thornton as the newly appointed executive director of Venues Parks & Arts.
What the first phase buys
First, a road. "Phase 1 is underway at Rum Village, where visitors can now enjoy the newly paved park road," the Park Board's Sept. 21 minutes say.
A day later, at a council budget hearing, Venues Parks & Arts said road improvements were under way "as part of the first (1st) phase of the recently adopted Rum Village Park Master Plan," according to the minutes. Thornton listed continuing enhancements at the park among the department's priorities.
The Aug. 25 design agreement covers six pieces of work. The largest estimated share, $46,220, goes to designing a nature center renovation. Trail improvements labeled ADA are next at $36,370. The smallest, $8,040, is for replacing the disc golf pavilion.
Those are design fees, and the agreement lets the engineer alter the split.
Source: City of South Bend Board of Public Works agreement, Aug. 25, 2026
The fence was awarded the same day. The city asked four firms for quotes and three answered. Custom Fence Company of Niles, Michigan, quoted $4,575. Schuell Fence Company quoted $7,350 and Milestone Fence LLC $7,358.
The records leave a good deal out. They do not show the full text of the final master plan. They show no construction cost estimate for the full plan or for the first phase beyond these contracts, and no cost for the road paving. They give no date for a next phase.
A center nearby
A second project is moving a short distance away. On July 27, the Common Council voted 9-0 for Bill 26-20, a neighborhood bond.
Joe Molnar, deputy director of Community Investment, said the bond would fund converting the former William Penn building on Indiana Avenue into a Rum Village Neighborhood Center. The city acquired the building earlier in 2026, and the Boys & Girls Club is a partner.
The bond presentation says the neighborhood "has no community center currently" and estimates the cost at $3 million to $4 million. Molnar said after-school activity space has been the top community request and that the hope is to begin construction by mid-2027. The center was called for in the Rum Village Neighborhood Plan, which the council adopted in October 2022.
Duane Wilson, CEO of the Boys and Girls Club, said the club intends to make it an intergenerational community space. Patti Huettl, treasurer of the Rum Village Neighborhood Association, said board members are all in favor.
Evelyn Gills, the association's vice president, noted the neighborhood's many children and seniors. The center, the minutes record her saying, "is something they have wanted for a long time."
More stories about Rum Village Neighborhood CenterSheila NiezgodskiSouth Bend Board of Public WorksSouth Bend Ecological Advocacy CommitteeSouth Bend Park BoardSouth Bend Venues Parks & Arts
- South Bend Park Board minutes, March 16, 2026(opens in a new tab)
- South Bend Ecological Advocacy Committee minutes, June 22, 2026(opens in a new tab)
- Councilmember Sheila Niezgodski news release, June 9, 2026(opens in a new tab)
- Common Council Zoning and Annexation Committee minutes, May 26, 2026(opens in a new tab)
- Board of Public Works minutes, Aug. 25, 2026(opens in a new tab)
- Professional services agreement, Rum Village Phase 1 Improvements, Project 126-054, Jones Petrie Rafinski Corp.(opens in a new tab)
- Quote award, Rum Village Phase I split-rail fencing, Custom Fence Company, Aug. 25, 2026(opens in a new tab)
- Amendment No. 1, Jones Petrie Rafinski agreement, approved Nov. 10, 2026(opens in a new tab)
- South Bend Park Board minutes, Sept. 21, 2026(opens in a new tab)
- Common Council Personnel & Finance budget meeting minutes, Sept. 22, 2026(opens in a new tab)
- Common Council meeting minutes, July 27, 2026 (Bill 26-20)(opens in a new tab)
- 2026 neighborhood bond presentation to Common Council, July 27, 2026(opens in a new tab)
- Common Council meeting minutes, Jan. 26, 2026(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.