South Bend's Amazon NDA is tied into a 10-year sewer contract
The contract keeps the 2023 agreement's terms in force after it expires, and Bill 67-26, up for a vote Monday, would order a city attorney review.
The confidentiality deal behind South Bend's sewer service to Amazon's New Carlisle data centers is older than the city has described in public, and it is tied into a contract that runs at least until 2035.
A council leader told a committee in September that the city's one active nondisclosure agreement with Amazon "is set to expire at the end of the year." But the city's wastewater service agreement with Amazon Data Services, approved by the Board of Public Works on Dec. 17, 2024, names a "Non-Disclosure Agreement by and between Amazon.com, Inc. and the City of South Bend, dated 12/27/2023." And it says that if that NDA "expires or is terminated during the Term and is not renewed or replaced, the terms of such prior NDA will continue to apply" to the parties' activities under the contract "until a new NDA is executed."
That matters for Bill 67-26, the ordinance the Common Council takes up for a public hearing and final vote Monday, Nov. 9. As filed, it would order the city attorney to review every confidentiality arrangement the city entered into before Sept. 14, 2026, and to start "immediate legal challenges or termination proceedings" against any that don't comply with the ordinance or Indiana's public records law. The 2023 NDA and the 2024 contract both predate that cutoff.
What the city said
At a joint council committee meeting Sept. 8, Council Member Sherry Bolden-Simpson asked whether the permit information for the Amazon data center is public. Public Works Director Eric Horvath said the city entered a nondisclosure agreement with Amazon "because this was the first (1st) hyperscale data center permit the City had ever written, and access to confidential operational information was needed to design the permit appropriately," according to the minutes. He said he does not foresee that being necessary for a similar facility in the future.
On Sept. 28, Council President Canneth Lee told the Personnel and Finance Committee "that there is currently one (1) active NDA between the City and Amazon, and it is set to expire at the end of the year," the minutes say. The minutes do not say whether that is the Dec. 27, 2023, agreement named in the sewer contract.
What is public
Much of the paperwork is posted in the city's online records.
The service agreement. The 17-page Wastewater Service Agreement covers three Amazon sites in the Indiana Enterprise Center east of New Carlisle, known as IEC Sites 2, 3 and 4. It took effect Jan. 1, 2025, for an initial 10-year term and then renews automatically for one year at a time unless Amazon gives notice. Amazon may end it on 90 days' notice. The city may end it only if the project stops data center operations for more than 12 straight months, at least three years have passed, and the city has paid Amazon what it owes. Amazon pays the city's standard sewer rates under the municipal code. The agreement caps peak discharge into the sanitary sewer at 2,800 gallons per minute.
Every page of the contract as posted carries the header "AMAZON CONFIDENTIAL." Besides the NDA clause, it says the city will not issue "any public announcement, press release or public statement" about the agreement without Amazon's written consent. That consent is "not to be unreasonably withheld." The city may share information that Amazon has already made public when a third party asks for it. Both the confidentiality and announcement clauses survive the agreement's end, the contract says.
The wastewater permit
The Board of Public Works approved Amazon Data Services' industrial wastewater discharge permit on Jan. 14, 2025. The posted copy describes a multibuilding data center that uses non-contact cooling water from April through September and runs 24 hours a day. It classifies Amazon as a "Significant Industrial User" discharging more than 100,000 gallons a day. It sets numeric limits for pH, mercury and oil and grease, requires monthly sampling for metals and other pollutants, and was set to expire May 31, 2026. A March 2025 letter from the city's pretreatment manager added equipment wash-down water to the permit after what it called a "scrivener's error" on Amazon's application. The seven-page posted copy appears to be incomplete: its pages are numbered 4, 5, 7 and 10.
The renewal. On May 26, 2026, the Board of Public Works approved permits for two Amazon entries, "Amazon Data Services, Inc. DBA IEC 3" on State Road 2 and the original Edison Road site. According to the minutes, it was clarified during discussion that the item was a short-term extension of the earlier permits with no other changes. The renewed permits are not among the files in the city's posted Board of Public Works records, and the minutes do not give a new expiration date.
The numbers. In his Sept. 8 presentation, Horvath said Amazon ranks 11th among the city's 12 largest wastewater customers by volume, at about 0.03 billion gallons a year, or 0.28% of the city's 10.9 billion gallons of annual flow. He said the discharge is mostly cooling water plus sanitary sewage from workers, is separately metered, and pays a 14% surcharge for customers outside city limits, according to the minutes.
What is not public
The NDA itself is not among the city's posted records, so its terms are unknown. That includes what information it covers, how long it lasts and whether it limits what the city can release under Indiana's Access to Public Records Act. Neither is the "confidential operational information" Horvath said the city needed to write the permit. The South Bend Paper has not obtained the agreement.
Would Bill 67-26 reach it?
On its face, the bill's review section covers the Amazon agreements. It applies to "every such arrangement entered into by any City Department ... prior to September 14, 2026." It describes those arrangements broadly: "any Non-Disclosure Agreement, confidentiality agreement, contract, or any other arrangement by whatever name" that restricts public disclosure about city government. Another section bars any such agreement about "the development, construction, zoning, or tax abatement of technology data centers." The bill would also bar the city from renewing such an agreement. Mayor James Mueller's Sept. 16 executive order separately bars city departments from renewing or extending data center agreements that restrict disclosure beyond what the law requires.
Whether a review would void the Amazon deal is not settled by the text. The bill says a noncompliant arrangement "is deemed void ab initio," meaning invalid from the start, and directs the city attorney to challenge it. It does not address a contract like this one, whose own terms keep an expired NDA in force. The city's posted materials for Monday's meeting include no written comment from the administration or the Legal Department on how the bill would apply to existing contracts.
Concerns about Amazon and confidentiality agreements were raised in public before the council took them up. At a St. Joseph County Board of Commissioners meeting on Dec. 30, 2024, Dan Caruso of New Carlisle spoke "about Amazon and the non-disclosure agreements," the county's minutes say.
More stories about AmazonCanneth LeeEric HorvathSouth Bend Board of Public WorksSouth Bend Common Council
- Wastewater Service Agreement - Amazon Data Services, Inc., approved by the Board of Public Works Dec. 17, 2024(opens in a new tab)
- Industrial Wastewater Discharge Permit - Amazon Data Services Inc., approved Jan. 14, 2025, with March 20, 2025 correction letter(opens in a new tab)
- Board of Public Works agenda, May 26, 2026(opens in a new tab)
- Board of Public Works minutes, May 26, 2026(opens in a new tab)
- Community Investment and Personnel & Finance joint committee minutes, Sept. 8, 2026(opens in a new tab)
- Public Works presentation to joint committee, Sept. 8, 2026(opens in a new tab)
- Personnel & Finance Committee minutes, Sept. 28, 2026(opens in a new tab)
- Bill 67-26, Prohibiting NDAs, as posted for Nov. 9, 2026(opens in a new tab)
- Executive Order No. 01-2026, Data Center Transparency & Accountability Order(opens in a new tab)
- St. Joseph County Board of Commissioners minutes, Dec. 30, 2024(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.