South Main apartment rehab finishes under 2023 tax break
City records list the fire-damaged 1915 building as finished in May 2025, more than a year late and $70,000 under its cost pledge, with its tax break starting in 2026.
Older records: Published November 29, 2026. The main records behind this story run through June 2025.
The fire-damaged apartment building at 536 S. Main St., across from the Transpo building downtown, was rebuilt for about $2 million and finished in May 2025, according to the city's most recent annual tax abatement report. The work came more than a year after the date its owner gave when the Common Council approved an eight-year property tax break in 2023.
The report, filed with the council June 13, 2025, rates the project "in compliance." It is the newest annual abatement report in the city's posted records; a report covering 2025 was not found, so the records in this story are about six months to a year old.
What was promised
SoMa Capital LLC, whose co-manager is Mark Neal, petitioned for the abatement in February 2023. The Department of Community Investment's report to the council said the brick building, built in 1915, had been vacant since a summer 2021 fire, after an earlier fire, and had "fallen into neglect due to serious deferred maintenance."
The plan was to turn what had been 8 apartments into 12: four studios, five one-bedrooms and three two-bedrooms, with new plumbing, electrical, fire and heating systems, new windows and a restored brick facade. The department's report said at least three units would be affordable to low- and moderate-income households earning up to 80% of the area median income. Neal's petition said leasing would target entrepreneurs and small-business owners.
The council confirmed the abatement 9-0 on March 13, 2023, as Resolution 5006-23, according to the meeting minutes. The minutes say the city presented a private investment commitment of $2.065 million, and that Neal told council member Lori Hamann the company had agreed to rent 3 of the 12 units at the income limit. No member of the public spoke.
The city estimated the abatement would save the owner $213,157 in property taxes over eight years, with $129,693 still paid. The break phases down from 100% in the first two years to 85% in the last two.
What the records show since
The city's report on 2023, included in the Department of Community Investment's September 2024 answers to council budget questions, listed the project as "Not Started," with completion expected March 31, 2024.
The 2024 report lists an actual cost of $1,995,000, about 3% below the $2,065,000 estimate, and an actual completion date of May 15, 2025. It shows the tax break taking effect for taxes payable in 2026 and running through 2033. The report rates the project "1," which its key defines as a company "in compliance with all goals." The petition listed no jobs.
The annual report does not track whether the three affordable units are rented at the promised income level, and the records reviewed do not show a check of that commitment.
Part of a larger block
The apartments are one piece of a project with the former Salvation Army building next door at 510 S. Main St. In August 2024, the Redevelopment Commission approved a development agreement with SoMa Capital and Momentum Development Group, which the agreement describes as under common ownership. It caps the commission's spending at $475,000 in tax increment financing (TIF), the property tax growth captured in a district, for public improvements such as parking lot repairs, lighting and fencing, against at least $5,825,000 in private investment.
In December 2025, the commission issued a certificate of completion for the Salvation Army building, saying Momentum spent more than $6 million and met its construction deadlines. The records reviewed do not show how much of the $475,000 in TIF has been spent.
More stories about Momentum Development GroupMomentum Entrepreneurship HubSouth Bend Common CouncilSouth Bend Department of Community InvestmentSouth Bend Redevelopment Commission
- Bill 23-06 / Resolution 5005-23, designating 536 S. Main St. for SoMa Capital LLC abatement, with DCI tax abatement report, schedule and petition (Feb. 22, 2023)(opens in a new tab)
- Bill 23-09, confirming resolution for 536 S. Main St. (filed March 8, 2023)(opens in a new tab)
- Resolution 5006-23, confirming eight-year real property tax abatement, SoMa Capital LLC (March 13, 2023)(opens in a new tab)
- South Bend Common Council minutes, March 13, 2023(opens in a new tab)
- DCI budget meeting answers with 2023 Annual Tax Abatement Report (Sept. 12, 2024)(opens in a new tab)
- City of South Bend 2024 Annual Tax Abatement Report (filed June 13, 2025)(opens in a new tab)
- Redevelopment Commission packet, Aug. 8, 2024 (Development Agreement, Momentum Development Group/SoMa Capital)(opens in a new tab)
- Redevelopment Commission minutes, Aug. 8, 2024(opens in a new tab)
- Redevelopment Commission minutes, April 13, 2023(opens in a new tab)
- Certificate of Completion, Momentum South Bend, 510 S. Main St. (Dec. 11, 2025)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.