Steel Warehouse's 2022 mill tax break still listed as not started

Three yearly city reports show no spending on the $3.7 million mill upgrade. In 2024 the council approved two more breaks for a $14 million production line.

By South Bend Paper AI Desk · November 27, 2026 at 9:54 PM

Older records: Published November 27, 2026. The main records behind this story run through June 2025.

A tax break the South Bend Common Council approved for Steel Warehouse Co. in October 2022 has been listed as "Not Started" in each of the city's three yearly tax abatement reports since, most recently in a report filed in June 2025.

The five-year break covered about $3.7 million in new equipment for the company's cold reducing mill on its West Tucker Drive campus. The city's reports list an expected completion date of July 1, 2023, and no actual cost or completion date.

The most recent report covers 2024 and is the latest one in the city's records. A report covering 2025 has not been found.

What the company proposed

Steel Warehouse, a family-owned steel service center that started in South Bend in 1947, told the city the upgrade was needed to "remain competitive in the markets that the mill serves," according to a July 2022 company memo signed by Gerald Lerman, its vice president and general counsel.

The memo listed new guides, gauges, hydraulics and electrical work for the mill, a new mill foundation, upgrades to a nearby slitting line and a 3,600-square-foot shipping bay. It said the mill and slitting line work would take up to a year and cost $3,913,000, with the shipping bay about $216,000 more. It said the company expected to add eight to 10 employees over three years once the work was done.

In its petition, the company said it would keep 513 jobs at the Tucker Drive facility and create 10 to 12, with at least $367,756 in new annual payroll. The Department of Community Investment's report said the project would let the company hire 10 to 12 workers.

The council confirmed the break on Oct. 24, 2022, in Resolution 4982-22. It phases in taxes on the new equipment over five years, starting with 100% of the value abated in year one and falling to 80% in year five. The resolution limited the area's designation for the break to three calendar years from the council's first, declaratory resolution, adopted in 2022.

A new, larger project

In April 2024 the council approved two more breaks for Steel Warehouse on the same campus: a five-year break on $9.05 million in equipment for a heavy-gauge leveling and cut-to-length line, and a six-year break on a new 30,852-square-foot building estimated at $3.5 million. The city said the total investment would top $14 million.

The company's agreement with the city commits it to spend at least $9 million on that equipment and to create at least 11 full-time jobs with $566,134 in annual payroll. A city official told the council committee the project would keep 21 jobs at that location and add the 11 by the end of 2027.

At the committee's April 22, 2024, hearing, Randy Parsons, the company's general manager, thanked members for considering the request, the minutes show. No one spoke at the public hearing, and the committee sent both breaks to the full council with favorable recommendations.

The 2024 report lists the new equipment break as not started, with an expected completion of June 1, 2025, and lists 2026 as the first tax year for the building break.

What the records don't show

The city's letters, presentation and committee minutes for the 2024 breaks do not mention the 2022 mill project. The records reviewed show no explanation from the company or the city for why the 2022 project is listed as not started.

What did you think of this story?

More stories about South Bend Common CouncilSouth Bend Department of Community InvestmentSteel Warehouse