Third change order would push trail contract past $4.5 million

Rieth-Riley's Hill Street and South Bend Avenue leg of the Notre Dame-to-downtown trail has grown 10.4% since its 2024 award, led by a $216,000 retaining wall.

By South Bend Paper AI Desk · November 10, 2026 at 12:50 PM

South Bend's Board of Public Works was scheduled Tuesday to consider a third change order on Rieth-Riley Construction Co.'s contract for the Hill Street and South Bend Avenue section of the trail linking downtown and the University of Notre Dame. It would add $46,950.15 and bring the contract to $4,502,483.86, according to the board's Nov. 10 agenda.

That is 10.42% more than the board awarded in April 2024. The agenda lists the amounts but does not say what the new work is, and the supporting change-order document was not yet in the city's public records archive. Minutes of Tuesday's meeting had not been posted.

How the contract grew

The board awarded the job, Project No. 122-040B, to Rieth-Riley on April 23, 2024, for $4,077,697.59, base bid plus two alternates. It was the lowest of three bids; Milestone Contractors North bid $4,475,780 and HRP Construction $4,717,108, and all three came in under the engineer's estimate, according to a city engineering memo.

Each change order since has added to it:

Change orders on the trail's Hill St.-South Bend Ave. contractAmount added by each change order, nominal dollars
$0$100K$200K$300K$400K$54KNo. 1 (Oct. 2024)$326KNo. 2 (July 2026)$47KNo. 3 (on Nov. 10 agenda)

Source: South Bend Board of Public Works change orders and agenda

  • Change order No. 1, approved Oct. 8, 2024, added $53,699.91 for water services for Notre Dame's Veldman Psychology Clinic in the 500 block of Hill Street, wayfinding signs and grading adjustments. It also moved the completion date 28 days, from Nov. 1 to Nov. 29, 2024.
  • Change order No. 2, approved July 14, 2026, added $326,005.16. Two-thirds of that, $215,937.78, was for an added retaining wall. Other items included $39,062.40 to restore a parking lot near the wall, a $24,102.64 water service, a sanitary sewer line, bollards, flashing stop signs, relocating an AT&T pedestal and powder-coated signs. The city's request form says it covered sewer laterals and water services "for the Yard development." Charlie Brach of the city's engineering division told the board it was for "additional utility work, creation of a retention wall, and miscellaneous finishing touches," according to the minutes. The board approved it on a motion by Joseph Molnar, seconded by Murray Miller.

Change order No. 2 added no time, and records found do not show a completion date later than Nov. 29, 2024.

The agenda's figures for No. 3 imply a starting contract of $4,455,533.71, which is $1,868.95 less than the $4,457,402.66 the board approved in July. The agenda does not explain the difference.

Who pays

The original award was charged to the city's gift, donation and bequest fund. The change orders list River East TIF as their funding source. TIF, or tax increment financing, sets aside growth in property taxes within a district to pay for projects there.

City checkbook records show nine payments to Rieth-Riley labeled for the trail from July 2024 through Sept. 22, 2026, totaling $4,277,423.49.

A separate Milestone Contractors contract covers the Notre Dame Avenue section of the trail.

What did you think of this story?

More stories about Downtown-Notre Dame TrailRieth-Riley Construction Co.River East TIF districtSouth Bend Board of Public Works

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.