Toyo Seiko falls short on equipment pledged for tax breaks
The 2019 petition promised $1.05 million in equipment, and the city's latest report lists $280,640, though the $2.1 million building beat its $1.6 million plan.

Older records: Published November 6, 2026. The main records behind this story run through September 30, 2025.
When Toyo Seiko North America asked South Bend for tax breaks in November 2019, it made two promises: about $1.6 million for a new 26,000-square-foot plant on vacant land in Blackthorn Commercial Park, and about $1.05 million for new equipment to go inside it.
City records show the company kept the first promise and then some. The second is still far short.
The Common Council approved a six-year real property tax abatement and a five-year personal property abatement for the company on Nov. 25, 2019, and confirmed them Dec. 9. A tax abatement phases in the taxes on new construction or equipment over several years instead of all at once.
What was promised
Toyo Seiko's petition said it would spend about $30,000 on land and $1,576,000 to build a manufacturing and distribution plant, plus $1,055,000 on equipment, $900,000 of it bought out of state. It promised to keep four full-time jobs, with an average wage of $49.03 an hour, and add one more at $21 an hour.
City staff estimated the breaks would save the company $160,658 on the building over six years and $61,052 on the equipment over five.
At the council's Nov. 25, 2019 hearing, Daniel Buckenmeyer, then the city's director of economic resources and business development, said the company had been outside city limits, that the city had worked with it for about a year to bring it in, and that it had looked at "other options such as Mexico." He said the empty site paid about $5,000 a year in taxes and that the company would pay "almost $40,000 a year" once the building's break phased out.
Larry Catanzarite, the company's general manager, told the council that Toyo Seiko makes the tiny steel balls used in shot peening, a process that strengthens metal parts for aerospace and automotive use, and that the company produces "about sixty percent (60%) of the world's production" of the material. "Our original plant was much bigger but due to some global insecurity, we've actually brought this down," he said, according to the minutes.
The building: done, then a missed form
In a June 2022 letter to the council, Catanzarite wrote that construction began in fall 2020 and the building and grounds were finished at the end of May 2021, and that spending "exceeded the abatement commitment." City abatement reports list the plant at 3585 Moreau Ct. as costing $2,101,604.
But the company did not file a required deduction form with the St. Joseph County auditor in 2021 or 2022, so it got full tax bills. The council voted June 27, 2022 to waive the lapse for both years. At a committee meeting that day, Catanzarite said he "was unaware of the filing requirements" and had missed one of three forms. Mark Bemenderfer, a city business development manager, said companies must file with three agencies and "it is not uncommon for some to be missed," and that the reminder process "could be reviewed for improvements," according to the minutes.
The city has rated the building abatement in full compliance in each of its last three annual reports.
The equipment: an extension, and a gap
The same night, the council gave the company two more years, until November 2024, to install the equipment. Catanzarite's letter blamed supply chain delays and "an unexpected but temporary drop in revenue" that "negated the need for the additional equipment," and said shipping the machines from overseas had risen from $30,000 to $200,000. At the committee meeting, the minutes record him putting the cost at $3,400 per container rising to $22,000, with 10 containers needed.
City reports since then show the equipment spending growing slowly, and the city now rates that abatement "substantially in compliance," a category that includes companies that did not meet their estimated project cost.
Source: City of South Bend Department of Community Investment abatement reports; Toyo Seiko 2019 petition
The report covering 2024, filed in June 2025, lists $280,640 against an estimate of $1,050,000. It is the latest report in the city's online records. The city's report key notes that "abatement is only applied to improvements actually built," so the company's break shrinks when it spends less.
Jobs have stayed close to the promise. The three reports list four retained and three new jobs, then three and three, then five retained and one new, against the four and one promised.
What the breaks are worth
A county list of abatements for taxes payable in 2024, filed with the council in September 2025, shows the city's share of the property taxes Toyo Seiko did not pay that year: $34,834 on the building and $1,612 on equipment. The figures cover only the city's portion of the tax rate, not the county, schools or other units. The site is in the River West TIF district, so new property taxes from the building go to that district's fund, Buckenmeyer told the council in 2019.
The building's break runs through taxes payable in 2027, and the equipment break through 2029, according to the city's reports.
Records since 2023 show the company still has room on Moreau Court. In May 2023 the Board of Public Works agreed that Toyo Seiko would not have to build a sidewalk along its property until a neighbor does, because the nearest one is about 3,000 feet away. That November, a plat redrawing two lots of the Moreau Court subdivision, listing Blackthorn Associates LLC and Toyo Seiko as owners, was recorded with the county. The records reviewed do not say what, if anything, is planned for the land.
- Bill 19-78: DCI report and petition, real and personal property abatements for Toyo Seiko North America (Nov. 18, 2019)(opens in a new tab)
- Resolution 4831-19, designating real property abatement (Nov. 25, 2019)(opens in a new tab)
- Resolution 4833-19, designating personal property abatement (Nov. 25, 2019)(opens in a new tab)
- Resolution 4832-19, confirming real property abatement (Dec. 9, 2019)(opens in a new tab)
- Resolution 4834-19, confirming personal property abatement (Dec. 9, 2019)(opens in a new tab)
- Common Council minutes, Nov. 25, 2019(opens in a new tab)
- Bill 22-29: Toyo Seiko letter of June 17, 2022 and Resolution 4964-22(opens in a new tab)
- Resolution 4964-22, modifying and reconfirming Resolution 4833-19 (June 27, 2022)(opens in a new tab)
- Resolution 4963-22, confirming real property abatement and waiving noncompliance (June 27, 2022)(opens in a new tab)
- Community Investment Committee minutes, June 27, 2022(opens in a new tab)
- 2022 Annual Tax Abatement Report (June 15, 2023)(opens in a new tab)
- Budget meeting questions answered, Department of Community Investment, with 2023 abatement report (Sept. 12, 2024)(opens in a new tab)
- 2024 Annual Tax Abatement Report (June 2025)(opens in a new tab)
- 2026 Budget Questions for City Controller (Answered), abatements 2023 pay 2024 (filed Sept. 30, 2025)(opens in a new tab)
- Sidewalk Construction Agreement, Moreau Ct., Toyo Seiko, Board of Public Works (May 9, 2023)(opens in a new tab)
- Moreau Court Minor Subdivision, First Lot Adjustment plat (recorded Nov. 21, 2023)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.