City report shows Tri-Pac spent quarter of equipment estimate

The contract manufacturer spent well beyond its estimates at a second plant on Technology Drive, and the city rates three of its four breaks fully compliant.

By South Bend Paper AI Desk · November 3, 2026 at 9:32 PM

Older records: Published November 3, 2026. The main records behind this story run through June 13, 2025.

Tri-Pac Inc., a contract manufacturer of aerosols and liquids, has received four property tax abatements from the South Bend Common Council since 2017. The city's annual abatement reports show the company spent well beyond its estimates on its second site, at 4303 Technology Drive, but put far less than projected into equipment at its first plant, on North Kenmore Street.

A tax abatement lets a company phase in property taxes on new buildings or equipment over several years. In return, the company files a Form CF-1 with the city each year reporting what it spent and how many people it employs.

The 2017 move from Michigan

On Oct. 23, 2017, the council approved a seven-year real property abatement (Resolution 4673-17) and a five-year personal property abatement on equipment (Resolution 4677-17) for 3333 N. Kenmore St. The council minutes record Dan Buckenmeyer of the Department of Community Investment calling Tri-Pac "a new entrant into South Bend" and saying the break "will aid them in funding the relocation of their business from Michigan."

Vikram Shah, the company's president, then listed in the minutes at an address in Vandalia, Mich., said Tri-Pac makes consumer products. Asked by Councilmember Oliver Davis how many jobs he would bring, he answered, "About forty (40) jobs," according to the minutes. Both resolutions passed 9-0.

At the public hearing, Sue Kesim, who lives on Kennedy Drive, spoke in opposition, raising concerns about building height near the airport, landscaping and drainage. The minutes record Councilmember Tim Scott saying her concerns went to the rezoning, not the tax abatement.

The 2020 expansion

In August 2020 Tri-Pac petitioned again, this time to buy a 40,000-square-foot building at 4303 Technology Drive. The city's staff report put the cost at $2,125,000 for the building, about $1 million in renovations and about $2 million in new equipment, for a total of about $5.1 million. The report said the company was shifting toward pharmaceutical and over-the-counter manufacturing, protective equipment and hand sanitizer, and estimated it would create 20 full-time jobs with a total annual payroll of $748,800, at an average of $18 an hour.

The council confirmed a five-year equipment abatement (Resolution 4873-20) and a seven-year real property abatement (Resolution 4875-20) on Oct. 12, 2020, both 9-0. Paras Shah, a Tri-Pac director, thanked the council and said the company looked forward to being in the city for a long time, according to the minutes.

What the reports show

The city's annual report for 2024, filed with the council June 13, 2025, compares each abatement's estimates with what the company reported:

Tri-Pac abatements: estimated vs. reported investmentNominal dollars, one-time totals, as listed in the city's 2024 Annual Tax Abatement Report
EstimatedReported actual
$0$1M$2M$3M$4M$5MKenmore St. building (2017)$1M$1.2MKenmore St. equipment (2017)$1.5M$385KTechnology Dr. building (2020)$1M$3MTechnology Dr. equipment (2020)$2M$4.5M

Source: City of South Bend 2024 Annual Tax Abatement Report

  • Kenmore Street building: estimated at $1 million; the company reported $1,187,634. The report lists 7 retained and 20 new jobs announced, and 157 retained and 7 new jobs reported. It rates this abatement fully compliant.
  • Kenmore Street equipment: estimated at $1.5 million; the company reported $384,806, about a quarter of the estimate. The report rates this abatement "substantially in compliance." Under the report's key, that rating can mean a company missed one or more goals, including its estimated project cost. The report does not say which reason applied here.
  • Technology Drive building: estimated at $1 million in improvements; the company reported $2,957,442. The report lists 144 retained jobs and 20 new jobs, the number the company had projected. Rated compliant. The abatement runs from pay year 2025 through 2031.
  • Technology Drive equipment: estimated at $2 million; the company reported $4,488,160. Rated compliant.

The jobs numbers have changed from year to year. The city's 2022 report listed 110 retained and 20 new jobs at Kenmore Street. The 2024 report lists 157 retained and 7 new. The reports do not explain the change.

The report's key also says an abatement covers only improvements that were actually made, so when a company spends less than it estimated, its tax break shrinks automatically.

Citywide, the 2024 report found 65 abatements fully compliant, 14 substantially in compliance and one noncompliant, and six personal property abatement holders did not file a CF-1.

The South Bend Paper did not interview anyone for this story. Everything here comes from the city records listed below.

What did you think of this story?

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.