Ethanol plant's 2012 shutdown left South Bend paying to pump water
City records trace flooded basements on West Calvert Street, a deal to run one plant pump and a $150,000 emergency pumping station approved in December 2013.

Four and a half feet.
That is how far the water table near West Calvert Street had dropped by March 25, 2013, five weeks after the City of South Bend reached an understanding with the liquidators of a bankrupt ethanol plant and switched one of the plant's own pumps back on. Eric Horvath, the city's director of public works, gave the figure to a Common Council committee that day. He also gave the bill: about $8,100 a month, security included, and about $2 million a year in lost sewer revenue.
The number explained what residents near the plant had learned the hard way. The New Energy Corp. plant at 3201 W. Calvert St. had been pulling "upwards of 6 million gallons of water a day" to make ethanol, the committee's May 13, 2013 minutes say, "which artificially lowered the water table." When the plant went bankrupt and stopped in late 2012, "the water table rose to its natural level, flooding basements."
"A private matter"
The council's Public Works and Property Vacation Committee, chaired by 6th District Councilman Oliver Davis, met on the problem again and again that winter. By Feb. 7, 2013, the minutes count the session at the Rum Village Nature Center as "the 6th in a series of neighborhood meetings."
That meeting is the low point in the record. Mike Schmuhl, the mayor's chief of staff, reported that the plant "was purchased at a bankruptcy auction by a liquidator firm, not one involved in the production of ethanol." Horvath said the city had found no state or federal money and "sees this as a private matter between the homeowner and their insurance company." Davis "suggested the city sink wells to pump out ground water lowering the water table." Horvath answered that "a range of approaches from filling basements with concrete to sump pumps might be more cost effective."
Then 15 residents spoke. The minutes do not name them, recording only "water in their basements, mold, mildew, constantly running sumps each pleading for help now."
The pump, then the wells
The city's position shifted within days. On Feb. 15 the mayor's office announced that "a single water pump at the former New Energy ethanol plant was turned on Friday afternoon," taking "roughly four million gallons of water out of the ground each day."
The deal behind it came before the Board of Public Works on March 26: a memorandum of understanding with South Bend Ethanol Real Estate LLC for "Limited Temporary Access, Operation, and Maintenance of Water Pump No. 4." The city would pay the electric bill, estimated at $6,400 to $8,100 a month, $1,000 a week for security and half of a $15,000 electric deposit, to help "the approximately thirty (30) homeowners with water and mold issues." Davis warned that "when the agreement expires in six (6) months ... we will be back to the same situation with flooding of the properties." The board ratified it "subject to funding."
Then came the wells. The board had already approved a $6,475 emergency hydrologic study on Feb. 5. On May 6 it approved $24,907 for Peerless Midwest Inc. to install "three (3) wells and seventy-two (72) hours pump testing for the Calvert Street/New Energy flooding area." A week later Horvath "advocated wells installed by the City to draw down water levels." Judy Fox, a Notre Dame attorney representing 55 homeowners, told the committee a proposed building-code change requiring groundwater tests "was a good first step."
By July 22 the plan had grown. "When the prospects for new ownership and resumed operation look bleak," the minutes say, "the City proposed sinking several perimeter water wells to lower the water table." Pumps "were activated with final installation scheduled for October," and the city now "intends to sink new deeper wells than the originally proposed 40 foot wells," 140 feet deep, at a cost "yet to be determined."
On Dec. 30, 2013, in a 12-minute claims meeting, the board added an item to its agenda: a $150,000 special purchase from Peerless Midwest for "Emergency Installation of a Groundwater Pumping Station to Control Basement Flooding for Former Ethanol Plant Re Activation," paid from the Loss Recovery Fund.
Source: Board of Public Works minutes, Feb. 5, May 6 and Dec. 30, 2013, via the Transparency Portal
A plant that came back
Then Noble Americas bought the plant. In February 2014, Chris Fielding of the Department of Community Investment told the Redevelopment Commission that "Mr. Horvath of Public Works is working diligently on the permanent well solution," and that "the pump that we've always had running there to address those issues will continue to run until the plant starts or the well starts." He added: "There is a permanent solution being put into place."
The department's 2014 annual report summed it up in a sentence: Public Works "was able to devise a plan to temporarily operate the pumps to reduce the water table," while the city negotiated with Noble, which "has invested $54 million to redevelop the facility." The plant has changed hands twice since, to Mercuria in 2017 and to Verbio North America in 2023.
What became of the city's wells is harder to find. The committee's 2013 annual report says "the 2014 budget has monies earmarked for a permanent solution." But no Board of Public Works or council record from 2014 on reports the permanent wells finished, says where they are, or shows them running. The city's checkbook, which goes back to 2019, holds a single line labeled "CALVERT ST WELL": $16,431.88 paid to J&K Communications Inc. on Dec. 30, 2019.
The last word in the record comes from a neighbor, at an Oct. 8, 2018 council committee hearing on annexing farmland next to the plant. Steve Matthys, who farms on Mayflower Road, told the committee: "When the Ethanol Plant shut down, the City spent, what, 150,000 to drive a few wells that aren't even being used now because the Ethanol Plant is back open." He went on: "Somehow those homes got built, the basements got flooded, the Ethanol Plant got shut down for two (2) years, the water tables rise, and then they spend a bunch of money for wells that probably should have bought the homes up."
Records do not show whether the city agrees. They show only that the plant is pumping again, and that the city once paid, by the month, to keep the water down.
More stories about Eric HorvathOliver DavisSouth Bend Board of Public Works
- Public Works & Property Vacation Committee minutes, March 25, 2013 (4.5 feet; $8,100/month; $2 million sewer revenue)(opens in a new tab)
- Public Works & Property Vacation Committee minutes, May 13, 2013 (6 million gallons; Judy Fox; Horvath on city wells)(opens in a new tab)
- Public Works and Property Vacation Committee minutes, Feb. 7, 2013 (6th meeting; liquidator; 'private matter'; 15 residents)(opens in a new tab)
- Office of the Mayor news release, 'Water Pumping at Former New Energy Site,' Feb. 15, 2013(opens in a new tab)
- Board of Public Works minutes, March 26, 2013 (MOU with South Bend Ethanol Real Estate LLC)(opens in a new tab)
- Board of Public Works agenda, March 26, 2013 (Water Pump No. 4; electric, security and deposit costs)(opens in a new tab)
- Board of Public Works claims review minutes, Feb. 5, 2013 (Peerless Midwest $6,475 hydrologic study)(opens in a new tab)
- Board of Public Works special meeting minutes, May 6, 2013 (three wells, $24,907)(opens in a new tab)
- Public Works & Property Vacation Committee minutes, July 22, 2013 (perimeter wells; 40-foot and 140-foot wells)(opens in a new tab)
- Board of Public Works claims review minutes, Dec. 30, 2013 ($150,000 emergency groundwater pumping station)(opens in a new tab)
- Board of Public Works minutes, Oct. 8, 2013 (permit transfer to Noble Americas)(opens in a new tab)
- Redevelopment Commission minutes, Feb. 13, 2014 (Fielding on 'permanent well solution')(opens in a new tab)
- 2014 Department of Community Investment Annual Report (Noble America's Ethanol Plant summary)(opens in a new tab)
- 2013 Annual Report, Public Works & Property Vacation Committee (2014 budget monies earmarked)(opens in a new tab)
- Resolution 18-67, South Bend Ethanol LLC confirming tax abatement, DCI letter Oct. 17, 2018 (Mercuria purchase, December 2017)(opens in a new tab)
- Bill No. 23-22, Verbio North America LLC real property abatement, DCI packet filed May 3, 2023 (acquisition; photo page)(opens in a new tab)
- Zoning and Annexation Committee minutes, Oct. 8, 2018 (Steve Matthys remarks)(opens in a new tab)
- City of South Bend checkbook via the Transparency Portal: J&K Communications Inc., 'CALVERT ST WELL,' Dec. 30, 2019, $16,431.88 (Public Works, fund 641)(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.