Sunday, November 29, 2026Sun, Nov 29

The South Bend Paper

Development, money and daily life in Michiana

Community

City adds $41,261 to Seitz-to-Howard riverwalk rebuild

The Nov. 24 change order covers steel, a water line, benches and anti-vandalism fencing, and brings the concrete trail contract to $5.32 million, still due May 1, 2027.

By South Bend Paper AI Desk · November 26, 2026 at 8:50 AM

The wooden boardwalk between Seitz Park and Howard Park sat on gabion baskets along the St. Joseph River, and those baskets were sinking.

That detail comes from a budget request Patrick Sherman, the city's director of project management, signed March 26, 2026. It describes the riverwalk as "a heavily used section of wooden boardwalk" whose wood and wooden supports were deteriorating with age. The sinking baskets, the request says, were creating an uneven trail surface. It also describes awkward blind corners toward Howard Park, under the Jefferson Bridge, that it says are not conducive to a safe and comfortable multi-use trail.

The replacement is a 14-foot-wide concrete multi-use trail supported by new piers. The project adds a staircase on the north side of the bridge, from the bridge surface down to the riverwalk, and replaces the concrete staircase down to Howard Park on the south side to meet current design standards.

On Nov. 24, the Board of Public Works approved the project's first change order, adding $41,261.27 to Larson-Danielson Construction Co.'s contract. That brings the LaPorte company's contract to $5,322,280.27, an increase of 0.78% over the original $5,281,019.

Most of the added cost, $30,622.84, covers steel changes and a water line. A staff memo says the steel changes account for conditions found on site after the boardwalk was demolished, and the water line had to be changed at the request of the building department.

The rest pays for smaller items. Two new park benches, requested by Venues Parks & Arts to replace existing ones, cost $6,000. Additional steel tubing on fencing panels under the bridge, added "to help prevent vandalism," according to the memo, costs $3,288.56. A small amount of added sidewalk "for better connectivity" costs $1,349.87.

The completion date does not change. Records show it remains May 1, 2027, with no time extension.

How it is paid for

The money comes from tax increment financing, or TIF, which sets aside property taxes from growth in property values inside a district for projects in that district instead of sending them to the usual taxing units. Sherman's March 26 request to the Redevelopment Commission sought $5.6 million for final design and construction: $4 million from the River East Residential TIF and $1.6 million from the River East TIF. An earlier version on the commission's March 12 agenda asked for $4 million from the River East Residential TIF alone; that version is marked tabled.

Board of Public Works minutes show bids were opened March 10, after a Feb. 24 bid-opening item was tabled. One bid was received, from Larson-Danielson, and the board awarded the contract April 14.

The engineering memo with the award says the project had goals for minority- and women-owned business participation that Larson-Danielson was unable to meet. The city's Office of Diversity and Inclusion reviewed the bid and determined the company would be granted a good-faith effort, the memo says.

The same day, the board approved $122,905 for SmithGroup Inc. for final design changes and construction administration. The requested changes included switching the main walking path to exposed aggregate and integral colored concrete, and adding a screening element below the metal stair. SmithGroup's agreement, which dates to Dec. 12, 2017, and covers the Seitz Park design as well as this phase, now totals $1,572,100.

The riverwalk is the second phase of the Seitz Park work. The board approved a completion affidavit for the first phase, Ziolkowski Construction's renovation of the park at 316 E. Colfax Ave., on Aug. 26, 2025, in the amount of $10,235,924.48.

What did you think of this story?

More stories about Howard ParkLarson-Danielson ConstructionSeitz ParkSouth Bend Board of Public WorksSouth Bend Redevelopment Commission

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.