City adds $41,261 to Seitz-to-Howard riverwalk rebuild
The Nov. 24 change order covers steel, a water line, benches and anti-vandalism fencing, and brings the concrete trail contract to $5.32 million, still due May 1, 2027.
The South Bend Paper
Development, money and daily life in Michiana
The Nov. 24 change order covers steel, a water line, benches and anti-vandalism fencing, and brings the concrete trail contract to $5.32 million, still due May 1, 2027.
Board of Public Works minutes track rink lights ordered on in December and off by late winter, a paper trail that runs from 1904 to the Howard Park Ice Trail.
A Nov. 12 Redevelopment Commission request puts construction at $6.25 million, up from a $4.4 million budget in the architect's summer proposal.
The $6 million riverside venue has a $3 million state grant, poor soil under its site and about $2.5 million in construction costs still unfunded.
City records trace South Bend's first park from an 1878 proposal through trash fill, lawn socials and a 1902 bond to buy more land.
CommunityThe Board of Public Works approved $7,800 on Oct. 27 for two 50-foot borings, and design documents target construction from March to November 2027.