City pays out full $3.8M loan as Stadium Flats still under way

Diamond View's 60 affordable apartments opened with a 200-person waitlist. The 90 market-rate units next door are still being built after a September fire.

By South Bend Paper AI Desk · November 23, 2026 at 12:54 AM

South Bend has now paid out the full $3.8 million tax increment financing loan it promised for the Diamond View and Stadium Flats apartments, city checkbook records show, while the market-rate half of the RealAmerica Development project is still under construction near Four Winds Field.

The affordable half is finished. Diamond View's 60 income-restricted apartments were fully leased by July, a city official told the Redevelopment Commission, and a ribbon cutting took place by early October. On Oct. 12, Joe Molnar, deputy director of Community Investment, cited a 200-person waitlist at Diamond View as evidence of the city's need for affordable housing, according to council committee minutes.

The 90 market-rate Stadium Flats apartments started construction this spring. A fire at the construction site in early September forced the evacuation of Diamond View residents. Commission minutes from Sept. 24 record that construction was proceeding despite the fire.

What the city put in

Since 2021 the city has backed the block bounded by Lafayette Boulevard and Main, Monroe and South streets with three kinds of help, according to city records:

Incentive Approved Amount
Land sale below appraised value July 2021 $1,000 for land appraised at $280,000
Diamond View tax abatement, 8 years 2021, revised June 2023 Estimated $199,000
Stadium Flats tax abatement, 8 years June 2023 Estimated $315,000
Forgivable TIF loan to Legacy25 Inc. February 2024 $3.8 million

The abatement estimates come from a review of city records.

The Redevelopment Commission sold the six vacant lots to RealAmerica for $1,000 in July 2021. The commission had set an offering price of $280,000 in 2016 and received no bids. The deal gave the buyer 36 months from closing to finish construction, or the city could demand the $280,000, according to the 2021 staff memo. At the time, the project was pitched as a $12 million mixed-income complex.

A project that grew and split

RealAmerica won state low-income housing tax credits in November 2022, Molnar told the commission in March 2025. By 2024 the plan had grown to three buildings: 60 affordable units and two buildings of at least 45 market-rate units each, with about $21.5 million in investment, according to the loan ordinance the Common Council passed in February 2024.

That ordinance authorized a loan of up to $3.8 million from TIF revenues to Legacy25 Inc., a nonprofit that shares the development agreement with RealAmerica, to pay for site work and infrastructure. The loan is forgiven if the representations in its loan agreement are met; if they are not, it is not forgiven.

The two halves then moved on different schedules. In February 2024 the commission split the closings. The affordable parcel transferred in 2024 and construction began that fall, Molnar said. The market-rate parcels were held up by contamination: Indiana Brownfields paid about $250,000 to dig out roughly 1,500 tons of lead-contaminated soil, more than 68 truckloads, Molnar told the commission in March 2025, when it approved a seventh amendment extending that closing to July 31, 2025. Commission minutes from June 26, 2025, said the city would close with RealAmerica the following week.

Both halves fell behind the dates in their 2023 tax filings. Each statement of benefits listed an Oct. 1, 2023, start and a March 1, 2025, finish.

Where the money went

The city paid the loan in nine installments, all recorded in the checkbook to Legacy25 Inc. under Community Investment. Three payments from July to October 2024 totaled $550,000 for Diamond View, the share the review of city records assigns to the affordable units. Six payments from February to Aug. 18, 2026, totaled $3.25 million and are labeled for Diamond View and Stadium Flats. Together they come to exactly $3.8 million.

The tax breaks carry their own clock. Both abatement resolutions say the site's designation expires Dec. 31, 2026. In its agreement for the Stadium Flats break, RealAmerica committed to build a market-rate building and create at least two full-time jobs, and the city may end the break and seek repayment of tax savings if the company falls out of compliance.

The city's 2022 abatement report listed Diamond View as "Not Started." The text of the 2024 report, filed in June 2025, does not mention the project.

The fire

The Common Council said in a Sept. 8 statement that Stadium Flats was not yet occupied and that the cause of the fire was under investigation. Police Chief Scott Ruszkowski later commended Capt. Russell Buysse for recognizing that the fire had spread to the occupied Diamond View building, according to Board of Public Safety minutes. The records reviewed show no finding on the cause.

The records reviewed also do not show a completion date for Stadium Flats or whether the city has found that the loan's conditions for forgiveness have been met. The record shows no statement from RealAmerica on the project's schedule.

What did you think of this story?

More stories about Joe MolnarRealAmerica DevelopmentRiver West Development AreaSouth Bend Common CouncilSouth Bend Redevelopment Commission

Sources
  1. Redevelopment Commission packet, July 22, 2021: Real Estate Purchase Agreement with RealAmerica Development and staff memo(opens in a new tab)
  2. Resolution 5023-23, modifying and reconfirming the Diamond View Apartments LP abatement, with Statement of Benefits (June 12, 2023)(opens in a new tab)
  3. Resolution 5036-23, confirming eight-year mixed-use abatement for RealAmerica Development (Stadium Flats), with Statement of Benefits and Memorandum of Agreement (June 26, 2023)(opens in a new tab)
  4. Ordinance 11109-24, TIF-funded forgivable loan to Legacy25 Inc. (RealAmerica project) (Feb. 12, 2024)(opens in a new tab)
  5. Redevelopment Commission minutes, March 27, 2025 (seventh amendment; brownfield cleanup)(opens in a new tab)
  6. Redevelopment Commission minutes, June 26, 2025(opens in a new tab)
  7. Redevelopment Commission minutes, April 23, 2026 (signed)(opens in a new tab)
  8. Redevelopment Commission minutes, July 23, 2026 (signed)(opens in a new tab)
  9. Redevelopment Commission minutes, Sept. 24, 2026 (signed)(opens in a new tab)
  10. Redevelopment Commission agenda and packet, Nov. 12, 2026 (Oct. 8, 2026 minutes)(opens in a new tab)
  11. Common Council Community Investment Committee minutes, Oct. 12, 2026(opens in a new tab)
  12. South Bend Common Council statement on Stadium Flats fire, Sept. 8, 2026(opens in a new tab)
  13. Board of Public Safety minutes, Oct. 21, 2026(opens in a new tab)
  14. Common Council Personnel & Finance budget meeting minutes, Sept. 9, 2026 (police and fire chiefs)(opens in a new tab)
  15. City of South Bend checkbook: payments to Legacy25 Inc., July 2024 to Aug. 18, 2026 (South Bend Transparency Portal)(opens in a new tab)
  16. Redevelopment Commission claims allowance, May 5, 2026 (Legacy25 draw 6)(opens in a new tab)
  17. City of South Bend 2022 Annual Tax Abatement Report (June 15, 2023)(opens in a new tab)
  18. City of South Bend 2024 Annual Tax Abatement Report (filed June 13, 2025)(opens in a new tab)
  19. A review of city records: Diamond View Apartments and Stadium Flats, project R0119-1 (South Bend Transparency Portal)(opens in a new tab)

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.