Row at Ward framing re-quote drops MWBE goals, draws same two firms
Borkholder Buildings & Supply cut its price to $266,314.32, below Carter Lumber's unchanged quote, for TIF-funded framing on six Portage Avenue homes.
The South Bend Paper
Development, money and daily life in Michiana
Borkholder Buildings & Supply cut its price to $266,314.32, below Carter Lumber's unchanged quote, for TIF-funded framing on six Portage Avenue homes.
The 2025 Lincoln and Kennedy Park district took four votes by three city bodies in under three months, and it collects taxes on new houses that commercial districts miss.
Diamond View's 60 affordable apartments opened with a 200-person waitlist. The 90 market-rate units next door are still being built after a September fire.
Bonds issued Oct. 1 pay for a west side trail, a Rum Village center, Drewrys site streets and a Morris garage. Officials estimated about $27 million in borrowing.
TIF money paid for roofs, masonry, fire stairs and site work at the 60-unit West Washington complex from 2019 to 2021. A window job stalled with six units unfinished.
The city split eight areas off the River West TIF this year in four votes, giving each its own tax base ahead of a new state tax deal downtown.
City payments for site work and a playground at the OneRoof center on Dubail Avenue total exactly $1.4 million. A second center is now planned in Old Marquette School.
Debt payments rise 31% to $17.3 million and infrastructure spending more than doubles, and the plan spends $2.5 million more than it expects to take in.
A $1.25 million loan for the Beacon Heights apartments shows the four votes it takes, including one by a little-known Economic Development Commission.
The Bakery Group reported $3.34 million spent on the vacant Portage Avenue landmark against $3.75 million promised, and the city paid $305,000 for its facade work.
The hotel beat its 2016 tax-break goals, but city records show the promised apartments needed a second abatement, $1.6 million in TIF and later deadlines.
The 1926 Main Street building came back with a five-year tax break, a $1 city lot and $480,000 in TIF work. City reports count 65 jobs against 32 promised.
The city has hired a concrete contractor and a plumber with TIF money for ID2 LLC's Portage Avenue homes, but framing and siding must be quoted again.
State law sets a minimum price from two appraisals and requires a public bid round. A LaPorte Avenue lot shows what happens when nobody bids.
Each year the Redevelopment Commission votes that none of its districts' added value goes back to other local governments. Douglas Road was the one exception.
A 2020 tax break for senior apartments went unused without state tax credits. The 57-unit Monreaux is now being built with up to $3.3 million in TIF loans.
The TIF-funded lot pushed the city's payments to excavator Indiana Earth to $2.9 million in 2025, up from about $497,000 the year before.