City rejects framing quotes for Row at Ward homes over MWBE goals
The city has hired a concrete contractor and a plumber with TIF money for ID2 LLC's Portage Avenue homes, but framing and siding must be quoted again.
South Bend's Board of Public Works on Oct. 27 threw out both quotes to frame, roof and fit windows and doors on six new homes in the 800 block of Portage Avenue, after the city's lawyer said neither company met the city's goals for hiring minority- and women-owned businesses.
The homes are the first phase of the Row at Ward, a private, mixed-income housing development by ID2 LLC. Under a development agreement the Redevelopment Commission approved June 11, the city pays for some of the building itself: up to $950,000 in River West Development Area tax increment financing, or TIF, money that comes from growth in property taxes inside the district. The agreement lists foundations, footings and other structural work, plus materials such as framing, windows and doors. Because public money pays for that work, the Board of Public Works buys it piece by piece through public quotes.
So far the board has awarded two contracts worth $224,228.75 and rejected two other rounds of quotes, according to board records.
| Work | Company | Amount | Board action |
|---|---|---|---|
| Excavation, foundations, footings, sidewalks | Richard Custom Concrete | $90,968.75 | Awarded Oct. 13 |
| Underground plumbing | Niezgodski Plumbing | $133,260 | Awarded Oct. 27 |
| Siding and exterior trim materials | Carter Lumber | Not stated in rejection | Rejected Oct. 13 |
| Framing, lumber, roofing, windows, exterior doors | Carter Lumber | $274,875.04 | Rejected Oct. 27 |
| Framing, lumber, roofing, windows, exterior doors | Borkholder Buildings & Supply | $299,873.61 | Rejected Oct. 27 |
Why the quotes were rejected
The city's quote packet says contractors must either meet its minority- and women-owned business goals or show good-faith efforts to do so, and that failing at both is grounds to reject a quote as non-responsive.
At the board's Oct. 22 agenda review, board member Abigail Magas asked about an engineering memo saying both framing quotes might be rejected. According to the minutes, project manager Jennifer Guard said both companies had filled out both parts of the city's MWBE checklist, saying they would meet the goals and that they would seek waivers. Board Attorney Michael Schmidt said the forms were waiting on review by the Office of Diversity and Inclusion. The minutes summarize his view that the job is hard to split up, that its small size appeals to smaller contractors who find the city's paperwork difficult, and that parts of the forms were filled out in a confusing and sometimes contradictory way. The minutes say the city was being patient because the quoters were unfamiliar with its process.
At the Oct. 27 meeting, Schmidt recommended rejecting both, saying neither company met the goals and neither gave enough evidence for a good-faith waiver. The board agreed. Letters to both companies say the work will be quoted again later. Carter Lumber's quote was the lower of the two; the city had asked a third supplier, Big C Lumber, which did not quote.
The siding quote, the only one received at a Sept. 22 opening, was rejected Oct. 13 because it did not meet the project specifications. The rejection letter says that work will go to the open market under city purchasing rules. The minutes of the Sept. 22 opening say Carter Lumber had not completed the non-collusion affidavit with that quote.
The two awards each drew a single quote. The plumbing job got no quotes on Sept. 22 and one, from Niezgodski, when it was offered again Oct. 13. The engineering memo on the concrete job said Richard Custom Concrete's quote might be rejected for an incomplete affidavit and quote form, pending legal review; the board awarded it Oct. 13.
What the homes are for
ID2 LLC, represented by member Jordan Richardson, agreed to buy seven city-owned parcels on Portage Avenue and Rex Street for $1,000 in an April 9 purchase agreement. As amended June 11, the deal calls for at least 15 housing units on 10 lots, a mix of townhomes and accessory dwelling units, with the developer spending at least $2.1 million of its own money within 24 months of closing.
At least 10 properties are to be offered for sale. At least four must go to households earning no more than 100% of the area median income, and three more to households at or below 120%. The original April agreement had required seven units priced for households at 100% of median income; the amendment changed that split.
At the June 11 meeting, Steve Smith of Irish Realty LLC told the commission the homes would sell at roughly $230,000 to $300,000, according to the minutes. Richardson said groundbreaking was expected in late 2026. The commission approved both the amendment and the development agreement unanimously.
If the developer fails to finish on time or spend its full investment, the agreement lets the city recover 150% of the TIF money it spent. The records reviewed for this story do not show when the land sale closed or when the framing work will be quoted again.
More stories about Borkholder Buildings & SupplyCarter LumberID2 LLCRiver West Development AreaRow at WardSouth Bend Board of Public WorksSouth Bend Office of Diversity and InclusionSouth Bend Redevelopment Commission
- Board of Public Works minutes, Oct. 22 agenda review and Oct. 27, 2026 regular meeting(opens in a new tab)
- Rejection of quotes, Row at Ward framing, lumber, roofing, windows and exterior doors, Project No. 126-051, with engineering memo (Oct. 27, 2026)(opens in a new tab)
- Award of quotation, Row at Ward underground plumbing, Niezgodski Plumbing (Oct. 27, 2026)(opens in a new tab)
- Board of Public Works minutes, Oct. 13, 2026(opens in a new tab)
- Award of quotation, Row at Ward excavation, foundations, footings and sidewalks, Richard Custom Concrete (Oct. 13, 2026)(opens in a new tab)
- Rejection of quote, Row at Ward siding and exterior trim materials, Carter Lumber (Oct. 13, 2026)(opens in a new tab)
- Opening of quotes, Row at Ward framing, lumber, roofing, Carter Lumber, with city quote packet and MWBE requirements (Oct. 13, 2026)(opens in a new tab)
- Board of Public Works minutes, Sept. 22, 2026(opens in a new tab)
- Development Agreement, The Row at Ward, Redevelopment Commission and ID2 LLC (approved June 11, 2026)(opens in a new tab)
- Real Estate Purchase Agreement, The Row at Ward, Redevelopment Commission and ID2 LLC (April 9, 2026)(opens in a new tab)
- First Amendment to Real Estate Purchase Agreement, The Row at Ward (June 11, 2026)(opens in a new tab)
- Redevelopment Commission minutes, June 11, 2026(opens in a new tab)
This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.
Comments
No comments yet.
Comments use your real name. To keep out fake accounts, we verify a US mobile number by text. We never show or share your number. Comment guidelines
Commenting as .
Replying to a comment.
Be civil and stay on topic. Criticism of anyone, including this paper, is welcome. Comments are reviewed before they appear. Guidelines
Comments open soon.