City's Madison Lifestyle garage contract reaches $34.9 million

The total includes $3.9 million for apartment work done for developer Great Lakes Capital, and the design contract faces an 11th amendment Tuesday.

By South Bend Paper AI Desk · November 8, 2026 at 8:48 AM

Updated November 8, 2026 at 8:49 AM: Correction: An earlier version said eleven amendments had added work to the design contract; ten have been approved, and the 11th is up Tuesday. It also placed Phase 2's building over its garage; the agreement lists them separately.

South Bend has now committed $34,927,000 to F.A. Wilhelm Construction to build the city-owned parking garage at the center of the Madison Lifestyle District downtown, plus $2,343,321 to its designer, American Structurepoint. Together that is about $37.3 million across the two contracts.

The Board of Public Works approved the last and largest piece of Wilhelm's guaranteed maximum price, $26,987,824, on Sept. 22. On Tuesday, Nov. 10, the board takes up Amendment No. 11 to Structurepoint's design contract. The amendment adds $5,000 to "reconcile the two bid packages into a single unified set of construction documents," bringing that contract to $2,348,321, according to the meeting agenda.

The money comes from River West development area bond funds, according to the contract's cover sheet.

How the price was built

A guaranteed maximum price is a cap the construction manager agrees not to exceed. Wilhelm's Aug. 18 proposal adds up three pieces the board approved one at a time:

  • $6,839,000 for early work, including foundations, site work and elevators, approved March 24
  • $1,100,176 for a change order to replace the Madison Street water main, approved April 28
  • $26,987,824 for the rest of the garage, approved Sept. 22

Wilhelm's bid recap breaks the $34.9 million down differently, by what it pays for: about $30.5 million for the garage and the podium it shares with the apartments, $521,094 for the water main and $3,909,822 for a section labeled "Multi-Family Scope Shift." That section covers exterior masonry and roofing drawn by the apartment architect, Studio M, and a fifth elevator for the apartment building.

At the board's Sept. 3 agenda review, Zach Hurst of city Engineering said $3.9 million "will be paid on behalf of development partner Great Lakes Capital at the request of Mayor Mueller," according to the minutes. The deal allows for that kind of spending: the city's June agreement with Great Lakes Capital says the city's public improvements may include "the exterior envelope of garage/multifamily structure."

The city's role in the building above the garage goes back further. A November 2024 amendment to Structurepoint's contract says it "reflects the fact the City will now construct two levels of the residential/commercial development to assist Great Lakes Capital with their building effort."

Hurst also told the board the project did not reach its goals for minority- and women-owned businesses and would seek a waiver. At the Sept. 17 agenda review, board member Murray Miller said he had seen the bid tabulation in the file and asked for the complete overall one. Hurst said that was the complete tabulation Wilhelm provided, and that an MBE waiver would be needed, according to the minutes.

The recap's budget column totals $34,266,794, which puts the final price $660,206 over it. The project manual projects substantial completion in July 2027.

The design contract

Structurepoint's contract started at $329,040 in February 2024. Ten approved amendments have added work: more schematic design, an environmental study, a traffic study, utility and water main design, design for a roundabout at Main and Marion streets, and, in December 2025, $802,895 for design development, construction documents and construction oversight. If Tuesday's 11th amendment passes, the contract will be about seven times its original amount.

Structurepoint's Madison Lifestyle design contractContract total after each approval, nominal dollars; Amendments 1-3 not shown separately
$0$500K$1M$1.5M$2M$2.5MOriginal (Feb. 2024)$329KNo. 4 (Nov. 2024)$669KNo. 5 (Jan. 2025)$729KNo. 6 (June 2025)$1.1MNo. 7 (Aug. 2025)$1.1MNo. 8 (Oct. 2025)$1.1MNo. 9 (Dec. 2025)$1.5MNo. 10 (Dec. 2025)$2.3MNo. 11 (proposed)$2.3M

Source: City of South Bend Board of Public Works agendas, minutes and contract amendments

What the developer builds

The garage is the city's share of Phase 1 under a June 25 notice-to-commence agreement between the Redevelopment Commission and Great Lakes Capital Development LLC. In it, the city agrees to build a cast-in-place garage of about 625 spaces at its own expense, deliver the site ready to build on, and keep sole responsibility for running and maintaining the garage under a parking license with a 25-year initial term.

Great Lakes Capital agrees to build an apartment building of about 190 units and a 119-room hotel with a ground-floor cafe open to the public. Both are larger than the 150 units and 105 rooms in the original 2024 plan.

Instead of a tax abatement, the city agreed to pursue about $17.99 million in bonds bought by the developer, at 7.5% interest. The bonds would be repaid only from the project's own taxes: 90% of its property tax increment, plus non-construction sales, income and employment taxes collected under the downtown Innovation Development District. The agreement says the bonds are not general obligations of the city. The city also agreed to pass through construction sales tax from the project, estimated at $1,611,704. Both need approval from the Indiana Economic Development Corporation. In exchange, Great Lakes Capital agreed to go ahead at a 7.5% return on cost, down from the 8% target in the original agreement.

Phase 2 has not been agreed to. The agreement describes it as a building of about 90 apartments, including workforce housing, with at least 7,000 square feet of retail, plus a second city garage of about 300 spaces. If the two sides don't sign a Phase 2 notice by Oct. 31, 2027, the developer must hand that land back to the commission if it asks.

The Board of Public Works meets at 9:30 a.m. Tuesday in the Council Chambers on the third floor of the County-City Building.

What did you think of this story?

More stories about American StructurepointF.A. Wilhelm ConstructionGreat Lakes CapitalMadison Lifestyle DistrictSouth Bend Board of Public Works

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.