How South Bend builds big projects under a guaranteed price cap

For Four Winds Field and a new downtown garage, the city picked builders by scoring proposals, not by low bid, then capped the price once trade work was bid.

By South Bend Paper AI Desk · November 4, 2026 at 8:18 PM

Most South Bend construction contracts go to the lowest responsible bidder. For some of its biggest recent projects, though, the city has used another method. It's called "construction manager as constructor," or CMc.

The $45 million renovation and expansion of Four Winds Field was built this way. So is the city's new parking garage in the Madison Lifestyle District. Here's how the process works, based on Board of Public Works records.

Step 1: Pick the builder by proposal, not by price

The city asks construction firms for proposals, and a scoring committee ranks them. For the Madison Lifestyle District garage, five firms applied: CRG Residential, CSM Group, F.A. Wilhelm, Garmong and Shiel-Sexton. Staff interviewed three of them, and the committee recommended F.A. Wilhelm.

In a Feb. 4, 2025 memo, Senior Project Engineer Zach Hurst asked the Board of Public Works to approve the top-scoring firm "in accordance with IC 5-32-4-1," the section of Indiana law he cited, so staff could start negotiating a contract. The board agreed on Feb. 11, 2025. Its letters to the other four firms say that if no deal is reached, "the award will go to the next highest scoring vendor."

The memo describes a garage of seven levels with at least 600 spaces, on the block bounded by Main, Madison and Michigan streets. The city's part of the project has a $20 million budget, paid from the River West TIF district. TIF, or tax increment financing, sets aside new property taxes in a district to pay for projects there.

Step 2: The builder helps with design

A CMc firm is hired while the project is still being designed. That's the main difference from a standard bid, where a contractor prices a finished set of plans.

For Four Winds Field, the board approved a professional services agreement with Larson-Danielson Construction Co. of LaPorte on Nov. 14, 2023.

Step 3: The builder bids out the trade work in public

The construction manager then splits the job into packages and bids them out to subcontractors such as steel, electrical and concrete firms. In May 2024, Project Manager Patrick Sherman told the board that each Four Winds bid opening would be an open public meeting. The minutes record him saying, "We are relying on the CMC to advertise and to notify the media about the meetings."

Step 4: Agree on a guaranteed maximum price

Once the bids are in, the builder and the city sign a guaranteed maximum price, or GMP. The Four Winds amendment defines it as "an amount that the Contract Sum shall not exceed," covering the builder's fee plus the cost of the work, "subject to additions and deductions by Change Order."

A big job can be approved in pieces so work can start sooner. According to board minutes, Four Winds came in three phases:

  • Phase one, approved July 23, 2024, for $11,196,499. It covered demolition and steel for the second deck so the stadium could open on schedule in April.
  • Phase two, approved Aug. 13, 2024, for $4,069,545. It covered a new splash pad, kids' zone, restroom and decking.
  • Phase three, approved Jan. 14, 2025, for $28,236,556. This was the remaining work, including a four-story events building in left field. It brought the guaranteed maximum price to $43,489,593.

When some early trade bids came in "insignificantly over" what the city expected, Sherman told the board, the city rejected those packages and rebid them. "We rescoped a lot of the HVAC and some of the electrical," he said, according to the minutes, and the rebid came in within budget.

Sherman also told the board the price includes a contingency, money set aside for surprises, of 1%, compared with 4% on the city's MLK project. The minutes quote him saying that is "reflective of the fact that we got the contractor on so much earlier in the process."

Step 5: Changes still go back to the board

A guaranteed maximum price can still change, but only by a change order the board approves. On Aug. 25, 2026, the board added $1,566,567.78 to the Four Winds contract for a third-floor office build-out in the events building, a concourse coating to stop leaks and three canopies. The contract total is now $45,132,658.78. A memo from Sherman says the money came from "project budget savings and bond interest dollars" and that this "is expected to be the only change order on the project."

What to watch

CMc decisions appear on Board of Public Works agendas as proposal openings, proposal awards, GMP amendments and change orders. The board meets in public, and its documents are posted on the city's website.

What did you think of this story?

More stories about F.A. Wilhelm ConstructionFour Winds FieldLarson-Danielson ConstructionMadison Lifestyle DistrictSouth Bend Board of Public Works

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.