City to award $1.47 million for LaSalle storm sewer outfall

Selge Construction's contract for work at Gwen Stiver Park is the first phase of separating storm water from combined sewers under LaSalle Avenue.

By South Bend Paper AI Desk · November 8, 2026 at 9:48 AM
The title sheet for Phase 1 of the LaSalle Avenue sewer separation project, approved by the Board of Public Works on Sept. 22, 2026. City of South Bend records

South Bend's Board of Public Works is set Tuesday to award Selge Construction Co. a $1,471,719.50 contract to rebuild a storm sewer outfall on the St. Joseph River at Gwen Stiver Park, the first construction phase of a plan to separate storm water from the combined sewers under LaSalle Avenue downtown.

The award is on the board's Nov. 10 agenda, for its 9:30 a.m. meeting in the third-floor Council Chambers at 215 S. Dr. Martin Luther King Jr. Blvd.

What the project does

In a combined sewer, rain runoff and household sewage share the same pipes. South Bend "owns and operates a combined sewer system," the U.S. Environmental Protection Agency says in its summary of the city's federal consent decree, and before that settlement the city discharged "over 2 billion gallons of untreated sewage during approximately 80 events" a year into the river.

The LaSalle project would give storm water its own route to the river. The city's 2025 agreement with McCormick Engineering describes the goal as "separation of combined sewer systems to provide conveyance of stormwater discharges to the St. Joseph River," with a separate storm sewer running from the intersection of Lafayette Boulevard and LaSalle Avenue to an existing 78-inch outfall pipe. The new sewer is to be sized for a 10-year storm, the agreement says.

City records do not say how much combined-sewer overflow the project is expected to prevent.

Phase 1: the river end

Phase 1 is the outfall in Gwen Stiver Park. Because the project would send more water to an existing permitted outfall, McCormick proposed a drop structure with a grated energy dissipator "to help reduce velocities at the pipe outfall," according to a structural engineering proposal in the design amendment. That proposal put the structure at about 24 feet long, 12 feet wide and 25 feet deep. A geotechnical proposal in the same file describes a new energy dissipation vault and a new 78-inch outfall pipe. The plans also include a lighting plan for a park light pole the work is expected to affect.

The board approved advertising for bids on Sept. 22 and opened them Oct. 27. Three firms submitted bids, city records show: Selge, C&E Excavating Inc. of Elkhart and HRP Construction. C&E's bid form shows a total of $3,484,695, more than twice the amount of the contract the board is set to award Selge. HRP's bid amount could not be read in the copy posted by the city. Records reviewed do not include an engineer's cost estimate.

Design costs and what comes next

The board hired McCormick Engineering in November 2025 for $123,000 in preliminary design. In May it approved a $350,320 amendment for final design, bringing the contract to $473,320. The amendment splits the work into two bid packages: the Gwen Stiver Park outfall and a LaSalle Avenue sewer phase, which includes traffic signal work at LaSalle's intersections with Main Street and Martin Luther King Jr. Boulevard.

The records reviewed do not include a construction estimate for the LaSalle Avenue phase or a date for bidding it.

What did you think of this story?

More stories about Selge ConstructionSouth Bend Board of Public Works

Comments

No comments yet.

This story was written with AI from the sources above. See something wrong? Tell us and we will correct it.