South Bend rejects pump station bids that ran over budget
Both bids to replace pumps at a station serving New Carlisle and the Indiana Enterprise Center topped the engineer's estimate. New bids open Dec. 8.
The South Bend Paper
Development, money and daily life in Michiana
Both bids to replace pumps at a station serving New Carlisle and the Indiana Enterprise Center topped the engineer's estimate. New bids open Dec. 8.
DevelopmentSelge Construction's contract for work at Gwen Stiver Park is the first phase of separating storm water from combined sewers under LaSalle Avenue.
City checkbook records show Selge Construction was paid $4.16 million in 2025, and more than half went to a TIF-funded Wall Street rebuild.
State law caps added work at 20% of the original price, and the Wall Street rebuild shows how two change orders raised, then trimmed, a $2.6 million contract.